Shaffer v. United States

121 F. Supp. 656, 128 Ct. Cl. 299, 1954 U.S. Ct. Cl. LEXIS 135
CourtUnited States Court of Claims
DecidedJune 8, 1954
DocketNo. 48885
StatusPublished
Cited by2 cases

This text of 121 F. Supp. 656 (Shaffer v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaffer v. United States, 121 F. Supp. 656, 128 Ct. Cl. 299, 1954 U.S. Ct. Cl. LEXIS 135 (cc 1954).

Opinion

MaddeN, Judge,

delivered the opinion of the court:

The plaintiff is the trustee in bankruptcy of Texasteel Manufacturing Company. He has been authorized by the bankruptcy court to bring this suit. It is a suit for damages for alleged breach of contract and taking of the bankrupt’s property by the United States, acting through the Bureau [302]*302of Ordnance of the Navy Department. For convenience of expression, the bankrupt will be called the plaintiff in this opinion.

The plaintiff’s corporate stock was owned entirely by members of the Armstrong family. In 1940 it made a contract with the War Department to manufacture shells at the plaintiff’s plant in Fort Worth, Texas. From that time until the-end of the war it produced shells at that plant efficiently, and at a large profit to itself.

In February 1941, the plaintiff requested the Bureau of Ordnance, Navy Department, to put the plaintiff on its list of prospective suppliers of shells, including the 5-inch shells,, to the Navy. The plaintiff said that its facilities were presently engaged on the Army work, but that they might be available in the future. The Navy inspected the plaintiff’s, plant and advised it that it could not qualify as a satisfactory source of Navy supply unless it proposed to expand its facilities. The plaintiff, by letters and in oral conversation advised the Navy of additions which it could make to its facilities if it could get substantial contracts to supply shells to. the Navy. On April 25, 1941, the Navy wrote the plaintiff acknowledging the receipt of the plaintiff’s statements about the proposed additions to its facilities, and saying that it would give the plaintiff an opportunity to bid on its work. The Navy sent bid forms to the plaintiff, and the plaintiff on May 6 returned them without a bid saying that it hoped by about May 20th to be able to make bids, but whether it could do so or not would depend upon whether and when it could get certain equipment which it was negotiating for. On May 7 the plaintiff sent the Navy a copy of a letter which it had written to the predecessor of the War Production Board in which it discussed expanding its and its parent company’s Fort Worth facilities and also building other facilities at a new location, naming Beaumont, Port Arthur and Texas City, Texas, as advantageous places. The proposed construction included a new steel mill to produce the-steel from which shells would be made. The letter said that, the plaintiff could not finance the proposed expansion without Government aid. It said that the Emergency Plant Facility Plan had been suggested as an alternative. The-[303]*303plaintiff apparently desired advice as to whether such construction would be permitted.

On May 19, 1941, the plaintiff made a contract with the Beyster Corporation for the architectural services incident to the erection of a steel mill. The architect’s services were to include the preliminary survey, detailed layout for contractor’s bids, and supervision of construction.

On May 22,1941, the plaintiff submitted a bid to the Navy on 114,000 5-inch shells at a unit price of $12.744 with deliveries to be completed by July 1, 1942. This bid was accepted on June 6, though it was not the lowest bid, because other lower bidders could not meet the required delivery schedule, insisted on larger quantities than the invitation called for, or stated that Government-furnished facilities; would be required. The plaintiff’s bid gave no indication that Government-furnished facilities would be required.

On June 5, the plaintiff by letter offered to supply 20,000' 6-inch projectiles at $25.00 apiece, deliveries to commence in January 1942, or as soon thereafter as possible, contingent upon the delivery of certain named equipment for which it was negotiating. In another letter of June 5 the plaintiff asked that if it received the award of either the 114,000 shell contract or the 20,000 shell contract it be given a certificate of necessity and a certificate of nonreimbursement, as well as an advance payment. These certificates, as we understand them, were assurances that the contractor had built the facilities with its own money, and were to enable it to take accelerated depreciation on the facilities, for income tax purposes.

In still another letter of June 5 the plaintiff urged expeditious action on its application for advance payment so that the advanced money would be available to pay for the acquisition and transportation of the necessary equipment, in order that production might be started without delay. In still another letter of June 5 the plaintiff described in detail the plaintiff’s facilities, actual and planned, for the production of shells and shell forgings. This letter was in response to a verbal request for such a description. This letter described the proposed new South Texas plant as having been planned and designed for the production of 5-inch or 6-inch Navy shells. It estimated that the steel plant would produce [304]*30412,000 tons of billet steel monthly; that the hydraulic presses would produce 110,000 forgings monthly, and that the machine tools which had been designed, and could be completed within six months, would completely machine the shells at that same rate.

On June 7,1941, the plaintiff bid for the supply of 300,000 or 500,000, or 750,000 5-inch shells at stated prices. It offered to commence deliveries in January 1942, and continue them at the rate of 100,000 per month until completion of the contract. The bid said “An investment by our company of approximately $1,000,000 will be entailed in the purchase of” certain necessary named facilities. It also said “Architect-engineers engaged for the purpose will undertake complete installation of plant in five months from date.”

. Three contracts were let to the plaintiff between June 6 and June 21, 1941. The one for 114,000 5-inch shells was designated NOrd-153 and called for completion of deliveries by July 1,1942. The one for 20,000 6-inch shells was designated NOrd-150 and called for delivery of 2,000 shells by January 1942, and 2,000 shells per month thereafter. The third one was for 250,000 5-inch shells, was designated NOrd-171 and called for deliveries to be completed by October 1942. The plaintiff furnished a performance bond, in a designated amount for each contract, written by Seaboard Surety Company.

Contracts NOrd-153 and NOrd-150 contained agreements by the Government to advance not to exceed 30 percent of the contract price to the contractor. On July 1, 1941, the plaintiff requested an advance of $435,844.80 on NOrd-153. In its request it enclosed the advance payment bond of the Seaboard Surety Company. It stated by items what it needed the money for, viz. specified equipment and the cost of transporting it. It said that in addition to this money, and $150,000 which it was requesting to be advanced under contract NOrd-150, it would obtain the balance of the needed :$1,000,000 by a loan of $500,000 from the Reconstruction Finance Corporation, secured by a first mortgage loan on plant and realty. It further said:

The H. E. Beyster Corporation, Detroit, Michigan, has been engaged under the usual form of contract for such services, to engineer and supervise the construction of [305]*305this plant. The engineers estimate that the plant can be installed and placed in production within five months from the date of commencement.

The requested advances on the two contracts were made by the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony M. Meyerstein, Inc. v. United States
137 F. Supp. 427 (Court of Claims, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
121 F. Supp. 656, 128 Ct. Cl. 299, 1954 U.S. Ct. Cl. LEXIS 135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaffer-v-united-states-cc-1954.