Sharp v. Johnson Bros.

917 F.2d 885, 1990 WL 169328
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 21, 1990
DocketNo. 89-3764
StatusPublished
Cited by1 cases

This text of 917 F.2d 885 (Sharp v. Johnson Bros.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sharp v. Johnson Bros., 917 F.2d 885, 1990 WL 169328 (5th Cir. 1990).

Opinion

W. EUGENE DAVIS, Circuit Judge:

Plaintiff Ernest D. Sharp appeals a directed verdict for Defendant Johnson Brothers Corporation (Johnson) rejecting Sharp’s suit on the ground that he was not a seaman. 719 F.Supp. 516. Additionally, Johnson, Wausau Insurance Companies (Wausau), and St. Paul Fire & Marine Insurance Company (St. Paul) appeal a summary judgment granted to Centennial Insurance Company (Centennial) exonerating Centennial from paying Johnson’s litigation costs. We reverse both rulings and remand for further proceedings.

I.

Johnson is a heavy construction company specializing in bridge and dock building. During the fall of 1985, Johnson began rebuilding Southern Railroad Company’s train bridge which spans Lake Pontehartrain. The project required Johnson to drive piles for the erection of piers to support the new bridge. Johnson bareboat chartered a group of vessels to assist in the project — the tug M/V FERDIE CANDIES and four deck barges, the CMS-206, JG-204, CMS-424, and CMS-575. Johnson installed cranes on the two spud barges, CMS-206 and JG-204. The company used [887]*887the CMS-206 for pile driving and the JG-204 for moving, digging, loading, and unloading. The CMS-424 and the CMS-575 barges were ordinary flat deck barges. Workers used these two barges for transporting and storing materials and as work areas during pile-driving operations.

Johnson hired Sharp in June 1985 as a welder/pile driver on the Pontchartrain project. Sharp was the leaderman of the pile-driving crew. Johnson is, however, a non-union employer which has no formal job classes; each of its workers performed a variety of tasks. Sharp lived ashore. Johnson transported its workers to and from the jobsite each day by boat.

During the first six months of the bridge project, most of the work involved pile-driving operations. Workers frequently moved the barges around the jobsite throughout the day. After the crew finished driving a piling, the M/V FERDIE CANDIES moved the flotilla of barges to the position of the next piling. At least once and sometimes twice a week early in the project, the pile-driving crew accompanied the M/V FER-DIE GANDIES, crane barge JG-204, and one of the material barges on a five-mile round trip across a portion of Lake Pontchartrain. On these trips, the crew transported equipment and supplies to the job-site. Whenever a hurricane threatened, which occurred four times in 1985, the crew moved the entire flotilla out of the Lake to a safe harbor on Bayou Liberty.

One day in late November 1985, the pile-driving crew took the M/V FERDIE CANDIES to the east side of the trestle to retrieve some materials located aboard the JG-204. The crew used the crane mounted on the JG-204 to transfer angle iron from the barge to the tug. Sharp, meanwhile, loaded small tools onto the tug. During this operation, the crane dropped a load of the angle iron on Sharp, who was standing on the bow of the M/V FERDIE CANDIES. This litigation followed.

When Johnson bareboat chartered the JG-204 from Central Marine Service (Central), Central’s insurer, Centennial, designated Johnson as an additional insured in the barge’s protection and indemnity policy. Johnson acquired excess coverage on the M/V FERDIE CANDIES and the JG-204 from St. Paul. When Sharp filed suit, Johnson called upon Centennial to provide a defense. Centennial refused. St. Paul then agreed to defend Johnson as the excess insurer with the understanding that St. Paul would seek reimbursement from the primary insurer, Centennial. St. Paul asserted a cross-claim against Centennial to recover Johnson’s defense costs.

The trial court severed the seaman status issue from the remaining issues in the ease. After three days of testimony, the court granted the defendants’ motions for a directed verdict on grounds that the evidence was insufficient to support a finding that Sharp was a seaman. The court concluded that the evidence would not support a finding that the barges were vessels because their use in transportation was merely incidental to their primary use as work platforms. In any case, reasoned the court, Sharp was a Pizzitolo2 longshoreman and therefore could not bring a Jones Act claim. Sharp argues on appeal that the barges’ transportation function was not merely incidental and that Pizzitolo does not apply.

The trial court also granted Centennial’s summary judgment motion. The court concluded that Centennial did not owe Johnson or St. Paul reimbursement for defense costs. The court reasoned that Johnson did not incur defense expenses because St. Paul paid for Johnson’s defense. Johnson and St. Paul argue on appeal that Centennial owes St. Paul for the defense costs as Johnson’s subrogee.

II.

To qualify as a seaman under the Jones Act, an injured maritime worker must establish that he was permanently assigned to or performed a substantial por[888]*888tion of his work aboard a vessel or fleet of vessels. Barrett v. Chevron, U.S.A., Inc., 781 F.2d 1067, 1074 (5th Cir.1986); Offshore Co. v. Robison, 266 F.2d 769, 779 (5th Cir.1959). The district court concluded that none of the barges on which Sharp worked were vessels; thus, a reasonable juror could not find that Sharp was a seaman.

Our cases illustrate clearly “that the question of seaman status should only be removed from the trier of fact (by summary judgment or directed verdict) in rare circumstances and that even marginal Jones Act claims should be submitted to the jury.” Bernard v. Binnings Constr. Co., 741 F.2d 824, 827 (5th Cir.1984). The trial court should direct a verdict only “if the facts and inferences point so strongly and overwhelmingly, in favor of one party that the court believes that reasonable men could not arrive at a contrary verdict.” Boeing Co. v. Shipman, 411 F.2d 365, 374 (5th Cir.1969). We must decide whether the district court properly concluded from the evidence presented that the barges to which Sharp was assigned were, as a matter of law, work platforms and not vessels.

We have held consistently “that dry docks and analogous structures whose primary purpose is to provide a work platform, even if the structures are afloat, are not Jones Act vessels as a matter of law.” Bernard, 741 F.2d at 830. In determining whether a structure is a “work platform,” we consider whether:

1) The structures involved were constructed and used primarily as work platforms;
2) They were moored or otherwise secured at the time of the accident; and
3) Although they were capable of moving and were sometimes moved across navigable waters in the course of normal operations, any transportation function they performed was merely incidental to their primary purpose of serving as work platforms.

See id. at 831; cf. Ducrepont v. Baton Rouge Marine Enters., 877 F.2d 393 (5th Cir.1989) (Bernard

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
917 F.2d 885, 1990 WL 169328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sharp-v-johnson-bros-ca5-1990.