Sha-I Corporation, a Delaware Corp., Cross-Appellant v. City and County of San Francisco, a Municipal Corp., Cross-Appellee

612 F.2d 1215
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 6, 1980
Docket77-2858, 77-2884
StatusPublished

This text of 612 F.2d 1215 (Sha-I Corporation, a Delaware Corp., Cross-Appellant v. City and County of San Francisco, a Municipal Corp., Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sha-I Corporation, a Delaware Corp., Cross-Appellant v. City and County of San Francisco, a Municipal Corp., Cross-Appellee, 612 F.2d 1215 (9th Cir. 1980).

Opinion

ELY, Circuit Judge:

The root of the present controversy is a contract between SHA-I Corporation (for *1217 merly Automated Health Systems, Inc.), a Delaware corporation with its principal place of business in Massachusetts, and the City and County of San Francisco (“the City”). The basis of federal jurisdiction is the diversity of the parties’ residency and the requisite amount of money involved.

Automated Health Systems (“AHS”) agreed to design and install a computer system at the clinical laboratory of a hospital, operated by the City, in three successive phases described as the “PDP-12 Basic System,” “PDP-12 Advanced Systems,” and the “PDP-15 System.” After installation, each system was to be subjected to a 30-day acceptance test, and if the system performed at “an effectiveness level of 95%,” as defined in the contract, the City was to accept the system and pay for it. Installation, acceptance, and payment for the PDP-12 Basic and Advanced Systems occurred in line with the terms of the contract, but the contract collapsed in its third phase. Although the PDP — 15 System was installed, the City, having decided that it was unsatisfactory, refused to pay for that installation.

The District Court found that after some delay to which AHS and the City agreed, a successful acceptance test was conducted as to the PDP-15 System, the third phase. The City rejected the PDP-15 System and all its parts. Accordingly, the City refused to make any of the monthly payments provided by the contract in respect to the third phase. Thus, held the trial court, the City was liable to AHS for $433,842 only. This sum did not include the maintenance charges for which the City would have been responsible had the contract been in effect for the entire 6-year term. Nor did it include payment for that documentation that AHS had not carried out or payment for the microbiology section of the PDP-15, which had not been implemented, which, implementing the terms of the contract, was not a prerequisite to the obligation to pay for the installation of the first two phases. The trial court also declined to award AHS any of the several million dollars in other damages it claimed to have suffered as a result of the City’s alleged breach. Both parties now appeal. We affirm.

The City raises essentially two claims. First, it argues that, contrary to the finding of the District Court, it was never obliged to pay for the PDP-15 system. Second, it argues that even if the obligation did arise, it was not required to pay the entire amount it would have owed had it kept the system in operation for the whole 6-year term of the contract.

I.

The “PDP-15 System,” the center of the dispute, involves the use of a PDP-15 computer owned by AHS and certain other computer hardware owned by the City. AHS’s principal function was to create more than “700” computer programs, which, in combination with the existing hardware, would provide the San Francisco General Hospital with a clinical laboratory information system. The PDP-15 System design was based on a similar clinical laboratory system at Massachusetts General Hospital, but the San Francisco System was more advanced. AHS was willing to devote a rather large portion of its resources to the project with the City. It was looking for a “live lab” in which to create and promote its product. It hoped that by successfully installing the system in the San Francisco facility, it could market the system to other hospitals. The San Francisco General Hospital, on the other hand, would have acquired one of the “most advanced clinical laboratory systems in the world.” For reasons that are disputed by the parties, by late 1973, six months after the acceptance test was run, the City’s hospital ceased to rely on the system that AHS had installed. The City argues, initially, that because AHS never developed a fully operational clinical laboratory and because, in fact, the defects in performance were so pervasive as to defeat the object which the parties hoped to accomplish, no obligation, on the part of the City, to commence payments ever arose.

The contract explicitly dealt with the standards AHS was required to meet *1218 before the City’s obligation to pay for the system arose. The trial court found, on the basis of the written contract and the facts surrounding its creation, that the City’s obligation to pay for the system arose automatically when a 30-day acceptance test, as contractually defined in elaborate detail, was performed at the level of 95% effectiveness. The court further found that such a test was run in March and April of 1973. .In reaching its conclusion, the court resolved conflicts in the evidence and carefully weighed the credibility of various witnesses when testimony was conflicting. The court’s findings are not clearly erroneous; therefore we cannot, consciously, object to them. F.R.Civ.P. 52.

It is therefore irrelevant that, subsequent to the test, the system may have developed problems and ceased to operate satisfactorily. In creating state-of-the-art data processing systems, there is, of course, a risk that the system will not function as originally hoped. Other things being equal, however, the parties are free to allocate this risk in their contract as they mutually choose. There, AHS assumed the risk that its system would not be able to pass the acceptance test. But once the system passed the test, as the trial court concluded, the City bore the risk and became obliged to pay the contract price and suffer the consequences if the system did not perform to expectations.

The City also argues that even if it did breach the contract by failing to begin monthly payments to AHS, it cannot be held liable for all the monthly payments it might have been required to make over the entire 6-year term of the contract. First, the contract itself contained a cancellation clause that clearly appears to have given the City the right to cancel the contract on 6-months’ notice. Thus, it argues, even if it breached the contract, the measure of its obligation under the appropriate forum law, California, is the amount of money it would have been required to pay had it exercised its option to terminate. Pecarovich v. Becker, 113 Cal.App.2d 309, 317, 248 P.2d 123, 129 (1952). The meaning of the cancellation provision is, however, colored by the facts surrounding its creation. In concluding that the City was obliged to pay the full amount, the trial court must have determined that in accordance with the statement of undisputed facts submitted by AHS before trial, the provision was merely intended to satisfy certain budgetary requirements of the City and was not intended to give the City a right to cancel the contract at will.

The City also argues that because AHS became insolvent in October, 1973, AHS was incapable of performing further under the contract and that this incapacity excused the City from further payments. Apart from the fact that AHS’s collapse was due, in large part, to the City’s failure to accept the system and pay for it, the City does not distinguish payments that the City would have paid AHS for servicing the system during the 6-year term of the agreement and the payments for the computer programming that AHS had already furnished to the City. The maintenance charges are not the subject of the litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerwin v. Southeastern California Ass'n of Seventh Day Adventists
14 Cal. App. 3d 209 (California Court of Appeal, 1971)
Nelson v. Reisner
331 P.2d 17 (California Supreme Court, 1958)
Leeper v. Beltrami
347 P.2d 12 (California Supreme Court, 1959)
Pecarovich v. Becker
248 P.2d 123 (California Court of Appeal, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
612 F.2d 1215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sha-i-corporation-a-delaware-corp-cross-appellant-v-city-and-county-of-ca9-1980.