Seymour v. Long Dock Co.

20 N.J. Eq. 396
New Jersey Court of Chancery·Decided October 15, 1869·Published·Cited by 4 cases

Opinion

The Master.

The Long Dock Company is a company incorporated by act ■ of February 26th, 1856, (Pamph. Laws, p. 67,) for the purpose of constructing a tunnel through Bergen hill, and ,certain accessories, intended for-the use of the New York and Erie Eailroad Company. The Long Dock Company-made a contract, dated May '28t-h, 1856, with one James H. Mallery, for the excavation of this, tunnel. The contract is set out in full in the complainant’s bill. Mallery [403] had performed but a small part of the work undertaken when he abandoned it, in October, 1857.

John P. Cumming, February 14tli, 1859, entered into a contract with the company to complete the tunnel, as also to perform some additional work undertaken by him; the complainant, A. B. Seymour, being a partner with Cumming, with the knowledge of the officers of the company, though, for some reasons unexplained, the contract was in the name of Cumming only. Under the contract, Cumming agreed to finish and complete all the rock work remaining to be done at its date, and to complete the tunnel and its approaches, according to the location, form, dimensions, conditions, and. requirements of said work, in the terms specified in the contract of James II. Mallery, and more particularly according to certain clauses in the specifications of that contract, and also according to certain clauses of the “conditions” of the same contract, specifically referred to, and thereby thus made a part of this second contract. The Mallery contract in these particulars, and as to these several “specifications” and conditions,” so far as not conflicting with the provisions of the Gamming contract, was made a part thereof. It is not necessary now further to recite this second contract, which is also set forth in full in the complainant’s bill. Cumming, June 2d, 1859, with the assent of the company, assigned his contract to Seymour, who thus became in name and in fact the contractor.

With much additional matter prescribed in the specifications and .conditions set forth in the Cumming contract, by it the contractor, in substance, undertook to complete what Mallery had begun.

The company, by the Cumming contract, had engaged to furnish cars to receive the materials excavated by the contractor, and to transport those materials to the places of deposit with such promptness as not to delay the work; to free the tunnel from water; to repair the shafts; and to repair the track, &c., in order to enable the contractor to proceed [404] in his work with the diligence and - promptness- required by his own interests as also those of the company. It is not necessary to refer to 'these stipulations on the part of the company with more particularity for the present purpose. They will be found in the contract itself already referred to.

As the work progressed, claims for additional compensa.tion on the part of the contractor were made, as well because of the allegéd inadequacy of .the contract prices, as also for damages sustained by him in consequence of the company failing to furnish cars when required, failing to ■promptly free the tunnel and shafts from water, and other alleged delinquencies. The company, on the recommendation of its engineer, about the 10th day of September, 1859, agreed to add a considerable sum to the contract price, provided for in the Cumming contract. It agreed about that day to add the sum of $27,500 to the schedule prices, in consideration of Seymour, by an instrument under seal bearing date on that day, agreeing to release and discharge the company from all right or claim to damage by reason of any violation, neglect, or non-performance of any stipulation or undertaking in said (Gumming) contract.

This agreement, I do-not deem to be any settlement of the long and voluminous accounts, which then existed between the company and its contractor. It seems to have been only an allowance of an extra amount of $27,500 on the contract as recomménded by Mr. Kirkwood, but in consideration of which-Mr. Seymour released all claim to the damages alleged to have been sustained by reason of any default on the part of the company. Eelinquishing such claims, he consented, from that time, to rely for his remuneration on the contract prices thus increased, to be paid to him by the company for his work.

I stop at this point of the case to say that I see no reason sustained by the evidence upon which this release, as it has been called, can be set aside for fraud. The company, on the recommendation of its engineer, made this large addition to [405] the contract price, but it did so on the express condition incorporated into the written instrument executed by Mr. Seymour, that the contractor should set up no claim for damages by reason of any violation, neglect, or non-performance of any stipulation or undertaking in said contract, on the part of the company, to date, &e. By the same instrument, Mr. Seymour also further proceeds to sell and transfer to the Long Dock Company all the machinery, sheds, workshops, fixtures, and tools on the premises, or used for the work, not absolutely, but it would seem by way of security, as the same were to be re-transferred on the fulfillment of the contract. I see no ground, as the case is presented to me, on which this instrument is to be invalidated. The contractor knew the condition of the work, and, it must be presumed, knew the effect of the instrument he then executed. He relinquished no part of the remuneration which had been stipulated to be given him. For the large sum of $27,500 thus paid, he simply relinquished his claim for damages alleged to have been sustained by the default of the company in the matters referred to. But, on the other hand, the agreement settled no questions as to the amount of the work, leaving them to be settled by a subsequent account between the parties. It simply estopped him from setting up any claim for these damages prior to the date of this release.

The work was then proceeded with by the contractor down to March 22d, 1860, when a new arrangement was made between him and the company. This now arrangement was, by an agreement of that date, set forth at length in the com-' plainant’s bill.

Free access — add to your briefcase to read the full text and ask questions with AI

Seymour v. Long Dock Co., 20 N.J. Eq. 396 (N.J. Ct. App. 1869).

20 N.J. Eq. 396 (Seymour v. Long Dock Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Maihack v. Mehl
57 A.2d 44 (New Jersey Court of Chancery, 1948)
Slavin v. St. Stephens Roman, C., Church
168 A. 226 (New Jersey Court of Chancery, 1933)
Burdick v. Grimshaw
168 A. 186 (New Jersey Court of Chancery, 1933)
Pine Building Co. v. Grossman
140 A. 251 (New Jersey Court of Chancery, 1928)