Shahin v. Taunton Land Development, LLC

27 Mass. L. Rptr. 222
CourtMassachusetts Superior Court
DecidedJuly 12, 2010
DocketNo. 07CV1776F
StatusPublished

This text of 27 Mass. L. Rptr. 222 (Shahin v. Taunton Land Development, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shahin v. Taunton Land Development, LLC, 27 Mass. L. Rptr. 222 (Mass. Ct. App. 2010).

Opinion

Curran, Dennis J., J.

Introduction

Davood Shahin, a licensed architect doing business as DSH Design Group, has sued developer Taunton Land Development, LLC for inter alia, breach of contract, quantum meruit, and a chapter 93A violation. Taunton counterclaimed for negligence, breach of contract, intentional and negligent misrepresentation, and chapter 93A violations. All of Taunton’s counterclaims were dismissed after Shahin’s motion for summary judgment.

Shahin’s claims went to trial before a jury on November 19 and 20, 2009, and resulted in an award of $68,496 for breach of contract. In response to a request for advisory findings under chapter 93A, the jury found that Taunton had engaged in unfair and deceptive practices and found that $35,000 was adequate compensation for such violations, but because Taunton’s conduct was willful or knowing, such sum should be doubled to $70,000.

The matter is presently before me on Shahin’s chapter 93A claim and his petition for attorneys fees and costs under that statute, both opposed by Taunton.

THE FACTS

Developer Taunton, through its promoter and principal Michael DiGuiseppe, was casting about for an architect to work on a substantial project to design a shopping center at Taunton Crossing. It requested bids from several architectural firms, to which Shahin, a sole proprietor, responded:

. . . [T]hank you for considering us to team up with you in the Design of Taunton Crossing. Because of our interest in establishing a long relationship with you and your company!,] we have based our fee on actual cost and have tried to be reasonable in our estimate by careful examination of the scope of work. I believe the fee presented in this agreement is by far below the market rate and I hope you will find it satisfactory.
We are veiy excited about the prospect of teaming up with you and your company on your current and hopefully!,] future projects.

(See letter of Davood Shahin dated October 27, 2004, trial exhibit.) (Emphasis added.) On February 1, 2005, DSH and Taunton entered into the first of four contracts by which Shahin would provide architectural services for the shopping center construction project. On May 27, 2005, the parties entered into three more such agreements, these for architectural design services to construct retail stores for Michaels, TJMaxx, and Her One Imports. The original agreement stated that:

This agreement is based upon a mutual obligation of good faith and fair dealing between the parties . . . Accordingly, the Owner and Architect with positive commitment to honesty and integrity will assist in the other’s performance and will work diligently to fulfill its obligation and will cooperate in the common endeavor of the agreement.

On February 28, 2006, Shahin submitted its final billing invoices totaling $68,496, and in doing so, reduced his bill as a courtesy by $1,855. Under the terms of their contract, payment was due within thirty days. Taunton responded by hurling charges of project deficiencies, and asserted that Shahin owed it more than $200,000 in “back charges” caused by design defects which increased construction costs. These claims were accompanied by Taunton’s in terrorem threat to sue Shahin for professional negligence and assert claims under his liability insurance policy. After six months of purported negotiation, Taunton agreed to pay Shahin nearly $54,000, with Shahin’s liability carrier agreeing to pay him an additional $8,000 to avoid protracted litigation defense costs. However, when Taunton learned that an additional money source existed, it immediately repudiated the settlement agreement and instead, asserted claims against Shahin’s insurance policy.

Suit commenced. Taunton asserted five counterclaims at Shahin, each of which required discovery and defense, but all of which were ultimately dismissed on summary judgment. DiGuiseppe admitted at trial that he had simply “made up” the facts in his summary judgment affidavit to disclaim liability. Shahin prevailed at the summary judgment stage on Taunton’s counterclaims, and ultimately, after trial on his contract claim. It took over three and a half years for a jury to confirm what Shahin knew, ab initio: that he was lawfully entitled to his entire fee for architectural work, and that Taunton had deceived him by falsely leading him on to believe he would be paid.

We now turn to the question of whether Shahin’s petition for fees and costs is reasonable, applying those facts detailed in Linthicum v. Achambault, 379 Mass. 381, 388-89 (1979): the time and labor, skill required, nature of the case, issues presented, amount of damages involved, skill of the attorney, experience, reputation and ability of the attorney, the similar prices for similar services, and the results achieved.

a. Time and Labor

The starting point in this inquiry is to examine the amount of time reasonably expended on the case. Here, plaintiff counsel’s records were detailed, properly descriptive and complete. He claims that although the case did not involve “big money,” the “original complexity and breadth of the factual issues involved in this case cannot be understated.” Taunton counters [224]*224that “at heart, this was a simple fee dispute.” The truth lies somewhere between these polar extremities.

Undercutting the plaintiffs present assertion is that discovery was essentially limited to word-processed interrogatories1 and a request for production of documents. The plaintiff took no depositions.

Four witnesses testified at trial, which began and ended in two days. For this effort, Shahin states that over 161 law firm partnership billing hours were required, as well as over 250 hours of associates’ time, run up by six different associates. There is no evidence that Mr. Shahin paid any of the $121,619 in legal fees and $2,319.15 in costs; rather, it appears that the liability insurer paid for his defense against the counterclaims, and continued even after the Court allowed a discovery sanctions motion that precluded Taunton from introducing any expert testimony at trial, the insurer also paid for Shahin to advance his non-payment claim.2 Thus, counsels’ bills to Shahin would have greater credence if they were actually paid by him,3 rather than passed off to an arguably less interested, institutional third party.4 Given this fact, the billings appear designed for the presentation of an anticipated chapter 93A fee recovery rather than reflecting an economical use of attorneys’ time in a relatively straightforward collection matter — albeit needlessly prolonged by the developer’s intransigence and litigation savvy.

b.The Amount of Damages

It is not simply the amount of money expended to chase a relatively modest recovery that is troubling; rather, it was the indulgent expenditure in obvious anticipation of fee-shifting. It is insufficient for the plaintiff to claim that his legal bills were high because this case underwent unsuccessful mediation, for many cases proceed down such a path, to no avail. Moreover, it is not enough for the plaintiff to claim that an extensive defense was warranted by the defendant’s counterclaims, for such commonly occurs in construction cases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Linthicum v. Archambault
398 N.E.2d 482 (Massachusetts Supreme Judicial Court, 1979)
Polion v. Wal-Mart Stores, Inc.
22 Mass. L. Rptr. 31 (Massachusetts Superior Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mass. L. Rptr. 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shahin-v-taunton-land-development-llc-masssuperct-2010.