Shambaugh & Son, LP v. Allen County Public Library (mem. dec.)

CourtIndiana Court of Appeals
DecidedAugust 9, 2017
Docket02A03-1701-PL-73
StatusPublished

This text of Shambaugh & Son, LP v. Allen County Public Library (mem. dec.) (Shambaugh & Son, LP v. Allen County Public Library (mem. dec.)) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shambaugh & Son, LP v. Allen County Public Library (mem. dec.), (Ind. Ct. App. 2017).

Opinion

MEMORANDUM DECISION Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any FILED court except for the purpose of establishing Aug 09 2017, 7:40 am

the defense of res judicata, collateral CLERK estoppel, or the law of the case. Indiana Supreme Court Court of Appeals and Tax Court

ATTORNEY FOR APPELLANT ATTORNEYS FOR APPELLEE Rebecca J. Maas Kevin P. Podlaski Smith Fisher Maas Howard & Lloyd, Joshua A. Burkhardt P.C. Beers Mallers Backs & Salin, LLP Indianapolis, Indiana Fort Wayne, Indiana

IN THE COURT OF APPEALS OF INDIANA

Shambaugh & Son, LP, August 9, 2017 Appellant-Defendant/Counterclaimant, Court of Appeals Case No. 02A03-1701-PL-73 v. Appeal from the Allen Superior Court Allen County Public Library, The Honorable Craig J. Bobay, Appellee-Plaintiff/Counterdefendant Special Judge Trial Court Cause No. 02D01-1002-PL-26

Vaidik, Chief Judge.

Court of Appeals of Indiana | Memorandum Decision 02A03-1701-PL-73 | August 9, 2017 Page 1 of 8 Case Summary [1] Shambaugh & Son, L.P. (Shambaugh) appeals the trial court’s judgment in

favor of the Allen County Public Library (Library) on Shambaugh’s breach-of-

contract claim. Finding no error, we affirm.

Facts and Procedural History [2] This is the second appeal in this case. In our first opinion, we explained that, in

2004, the Library undertook a capital-improvement project to renovate and add

to its main library branch building in Fort Wayne. Allen Cty. Pub. Library v.

Shambaugh & Son, L.P., 997 N.E.2d 48, 49 (Ind. Ct. App. 2013), aff’d on reh’g, 2

N.E.3d 132 (Ind. Ct. App. 2014), overruled on other grounds by Bd. of Comm’rs of

Cty. of Jefferson v. Teton Corp., 30 N.E.3d 711 (Ind. 2015). We noted that the

Library hired W.A. Sheets & Sons, Inc. as the construction manager and

MSKTD & Associates, Inc. as the architect and that it contracted directly with

Shambaugh to perform mechanical, electrical, and fire-protection work and

with Hamilton Hunter Builders, Inc. to do concrete work. Id.

[3] The Library agreed to pay Shambaugh approximately $12.4 million for its work

on the project. The Library’s contract with Shambaugh, which consisted of a

main agreement and multiple attachments, required it to “set aside ten percent

(10%) of the funds as retainage and hold the retainage in escrow until the work

Court of Appeals of Indiana | Memorandum Decision 02A03-1701-PL-73 | August 9, 2017 Page 2 of 8 was fully performed.” Appellant’s App. Vol. II pp. 22-23.1 Article 6 of the main

agreement, captioned “FINAL PAYMENT,” provides that

[f]inal payment . . . shall be made by the Owner to the Contractor when (1) the Contract has been fully performed by the Contractor . . .; and (2) a final Project Certificate for Payment has been issued by the Construction Manager and Architect; such final payment shall be made by the Owner not more than 30 days after the issuance of the final Project Certificate for Payment[.]

[4] Appellant’s App. Vol. VI p. 19. And Paragraph 7.2 of the main agreement

states, “Payments due and unpaid under the Contract shall bear interest from

the date payment is due at the rate stated below, or in the absence thereof, at

the legal rate prevailing from time to time at the place where the Project is

located.” Id. at 20. No rate was specified in the contract, and Shambaugh tells

us that it should be 8%, in accordance with Indiana Code section 24-4.6-1-102.

[5] In July 2007, Shambaugh submitted an “Application for Payment” indicating

that it had completed 100% of its work on the project and requesting the release

of the remaining retainage: $691,267.20. In December 2008, the Library

released $300,000 of the retainage to Shambaugh. Then, in early 2010, with the

remaining $391,267.20 still unpaid, the Library filed a lawsuit against

1 Shambaugh’s appendix consists of eight volumes, but the table of contents is written as though the documents are organized in four volumes. This, of course, threw off the pagination, rendering the table of contents, and some of the citations in Shambaugh’s briefs, largely unhelpful. We urge counsel to exercise greater care in the future.

Court of Appeals of Indiana | Memorandum Decision 02A03-1701-PL-73 | August 9, 2017 Page 3 of 8 Shambaugh and the other companies involved in the project. In our first

opinion, we described the basis for the suit as follows:

One part of the library renovation and addition project required Shambaugh to permanently install an emergency diesel generator and two diesel fuel storage tanks—one 1,000 gallon tank and one fifty gallon “day” tank—in the library’s basement. Hamilton Hunter poured the concrete floor supporting the generator and tanks, and which also covered copper piping connecting the “day” tank and generator. Part of the concrete pouring process required Hamilton Hunter workers to create a wooden form for the concrete and drive steel stakes into the ground. In December 2007, the Library discovered that a hole in the copper piping had caused approximately 3,000 gallons of diesel fuel to leak into the ground underneath the library. The Library believes that the hole was caused by a Hamilton Hunter employee having driven a steel stake through the pipe. The Library undertook to investigate and clean up the leaked fuel.

Allen Cty. Pub. Library, 997 N.E.2d at 51 (footnote omitted). Shambaugh filed a

counterclaim against the Library, seeking release of the remainder of the

escrowed retainage and the escrow income, as well as an award of 8% interest

under the contract.

[6] In February 2016, after six years of litigation that included the first trip to this

Court, the trial court entered summary judgment in favor of the defendants on

the Library’s fuel-cleanup claims, citing subrogation waivers in the relevant

contract documents. Shambaugh then filed a motion seeking the payment of

the remainder of the escrowed retainage, approximately $99,000 for the income

earned on the retainage, and nearly $213,000 for interest pursuant to the parties’

Court of Appeals of Indiana | Memorandum Decision 02A03-1701-PL-73 | August 9, 2017 Page 4 of 8 contract, dating back to 2007. In its response, the Library “agree[d] that the

retainage and interest [i.e., the income] earned on the retainage should be paid

to Shambaugh,” noted that it had “been working with the Architect to obtain a

certification for the release of these funds,” and stated that it would “release the

remaining retainage upon receipt of a properly authenticated payment

application in conformance with the Contract.” Appellant’s App. Vol. VI pp.

5-6. However, the Library argued that because it had not yet received the

certificate from the architect, the final payment to Shambaugh had not yet come

due under the terms of the contract, and that therefore the Library should not

be required to pay additional interest.

[7] On October 14, 2016, two days after the Library filed its response, the architect

signed a Certificate for Payment stating that to the best of its “knowledge,

information and belief the Work has progressed as indicated, the quality of the

Work is in accordance with the Contract Documents, and the Contractor

[Shambaugh] is entitled to payment of [$391,267.20].” Appellant’s App. Vol.

VIII p. 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Shambaugh & Son, LP v. Allen County Public Library (mem. dec.), Counsel Stack Legal Research, https://law.counselstack.com/opinion/shambaugh-son-lp-v-allen-county-public-library-mem-dec-indctapp-2017.