SHANKS v. Fisher

130 N.E.2d 231, 126 Ind. App. 402, 1955 Ind. App. LEXIS 207
CourtIndiana Court of Appeals
DecidedDecember 2, 1955
Docket18,521
StatusPublished
Cited by9 cases

This text of 130 N.E.2d 231 (SHANKS v. Fisher) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SHANKS v. Fisher, 130 N.E.2d 231, 126 Ind. App. 402, 1955 Ind. App. LEXIS 207 (Ind. Ct. App. 1955).

Opinion

Kelley, J.

Prior to the rendition of the original opinion in this cause (which said opinion appears in 130 N. E. 2d at page 231), by writ of certiorari, the record of the trial court’s finding No. 6, referred to in said opinion, as the same was certified to by the Clerk of the trial court, was corrected nunc pro tunc. Such correction was not called to our attention and we were unaware thereof until the filing herein of appellee’s petition for a rehearing. It appears that such correction requires changes in certain of the figures and wording of said opinion but does not alter the conclusion therein arrived at.

IT IS THEREFORE ORDERED, that the original opinion rendered by this court, be and the same is hereby withdrawn and on the petition for rehearing the following opinion is now substituted therefor, to-wit:

*404 Appellee commenced this action by filing a complaint, afterward amended, in which amended complaint he alleged, in substance, that on May 9, 1950, appellee and appellants entered into a certain written contract by the terms of which appellee agreed to erect for appellants a dwelling house on certain described real estate owned by them at a total cost not to exceed the sum of $42,000.00; that thereafter on or about November 1, 1950, the parties entered into ¿ supplemental parol agreement whereby appellants agreed to pay appellee for additional cost of construction and would likewise pay for extra construction and equipment not provided for in said written agreement upon the submission to them by appellee of an itemized statement thereof; that áppellee, pursuant to said written and supplemental parol contracts, furnished all the material and labor in the construction of said building which was completed on August 1, 1951; that appellee had done and performed all the conditions of said contract and supplemental parol agreement on his part to be performed and did at all times submit to appellants itemized statements of labor and material, which said statements were approved by appellants; that appellants had paid the sum of $52,000.00 and appellee had demanded of them the payment of the balance due him in the alleged sum of $18,669.62 which appellants failed and refused to pay. The amended complaint further alleged the filing by appellee on August 31, 1951, of a notice of his intention to hold a mechanic’s lien on appellants’ real estate and the recording of the same. Prayer of the complaint was for judgment against appellants for $25,000.00 and that the mechanic’s lien be foreclosed with attorney fees and all other proper relief.

Appellants answered the amended complaint by denial and by admission of the execution by them of the writ *405 ten contract and the filing and recording of appellee’s mechanic’s lien notice but that the notice was ineffective in that the amount claimed therein was for a builder’s commission to which appellee was not entitled. The answer further asserted that appellee was indebted to appellants in the approximate amount of $20,000.00, that appellee was not entitled to anything under “the pleading”, and not entitled to a foreclosure of the mechanic’s lien.

In addition, appellants filed what they term a “cross-complaint” in two paragraphs. The first paragraph alleged that appellee was indebted to them in the sum of $19,885.94 for money had and received, together with interest thereon. The second paragraph alleged the making of the written contract alleged in appellee’s amended complaint and that appellee agreed therein that the total cost of the construction of such building, including material, labor, and builder’s percentage, should not exceed the sum of $42,000.00; that when the aggregated amounts paid out by appellants had reached the sum of $42,000.00, the appellee had not performed said contract and that the building and improvements had not been made according to the specifications; that appellants loaned to appellee the sum of $10,000.00 which sum was in addition to the cost limitation provided in said contract; that appellee had refused and failed to pay for labor and material in building said house and mechanic’s liens were filed against appellants’ property, which appellants were compelled to pay in addition to said loan to appellee, that upon such accounts the appellee became indebted to appellants in the sum of $19,885.94; that appellants made written demand upon appellee to carry out said contract and discharge said indebtedness; wherefore appellants prayed judgment against appellee for $25,- *406 000.00. Appellee filed answer in denial of the allegations of said cross-complaint.

The issues so joined were submitted for trial to the court, without jury. The court made and entered special findings of fact and conclusions of law pursuant to the request of appellants therefor. This appeal is from the judgment for appellee hereinafter referred to.

The court made thirteen findings of fact and stated three conclusions of law. The findings, in substance, are as follows:

(1) . That on May 9, 1950 the appellants were and ever since have been the owners, as tenants by, the entireties, of the described real estate (on which the house was built).
(2) . That on May 9, 1950, the appellee and appellant, Ray W. Shank, “in behalf of himself and wife”, entered into a written contract . . . A copy of the written contract is then set forth verbatim.
(3) . That thereafter appellee began construction of the building and continued such construction from that time until the dwelling was completed.
(4) . That on or about November 1, 1950, appellee informed appellants that due to unforeseen price increases on material and on account of extra construction and equipment not provided for in said contract, the cost of the construction of the said dwelling would be greater, whereupon said appellants directed appellee to continue said construction, to submit current statements of the cost of labor and material and that they would pay the same.
(5) . That during the period of construction, the appellants paid the appellee the following amounts: (Here follows a schedule of payments totalling $52,895.25.)
(6) . That the total cost of said dwelling and other work and labor performed and mate *407 rials furnished by appellee was $67,836.87 and that appellee is entitled to recover an additional 5% as a contractor’s fee which sum amounts to $3,391.34, making a total cost of $71,228.71.
(7) . That in the course of said construction, appellee incurred indebtedness for material and labor used in the premises in the sum of $9,885.94, $8,885.94 has been paid by appellants and $1,000.00 of which amount appellants are entitled to credit.
(8) . That the extra charges and items of material and labor furnished by appellee at the instance and request of appellants which were not included in the written contract and blueprints and for which appellee is entitled to charge appellants, are as follows: (Here follows an itemized list of 103 of the various items and the allowances made therefor by the court totalling $19,127.45).
(9) .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archem, Inc. v. Simo
549 N.E.2d 1054 (Indiana Court of Appeals, 1990)
Captain & Co., Inc. v. Stenberg
505 N.E.2d 88 (Indiana Court of Appeals, 1987)
Leatherman v. Management Advisors, Inc.
448 N.E.2d 1048 (Indiana Supreme Court, 1983)
Woodward Insurance, Inc. v. White
437 N.E.2d 59 (Indiana Supreme Court, 1982)
Spickelmier Industries, Inc. v. Passander
359 N.E.2d 563 (Indiana Court of Appeals, 1977)
Myers v. Maris
326 N.E.2d 577 (Indiana Court of Appeals, 1975)
Seastrom, Inc. v. Amick Construction Co., Inc.
315 N.E.2d 431 (Indiana Court of Appeals, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.E.2d 231, 126 Ind. App. 402, 1955 Ind. App. LEXIS 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shanks-v-fisher-indctapp-1955.