Sharon Morgan v. The City of Norfolk

Court of Appeals of Virginia·Decided January 20, 2026·No. 0350251·Published

Opinion

COURT OF APPEALS OF VIRGINIA

Present: Chief Judge Decker, Judge AtLee and Senior Judge Humphreys PUBLISHED

Argued at Williamsburg, Virginia

SHARON MORGAN

OPINION BY

v. Record No. 0350-25-1 JUDGE ROBERT J. HUMPHREYS JANUARY 20, 2026

THE CITY OF NORFOLK

FROM THE CIRCUIT COURT OF THE CITY OF NORFOLK Everett A. Martin, Jr., Judge

Norman A. Thomas (Joseph T. Waldo; Brian G. Kunze; Blake A.

Willis; Norman A. Thomas, PLLC; Waldo & Lyle, P.C., on briefs), for appellant.

Kristopher R. McClellan (Adam D. Melita; City Attorney’s Office, on brief), for appellee.

This appeal arises from an inverse condemnation action brought by Sharon Morgan against the City of Norfolk (“the City”). In her complaint, Morgan alleged that the City damaged her house during the construction of Bruce’s Park Pump Station #152 (the “Project”). The Project was a multi-phase replacement and construction of the water and sewer infrastructure. After a motion in limine, the Circuit Court of the City of Norfolk granted the City’s motion to preclude Morgan from introducing evidence of damages from Phases I and II of the Project. Then, after a bench trial, the circuit court dismissed in part and granted in part the petition for declaratory judgment. The circuit court determined that the City did not take Morgan’s property, except for a 15 square foot temporary easement for 6 months to construct an asphalt pathway. Following this ruling, the parties

stipulated that Morgan was entitled to a $6.10 award for the City’s taking.1 After a final hearing, the circuit court awarded Morgan $29,828 in attorney fees and costs.

Morgan contends the circuit court erred by: (1) granting the City’s motion in limine on the statute of limitations; (2) granting the City’s motion to strike and finding that the City’s only taking was the 15 square foot temporary easement; (3) limiting Gruelle’s testimony for the just compensation trial; and (4) awarding $29,828 in attorney fees and costs.

BACKGROUND

Morgan is the owner of a house in Norfolk, Virginia (the “Property”) that is situated close to where the Project took place. Phase I of the Project occurred from 2015 to 2016 and included the construction of the pump station. Phase II took place from 2015 to February 2017 and consisted of construction and replacement of water and sewer pipes connected to the pump station. Phase IIIA occurred from August 2020 to January 2022 and included the replacement of water and sewer pipes “directly adjacent to the Property.”

On April 26, 2016, Morgan wrote a letter to the City complaining of “paint chipping,”

“cracks” in her wall, and a “broke[n] natural gas line in two different spots” due to the City’s work on the Project. Specifically, Morgan stated that the damage was from “the banging of huge metal plates into the ground” that “literally shake [her] entire house.” In her letter, Morgan stated that she noticed the cracking in February 2016. The City responded to Morgan’s letter, and, after an investigation, denied liability for her damages.

On February 2, 2021, Morgan filed a petition for declaratory judgment against the City but thereafter nonsuited the case on June 1, 2022. Then, on June 16, 2022, Morgan filed a new petition

1 Prior to this stipulation, the circuit court granted the City’s motion in limine to limit Morgan’s expert witness testimony to the fair market rental value of the 15 square foot temporary taking and exclude the expert’s “other theories and opinions of damages.” Morgan preserved her objection to the ruling on just compensation in the stipulation order.

for declaratory judgment alleging that the City had damaged her Property, without payment of just compensation, in violation of Article I, Section 11 of the Constitution of Virginia.

In July 2023, the City filed a motion in limine to exclude evidence of the City’s actions and evidence of causation of damages to the Property prior to February 2, 2018.2 The City argued that the statute of limitations precluded Morgan from introducing evidence of the City’s actions or of damages to the Property that occurred more than three years before the filing of her initial petition. As such, the City argued that Morgan was limited to damages sustained during Phase IIIA of the Project, because Phase II ended in February 2017 and no additional work was done until the start of Phase IIIA in August 2020. On August 7, 2023, the circuit court heard the City’s motion in limine and entered an order granting the City’s motion to exclude evidence of damages to the Property prior to February 2, 2018.

In August 2023, after a bench trial on Morgan’s petition for declaratory judgment, the circuit court entered an order granting the petition in part and dismissing in part. The circuit court found that the City had “taken, for a period of approximately six (6) months, a temporary easement to construct an asphalt pathway located in the front left corner of [Morgan’s] Property without just compensation.” The circuit court dismissed the portions of the petition regarding Morgan’s allegations that the City had “taken and/or damaged [Morgan’s] [P]roperty by causing vibrations and concussions to physically enter and shake the Property” because some of the damages alleged occurred outside of the statute of limitations period, and, as to the other damages, Morgan failed to prove the City’s actions caused them.

Before a jury trial regarding the amount of just compensation owed by the City, the circuit court held a hearing on the City’s motion in limine to limit Morgan’s expert witness’s testimony.

2 Pursuant to Code § 8.01-229(E)(3), the statute of limitations period is calculated based off the filing date of her initial, nonsuited petition, which was February 2, 2021.

Morgan sought to introduce evidence that because the Project “made the whole Property unrentable” she was entitled to just compensation based on the entire Project. Dennis Gruelle, Morgan’s expert, stated that he was looking “at the effect on the whole property” and that “construction and the closing of the road” would prohibit her from renting her Property “during the duration of the [P]roject.” Gruelle’s calculations for just compensation included “renting the entire property.” The circuit court found that Gruelle’s testimony went beyond its factual finding at the liability trial and granted the City’s motion limiting his testimony.

Finally, the circuit court held a hearing on Morgan’s motion for reimbursement of fees and costs pursuant to Code § 25.1-420.3 Morgan sought $119,856.67 in attorney fees and costs. After the hearing, the circuit court entered an order awarding Morgan $29,828 in attorney fees and costs. Morgan appeals.

ANALYSIS

I. Whether a portion of Morgan’s inverse condemnation claim was time barred Morgan argues that the stabilization doctrine, as articulated in United States v. Dickinson, 331 U.S. 745 (1947), extended the accrual date of her cause of action until the Project ended in January 2022.

3 Code § 25.1-420 states:

If a declaratory judgment proceeding is instituted pursuant to § 8.01-187 by the owner of any . . . real property because of use of his property in any program or project undertaken by a state agency, and . . . the court renders a judgment for the plaintiff in such proceeding and awards compensation for the damaging or taking of property . . . the court . . . shall determine and award . . . plaintiff, as a part of such judgment or settlement, such sum as will, in the opinion of the court, . . . reimburse such plaintiff for his reasonable costs, disbursements and expenses, including reasonable attorney, appraisal and engineering fees, actually incurred because of such proceeding.

“[T]he date of accrual of . . . [a] cause[] of action is a mixed question of law and fact that this Court reviews de novo.” Commonwealth ex rel. Fair Hous. Bd. v. Windsor Plaza Condo. Ass’n., 289 Va. 34, 58 (2014).

Free access — add to your briefcase to read the full text and ask questions with AI

Sharon Morgan v. The City of Norfolk, (Va. Ct. App. 2026).

Sharon Morgan v. The City of Norfolk (Sharon Morgan v. The City of Norfolk) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Dickinson
331 U.S. 745 (Supreme Court, 1947)
Dean v. COUNTY SUP'RS OF PRINCE WILLIAM
708 S.E.2d 830 (Supreme Court of Virginia, 2011)
Avent v. Com.
688 S.E.2d 244 (Supreme Court of Virginia, 2010)
Bethel Inv. Co. v. City of Hampton
636 S.E.2d 466 (Supreme Court of Virginia, 2006)
Richmeade, L.P. v. City of Richmond
594 S.E.2d 606 (Supreme Court of Virginia, 2004)
Jenkins v. County of Shenandoah
436 S.E.2d 607 (Supreme Court of Virginia, 1993)
Lambert v. Sea Oats Condo. Ass'n, Inc.
798 S.E.2d 177 (Supreme Court of Virginia, 2017)
AGCS Marine Ins. Co. v. Arlington Cnty.
800 S.E.2d 159 (Supreme Court of Virginia, 2017)
Nelson County v. Coleman
101 S.E. 413 (Supreme Court of Virginia, 1919)
Bly v. Southern Railway Co.
31 S.E.2d 564 (Supreme Court of Virginia, 1944)
Anderson v. Chesapeake Ferry Co.
43 S.E.2d 10 (Supreme Court of Virginia, 1947)
Etchegoinberry v. United States
132 F.4th 1374 (Federal Circuit, 2025)