Shacocass, Inc. v. Arrington Construction Co.

776 P.2d 469, 116 Idaho 460
CourtIdaho Court of Appeals
DecidedJuly 19, 1989
Docket17286
StatusPublished
Cited by9 cases

This text of 776 P.2d 469 (Shacocass, Inc. v. Arrington Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shacocass, Inc. v. Arrington Construction Co., 776 P.2d 469, 116 Idaho 460 (Idaho Ct. App. 1989).

Opinion

BURNETT, Judge.

This appeal arises from a dispute over the technical specifications in a construction subcontract. The subcontractor seeks compensation for additional work allegedly made necessary by ambiguities in the specifications and arbitrary actions by the other contractors on the project. The district court entered summary judgment against the subcontractor. Today we affirm.

The background facts may be summarized briefly. On a site located within the boundaries of the Idaho National Engineering Laboratory (INEL), the United States Department of Energy disposes of nuclear waste. A facility known as the Idaho Chemical Processing Plant reprocesses irradiated uranium fuels, generating several hundred thousand gallons of high level radioactive liquid waste every year. This liquid waste is converted to solid substances and stored in stainless steel bins. The bins are enclosed in partially buried concrete vaults.

In 1979, the Department of Energy arranged for construction of a new set of storage bins on the INEL site. The bin complex was designed to withstand flood, tornado, and earthquake without any release of radioactive material. EG & G Idaho, Inc., designed the project and agreed to serve as the Department’s operating contractor for the site during construction. Morrison-Knudsen Co., Inc., was selected as the prime contractor and construction manager for the project. Exxon Nuclear contracted to operate the storage facility upon its completion.

Morrison-Knudsen subcontracted with Arrington Construction Company to perform all cement work required in the construction of the bins. After calling for bids, Arrington executed a lower-tier, fixed price subcontract with Shacocass, Inc., to install reinforcing steel (rebar) that would be embodied in the concrete structures. Shacocass’ bid was prepared by Ted McKinley, a major stockholder in Shacocass and the project manager for Shacocass’ work on the site.

Construction on the project began in the summer of 1982. While Shacocass was installing the rebar, it became involved in a dispute with the other contractors over a concrete cover specification. Shacocass also contested the manner in which Arrington was building the concrete forms. Inspectors from the various contractors found that Shacocass was not placing the rebar in compliance with the concrete cover specification. Shacocass was directed to re-do much of its rebar work. Shacocass later requested payment for the additional work. Arrington forwarded the request to Morrison-Knudsen, which denied it. Shacocass ultimately was paid the fixed price specified in its subcontract with Arrington.

Shacocass then filed this action for damages. Its verified complaint alleged that the other contractors had violated its subcontract, and had acted arbitrarily, in demanding the extra work without paying for it. The complaint advanced the theories of breach of contract, negligence, defamation and quantum meruit. Upon the other contractors’ motion for summary judgment, the district court initially dismissed Shacocass’ claim of defamation. Subsequently, on renewed motions for summary judgment, the court dismissed all the remaining claims. .

In this appeal we adhere to our familiar standard for reviewing summary judgments. Controverted facts are viewed in favor of the party resisting a motion for summary judgment. Where, as here, a *462 jury has been requested, the non-moving party also is entitled to the benefit of every reasonable inference that can be drawn from the evidentiary facts. See Anderson v. Ethington, 103 Idaho 658, 660, 651 P.2d 923, 925 (1982).

I

With this standard in mind, we turn first to Shacocass’ assertion that the other contractors acted in derogation of its subcontract by demanding that the rebar work be re-done. Shacocass contends that the original work complied with the specifications in the subcontract or, alternatively, that the specifications were ambiguous — creating a question of fact for a jury. The district court rejected both contentions. That ruling is subject to free review. Whether a contract is ambiguous is a question of law; and if the contract is not ambiguous, its meaning is also a question of law. 1 E.g. Clearwater Minerals Corp. v. Presnell, 111 Idaho 945, 948, 729 P.2d 420, 423 (Ct.App.1986).

The ambiguity question is framed by Shacocass’ assertion that the subcontract contained conflicting specifications. The subcontract consisted of several documents. The main document, a purchase order from Arrington to Shacocass, outlined Shacocass’ role as a subcontractor on the Morrison-Knudsen project. The purchase order directed the subcontractor’s work to be done “in strict accordance with the contract drawings and specifications.” It further recited that “[t]he general conditions of the contract specifications and all sections pertaining to bid items are hereby considered to be a part of this purchase order.” Thus, Shacocass was bound to comply with the technical specifications and drawings as well as Morrison-Knudsen’s general conditions for subcontractors.

Although the dispute over the specifications crystallized while work was in progress, it had its origin during the bidding process. When Ted McKinley of Shacocass was preparing his bid, he noticed that one of the specifications set a very strict standard. Simply stated for ease of discussion, it required two inches of concrete cover over the reinforcing steel and allowed only a quarter-inch tolerance (permitted deviance from the standard). Elsewhere the specifications stated that the tolerance for minimum concrete cover would be as stated in Code 318 of the American Concrete Institute. That code, Shacocass claims, would allow a half-inch tolerance. Before he submitted Shacocass’ bid, McKinley spoke to a Morrison-Knudsen representative about the quarter-inch tolerance, stating his belief that it must be an error. The Morrison-Knudsen representative made no statement confirming or denying such a mistake. Shacocass tendered its bid without obtaining a clarification. Subsequently, it installed rebar to the half-inch tolerance until the project inspectors insisted on compliance with the quarter-inch requirement.

Although Shacocass has suggested that the subcontract unambiguously calls for a half-inch tolerance, we deem such an interpretation untenable. The real issue is whether the subcontract was rendered ambiguous by its references to both the quarter-inch and half-inch tolerances. On that issue the subcontract as a whole itself supplies an answer by putting the tolerances in context. The half-inch tolerance is mentioned as part of a general recital that the project shall comply with applicable codes. The quarter-inch tolerance is a specifically mandated requirement. Moreover, the specifications contain a provision that if there is a conflict between a code and a particular specification, the particular specification will control. Accordingly, we hold, as did the district court, that the contract is not ambiguous as to tolerances. Properly construed, the contract unambig *463 uously imposes the quarter-inch requirement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merrill v. Smith
477 P.3d 230 (Idaho Supreme Court, 2020)
Gugino v. Kastera, LLC (In Re Ricks)
433 B.R. 806 (D. Idaho, 2010)
Vanderford Co., Inc. v. Knudson
165 P.3d 261 (Idaho Supreme Court, 2007)
Puckett v. Oakfabco, Inc.
979 P.2d 1174 (Idaho Supreme Court, 1999)
Baker v. Boren
934 P.2d 951 (Idaho Court of Appeals, 1997)
State v. Hardman
818 P.2d 782 (Idaho Court of Appeals, 1991)
Johnson v. City of Homedale
796 P.2d 162 (Idaho Court of Appeals, 1990)
Melton v. Lehmann
794 P.2d 650 (Idaho Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
776 P.2d 469, 116 Idaho 460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shacocass-inc-v-arrington-construction-co-idahoctapp-1989.