Sexton v. United States

82 Ct. Cl. 550, 1936 U.S. Ct. Cl. LEXIS 290, 1936 WL 2925
CourtUnited States Court of Claims
DecidedFebruary 3, 1936
DocketNo. 41980
StatusPublished

This text of 82 Ct. Cl. 550 (Sexton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sexton v. United States, 82 Ct. Cl. 550, 1936 U.S. Ct. Cl. LEXIS 290, 1936 WL 2925 (cc 1936).

Opinion

Whaley, Judge,

delivered the opinion of the court:

Pursuant to competitive bidding the plaintiff entered into a contract with the defendant on June 25, 1929, for the construction of a reinforced concrete culvert along the Rio Corundu River at the Albrook Flying Field in the Panama Canal Zone. The contract provided that the plaintiff furnish all labor and material and perform all work in the construction of the concrete culvert for the lump sum price of $178,000. The culvert was to be 1,918 feet in length and constructed in accordance with the specifications, schedules, and drawings which were made a part of the contract.

This suit is brought to recover upon five different items, three of which involve extra work and two involve the supplying of material which plaintiff claims was not called for under the contract and for which he should receive extra compensation under the terms of the contract.

[560]*560EXTRA PILES

The first claim is for the retention by the Government of 174 piles which remained at the site of the work after the completion of the piling required under the contract. It appears that in preparing for the performance of the contract the plaintiff had shipped to the site along with other material 1,230 piles. It was found that this number of piles was not necessary for the completion of the piling section of the contract and there were 174 piles left over after all the piles had been driven which were necessary. The plaintiff requested permission to remove these piles. The Government officer in charge of the work refused to allow the piles to be removed and claimed that these piles belonged to the Government under the terms of the contract. The plaintiff protested. After sixteen months the Comptroller General ruled that the piles belonged to the plaintiff. The Government offered to deliver the piles to the plaintiff but the offer was declined owing to the fact that the piles had deteriorated during this period to such an extent that they were valueless.

It is too obvious for argument that, where there is a lump-sum contract for the construction of a given project, any material required for this work and left over after the work is completed belongs to the contractor, and when the Government under such circumstances claims under the contract the ownership of the property so left over, and after a long period of time admits it has no right to the property under the contract, the plaintiff is entitled to the damages suffered by the act of the Government in retaining the property. United States v. Smith, 94 U. S. 214.

The evidence shows that the value of these piles was $1,661.70 at the time the Government refused to allow plaintiff to remove them. When permission was given for their removal by the plaintiff the piles were valueless. The plaintiff is entitled to recover the sum of $1,661.70.

SPLICING OF PILES

The specifications provided that the piles required under the contract were based on a length of 40 feet and should be [561]*561driven to a good refusal where the penetration is less than 20 feet and where the penetration is more than 20 feet, the piles should be driven to satisfy a bearing value of 20 tons. During the performance of this part of the contract it was found that some of the piles would not produce the required bearing strength at 40 feet. When this was called to the attention of the officers in charge, a change order was given to the plaintiff for a lump sum to make tests to determine the approximate depth and length of the piles necessary to reach the bearing strength. The contracting officer decided that a greater depth than 40 feet for the driving of the piles was not within the terms of the contract and that the plaintiff was entitled to receive compensation for the additional work and material required in driving the piles to a greater depth than 40 feet. The plaintiff submitted estimates to the contracting officer who decided to issue a change order allowing the plaintiff $6.00 per pile as increased compensation for the furnishing of labor, material, and equipment incident to the splicing and the driving of the piles “exceeding 40 feet in length”, and also allowed the plaintiff ten days additional time in which to complete the contract. Plaintiff requested a rehearing and submitted a request for additional compensation above that fixed by the contracting officer in his change order and the contracting officer agreed to recommend increases if the plaintiff could show the actual cost including a reasonable overhead and profit exceeding the amount fixed in the change order. No appeal was taken by the plaintiff to the head of the Department from the decision of the contracting officer.

Article 3 of the contract provides for changes and Article 5 provides that no charge for extra work or material is to be allowed unless ordered in writing by the contracting officer and the price stated in such order. Article 15 provides that all disputes concerning questions of fact arising under the contract were to be decided by the contracting officer subject to written appeal to the head of the Department and the decision of the head of the Department was to be final and conclusive as to questions of fact. No appeal was taken by the contractor from the change order issued by the contracting officer to the head of the Department.

[562]*562The contracting officer having construed the contract and specifications not to include this extra piling which involved splicing, and having issued a change order under the terms of the contract as to the extra piling, the plaintiff is entitled to recover for 158 piles, which were spliced and di’iven, at the rate of $6.00 a pile or the sum of $918.00.

EXTRA EXCAVATION

The claim for extra excavation is properly divisible into three parts.

(a) The drawings upon which the plaintiff was invited to make a 'bid called for the excavation of approximately 2,933 cubic yards. During the progress of the work it was discovered that certain errors had been made by the defendant in the computations as set out in the drawings and when these errors were corrected the yardage of excavation was greatly increased over that on which the bids were invited. The defendant admits these errors and the only difference between the parties is the amount of the extra excavation and the price to be paid per cubic yard. The evidence establishes, and the commissioner who took the evidence has found, that the plaintiff was required and did excavate 605 cubic yards due to these errors and the reasonable value of the work so performed is $6.50 per cubic yard. The greater weight of the evidence establishes these figures. The plaintiff is entitled to recover $3,932.50 for performing this extra work.

(5) During the performance of the work the plaintiff requested permission to make a change in the alignment of the culvert and the defendant granted the change on the express condition that no payment would be made for any additional excavation which might result from such a change and no extension of time for the completion of the contract would be given. The change of alignment did require extra excavation and the plaintiff claims extra compensation. No argument is necessary to show that plaintiff is not entitled to recover on this claim.

(c) Previous to the time when the plaintiff entered into the contract and during the performance of the work there[563]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Smith
94 U.S. 214 (Supreme Court, 1877)

Cite This Page — Counsel Stack

Bluebook (online)
82 Ct. Cl. 550, 1936 U.S. Ct. Cl. LEXIS 290, 1936 WL 2925, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sexton-v-united-states-cc-1936.