Shamokin Area School Authority v. Farfield Co.

454 A.2d 126, 308 Pa. Super. 271, 1982 Pa. Super. LEXIS 6021
CourtSuperior Court of Pennsylvania
DecidedDecember 23, 1982
Docket1141 and 2252
StatusPublished
Cited by6 cases

This text of 454 A.2d 126 (Shamokin Area School Authority v. Farfield Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shamokin Area School Authority v. Farfield Co., 454 A.2d 126, 308 Pa. Super. 271, 1982 Pa. Super. LEXIS 6021 (Pa. Ct. App. 1982).

Opinion

WATKINS, Judge:

This case concerns an appeal from the Court of Common Pleas of Northumberland County which held that the Shamokin Area School District Authority’s obligation to arbitrate disputes arising out of the construction contract ended with the completion of the work; that the defendant-appellant The Farfield Company (Jaden Electric Division) did not demand arbitration prior to the completion of the work; and that the contract between Jaden and the school district as to whether the request for arbitration was timely made was to be decided by the Court of Common Pleas and not by the Board of Arbitrators.

We agree that the final decree of the court below which confirmed the Decree Nisi in all respects must be reversed with instructions that the petition of Jaden to compel arbitration and stay the action in equity pending arbitration and that the injunction granted to the school district enjoining *273 arbitration be vacated, in that the decisions made by the court below were errors of law.

The appellee authority of the school district commenced an action in equity seeking to enjoin an arbitration proceeding filed with the American Arbitration Association by the Jaden Electric Division of the Farfield Company. Jaden was the electrical contractor under contract with the Authority for the construction of the Shamokin Elementary School.

Concurrent with the filing of the suit, Jaden petitioned to compel arbitration and stay the equity suit pending the outcome of arbitration.

Jaden contends that the Court of Common Pleas erred as a matter of law in (1) holding that the Authority obligation was effective only during the course of construction; (2) concluding that the work was completed; and (3) rejecting Jaden’s contention that the issue of the timeliness of its demand for arbitration was a question for the arbitrators rather than the court.

The applicable provisions of the contract concerning arbitration are as follows:

“7.10.1 All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, except as set forth in Subparagraph 2.2.9 with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payments as provided by Subparagraphs 9.7.5 and 9.7.6, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof
*274 “7.10.2 Notice of the demand for arbitration shall be filed in writing with the other party to the Contract and with the American Arbitration Association, and a copy shall be filed with the Architect. The demand for arbitration shall be made within the time limits specified in Subparagraphs 2.2.10 and 2.2.11 where applicable, and in all other cases within a reasonablé time after the claim, dispute or other matter in question has arisen, and in no event shall it be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations.
“7.10.3 The Contractor shall carry on the Work and maintain the progress schedule during any arbitration proceedings, unless otherwise agreed by him and the Owner in writing.”

It was apparent that the electrical work was not entirely completed because the court below in its opinion stated that the work still to be done would take no more than one day. One day or not, this clearly indicates that the work was not completed. It was also clear from the evidence that the work to be done was not due to the fault of Jaden because of necessary preliminary work.

As to timeliness of Jaden’s demand for arbitration, the Supreme Court of Pennsylvania has made it clear that where, as here, the parties have agreed to arbitrate all issues arising from the contractual relationship, procedural questions such as timeliness are reserved for the arbitrators. Kardon v. Portare, 466 Pa. 306, 353 A.2d 368 (1976); Muhlenberg Township School District Authority v. Pennsylvania Fortunato Construction Co., 460 Pa. 260, 333 A.2d 184 (1975). See School District of The City of Duquesne v. Duquesne Education Association, 475 Pa. 279, 380 A.2d 353 (1977); Shaler Area Education Association v. Shaler Area School District, 61 Pa.Comm.Ct. 211, 433 A.2d 168 (1981); Pennsylvania Labor Relations Board v. Greater Johnstown Area Vocational-Technical School, 48 Pa.Comm.Ct. 604, 410 A.2d 1290 (1980).

*275 In the instant case, the contract expressly provides: “All claims, disputes and other matters in question concerning or relating to this contract and any dispute ... as to the interpretation of the contract document shall be decided by arbitration.” It follows that in Muhlenberg and Kardon, supra, that in the absence of express exclusions, adopted by the parties, to the broad language referring all issues to arbitration should be construed as conferring on the arbitrators the power to decide procedural questions as timeliness and the substantial matters raised.

Even if the court below was not in error as to the completion of the work, the obligation to arbitrate services survived the completion of the work. Chester City School Authority v. Aberthaw Construction Company, 460 Pa. 343, 333 A.2d 758 (1975); Westmoreland Hospital Association v. Westmoreland Construction Company, 423 Pa. 225, 223 A.2d 681 (1966).

The “work delay” provision 7.10.3 as set forth above, which the court below seized upon to hold that the arbitration obligation is limited to the completion of the work only provides for the continuance of the performance of the work in the event of arbitration.

In Chester, supra, the court concluded that the standard AIA provision authorized arbitration even after the performance of the work had been concluded. The result in Westmoreland,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark Hankin & Industrial v. Keystone Granite
Superior Court of Pennsylvania, 2022
Ross Development Co. v. Advanced Building Development, Inc.
803 A.2d 194 (Superior Court of Pennsylvania, 2002)
CGU Insurance v. Pinkerton Computer Consultants Inc.
49 Pa. D. & C.4th 481 (Philadelphia County Court of Common Pleas, 2000)
Commonwealth v. Milton
18 Pa. D. & C.4th 238 (Lycoming County Court of Common Pleas, 1992)
Village of Cairo v. Bodine Contracting Co.
685 S.W.2d 253 (Missouri Court of Appeals, 1985)
Donegal Mutual Insurance v. Stern
34 Pa. D. & C.3d 314 (Alleghany County Court of Common Pleas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
454 A.2d 126, 308 Pa. Super. 271, 1982 Pa. Super. LEXIS 6021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shamokin-area-school-authority-v-farfield-co-pasuperct-1982.