SFM Corp. v. Sundstrand Corp.

99 F.R.D. 101, 38 Fed. R. Serv. 2d 693, 1983 U.S. Dist. LEXIS 14085
CourtDistrict Court, N.D. Illinois
DecidedSeptember 2, 1983
DocketNo. 82 C 4933
StatusPublished
Cited by10 cases

This text of 99 F.R.D. 101 (SFM Corp. v. Sundstrand Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SFM Corp. v. Sundstrand Corp., 99 F.R.D. 101, 38 Fed. R. Serv. 2d 693, 1983 U.S. Dist. LEXIS 14085 (N.D. Ill. 1983).

Opinion

MEMORANDUM OPINION AND ORDER

SHADUR, District Judge.

SFM Corporation (“SFM”) brought this diversity action charging a refusal by Sundstrand Corporation (“Sundstrand”) to perform its contract to buy complex machine tools manufactured by SFM. In turn Sundstrand initially filed a one-count Counterclaim accusing SFM of breach of contract. Some nine months later Sundstrand filed a greatly expanded four-count Amended Counterclaim. SFM now moves to strike Amended Counterclaim Counts II through IY (“Counts II-IV”). For the reasons stated in this memorandum opinion and order, SFM’s motion is conditionally denied.

Background 1

Early in 1979 Sundstrand solicited a quotation from SFM for machines capable of making metal shafts for hydrostatic transmission controls produced by Sundstrand. In April 1979 SFM furnished a quotation for two machines. During the next 14 months SFM and Sundstrand conducted extensive negotiations, much of which centered on the performance standards to which the machines would be expected to conform. In July 1980 SFM submitted a revised quotation reflecting the results of those negotiations. In October 1980 Sundstrand issued a purchase order for two [103]*103lathes, a centering machine and accessory equipment (collectively the “Lathes”), setting the purchase price at $830,684 and calling for delivery by January 31,1982. Later the parties agreed on various written and oral revisions of the original purchase order (for convenience this opinion calls the purchase order as so modified the “Contract”). One such modification extended the delivery target date to May 28, 1982, prompted at least in part by SFM’s inability to complete the manufacture and testing of the Lathes due to a strike by its work force from May through July 1981.

Throughout the first half of 1982 SFM was continually beset by production difficulties (the cause of which is hotly contested by the parties). Consequently it was unable to complete the Lathes by May 28. Next day Sundstrand sent SFM a telex unilaterally cancelling the Contract. Sundstrand cited as the basis for its action SFM’s failure to complete a successful “runoff” of the Lathes and to meet the extended delivery deadline.

On August 10, 1982 SFM filed this lawsuit, seeking compensatory damages of $830,684 for breach of contract and $1 million for fraud and estoppel, plus punitive damages of $3 million for fraud and estoppel. On September 28 Sundstrand filed its Answer and Counterclaim, the latter charging SFM with breach of contract and seeking compensatory damages of $190,000 (the estimated costs attributable to (1) Sundstrand’s efforts to cover and (2) Sundstrand’s inability to procure substitute Lathes for a significant period of time since the May 28, 1982 delivery date).

Discovery proceeded at a brisk pace during the nine months that preceded Sundstrand’s May 25, 1983 motion for leave to file the Amended Counterclaim. By that date SFM had taken the depositions of 11 current and former Sundstrand employees, totaling 15 full days of testimony and 2,601 pages of transcript. During that same period Sundstrand deposed one former Sundstrand employee and six current and former SFM employees, consuming 18 full days of testimony and 2,326 pages of transcript.

Because discovery was nearing completion, on May 17, 1983 (just eight days before the Amended Counterclaim was filed) Magistrate Olga Jurco scheduled a June 27 status hearing to set the date for the final pretrial order. At a status hearing before Judge Flaum that same day (May 17), the parties discussed possible discovery cutoff dates. SFM’s counsel indicated discovery would be completed within six weeks, while Sundstrand’s counsel estimated an additional 60-90 days would be required. Judge Flaum declined to set a date for close of discovery because of his appointment to our Court of Appeals, preferring instead to leave such scheduling to the judge to whom the case would be reassigned.

On May 25 Sundstrand requested leave to file its Amended Counterclaim, which contained three wholly new Counts:

1. Count I is identical to the original one-count Counterclaim except that the claimed damages have been raised to $481,826.20.

2. Count II alleges SFM fraudulently misrepresented and omitted material facts to manipulate Sundstrand into entering a contractual arrangement to purchase the Lathes. Count II ¶ 16 identifies three such misrepresentations:

(a) SFM’s Model 400 Tracer Lathe, which SFM proposed to sell to Sundstrand, was a standard lathe as described in the sales literature provided by SFM to Sundstrand and expressly incorporated into the Contract.
(b) The lathes were capable' of holding diametrical and concentricity tolerances of .002 inch on the block spline diameter of Sundstrand’s shaft 3101867 and similar shafts.
(c) The lathes were capable of holding linear and other tolerances of plus or minus .002 inch on the parts turned on the Lathes.

Count II ¶ 17 lists five .assertedly fraudulent omissions:

(a) Before accepting the Contract SFM had never designed or built a Model 400 bar feed tracer lathe that it knew to be capable of holding linear [104]*104and other tolerances of plus or minus .002 inch.
(b) Before accepting the Contract SFM had designed and built Model 400 bar feed tracer lathes for only one customer. Those lathes had not been required to hold linear tolerances of plus or minus .002 inch.
(c) Before accepting the Contract SFM Vice-President Ebel had never consulted with SFM engineering personnel, or with SFM sales personnel with experience in engineering, as to the requirements of the Contract.
(d) SFM engineering personnel, and SFM sales personnel with engineering experience, doubted the capability of an SFM Model 400 bar feed tracer lathe of the type SFM proposed to build for Sundstrand to hold linear tolerances of plus or minus .002 inch.
(e) Although SFM had guaranteed Sundstrand in writing that the SFM machines could hold certain tolerances or achieve other performance specifications “on a production basis,” SFM did not intend those guaranties to apply to “production runoffs” of the machines that were expressly provided for in the Contract as a means for Sundstrand to determine whether or not to accept the machines.

3. Count III says SFM breached its contractual duty to deal in good faith by making material misrepresentations and omissions during the course of its attempted performance under the Contract. Count III ¶ 26 states two such misrepresentations:

(a) Despite a strike at SFM in the summer of 1981, SFM could complete work on the Lathes in time to deliver them to Sundstrand by the original delivery date in the Contract of January 31, 1982.
(b) At various times during the spring of 1982 the Lathes were producing shafts in accordance with the requirements of the Contract during quality runs conducted by SFM.

Count III ¶ 27 cites two such omissions:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tripwireless, Inc. v. King
N.D. Indiana, 2025
Matus v. Metropolitan Government of Nashville
128 S.W.3d 653 (Court of Appeals of Tennessee, 2003)
Jose & Gioconda Matus v. Nashville General Hospital
Court of Appeals of Tennessee, 2003
Tarkett Inc. v. Congoleum Corp.
144 F.R.D. 289 (E.D. Pennsylvania, 1992)
In Re VMS Securities Litigation
752 F. Supp. 1373 (N.D. Illinois, 1990)
FRANK McDERMOTT, LTD. v. MORETZ
898 F.2d 418 (Fourth Circuit, 1990)
Frank M. McDermott, Ltd. v. Moretz
898 F.2d 418 (Fourth Circuit, 1990)
Gardiner v. Word
731 S.W.2d 889 (Tennessee Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
99 F.R.D. 101, 38 Fed. R. Serv. 2d 693, 1983 U.S. Dist. LEXIS 14085, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sfm-corp-v-sundstrand-corp-ilnd-1983.