O’Connor, J.

{¶ 1} This appeal requires us to address issues regarding the statute of limitations that is applicable to claims for damage to real property occasioned by rainwater draining from adjacent land.

{¶ 2} Plaintiffs-appellants, Larry and Peggy Sexton, assert that flooding and erosion on their property was caused by the defendants’ negligent acts on the adjoining property. The trial court and the court of appeals determined that the statute of limitations for appellants’ claims expired prior to the filing of their suit because their claims were not based on a continuing trespass but on a permanent trespass that had been fully completed more than four years prior to the filing of the suit. A finding of a continuing trespass would have tolled the statute of limitations. For the reasons that follow, we affirm the judgment of the court of appeals.

I

{¶ 3} The Sextons built a home just outside the city limits of Mason and moved into the home in 1988. A creek runs through the Sextons’ property, and they built a bridge over the creek in order for their driveway to cross it.

{¶ 4} In the late 1980s, the development of a subdivision, “Trailside Acres,” began on adjacent property within the Mason city limits. Appellee, Rishon Enterprises, Inc. (“Rishon”), was the developer of Trailside Acres. Rishon contracted with appellee McGill Smith Punshon, Inc. (“McGill”), an engineering company, to design the stormwater drainage system for the subdivision. McGill completed all of its engineering services on the subdivision in 1994. Rishon’s work on the subdivision was completed in 1995.

{¶ 5} As the development of the subdivision progressed, the Sextons began to experience water problems. The problems worsened in 1992, with water rising in the creekbed, going over the bridge, and flooding the Sextons’ property in periods of heavy or prolonged rains. There had been no water problems prior to [276]*276the subdivision construction. Therefore, the Sextons attributed the problems to the development.

{¶ 6} In 1995, Peggy Sexton wrote a letter to a Mason city official expressing the Sextons’ concerns. That letter stated that the creek at one time had been dry most of the summer and that water in the creek had never been very deep until approximately one to two years after the Sextons built their home in 1988. The letter further stated:

{¶ 7} “The creek, which is now always running, frequently floods and comes over our [bridge] headers * * *. The force of the flow is eroding our land, and killing trees on the bank. All of this is coming from the * * * Trailside subdivision.

{¶ 8} “ * * *

{¶ 9} “During a storm, I cannot even drive over our bridge, as the water comes over walls that are over a foot above the road. If the creek comes another 2-3 inches higher than it does on a regular basis (like during a good spring rain) our basement will be flooded.” (Emphasis sic.)

{¶ 10} In the summer of 2001, after an all-day rain, the Sextons’ basement filled with water that entered the house with considerable force. The water rose to a depth of five feet in the basement and damaged the contents. Prior to that event, the Sextons had never experienced flooding inside their home. The Sextons’ driveway was blocked by flooding so deep that firemen who responded to a 911 call were unable to drive their vehicle up to the house.

{¶ 11} The Sextons worked with city officials and city employees for a number of years in an attempt to address their water issues, but those discussions, according to Peggy Sexton, “broke down” in 2003. On July 14, 2003, the Sextons filed a complaint against the city and its engineering department concerning the water problems. On August 27, 2003, the Sextons filed an amended complaint that added Rishon and McGill as defendants. One of the Sextons’ claims was that the negligence of the defendants caused the flooding of their property.

{¶ 12} The city and Rishon separately moved to dismiss the complaint, or alternatively, for summary judgment. McGill also moved for summary judgment. Along with other arguments, the defendants urged that the complaint was time-barred by the four-year statute of limitations of R.C. 2305.09 because the cause of action had accrued in 1992 (or at the latest in 1995) but the complaint was not filed until 2003.

{¶ 13} A magistrate issued decisions overruling the motions of the defendants. The magistrate held that the Sextons’ complaint stated a cause of action for a continuing trespass and that “the action may be brought at any time prior to the [277]*277expiration of the prescriptive period of 21 years, but recovery may be had only for damages sustained within four years prior to the filing of the action.”

{¶ 14} After the defendants filed objections to the magistrate’s decisions, the trial court initially agreed with the magistrate’s reasoning. The trial court stated that “[t]here is no dispute that the Plaintiffs first discovered or became aware of the water problems on their property in 1992,” so that the statute of limitations began to run at that time. However, the trial court held that the statute of limitations did not bar all of the claims because the Sextons’ complaint stated claims for a continuing trespass.

{¶ 15} The trial court later reconsidered its decision and granted summary judgment to all defendants. In granting summary judgment to Rishon and McGill, the trial court ruled that the Sextons’ claims were based on a permanent trespass (rather than a continuing trespass as the court had ruled earlier) and that the four-year statute of limitations in R.C. 2305.09 applied to bar all claims. In granting summary judgment to the city, the trial court held, inter alia, that the city was entitled to sovereign immunity under R.C. Chapter 2744.

{¶ 16} The court of appeals affirmed the judgment of the trial court in all respects. In the part of that decision pertinent to this appeal, the court of appeals held that this case involves a permanent rather than a continuing trespass and that the damage to the Sextons’ property occurred when the subdivision was constructed. The court of appeals further held that because McGill completed its work on the project in 1994 and because Rishon completed its work in 1995, and there was no ongoing conduct by either defendant after the work was completed, even though damages continued, the “tortious act” of each was completed in those years and the claims were time-barred.

{¶ 17} This court accepted for review only one of the Sextons’ propositions of law in this discretionary appeal: “A claim for a continuing trespass may be supported by proof of continuing damages and need not be based on allegations of continuing conduct.” 1 113 Ohio St.3d 1488, 2007-Ohio-1986, 865 N.E.2d 913.

II

{¶ 18} In Harris v. Liston (1999), 86 Ohio St.3d 203, 714 N.E.2d 377, paragraph one of the syllabus, this court held:

{¶ 19} “Tort actions for injury or damage to real property are subject to the four-year statute of limitations set forth in R.C. 2305.09(D).”

[278]*278{¶ 20} Pursuant to Hams, which involved facts similar in many respects to those of this case, the four-year statute of limitations of R.C. 2305.09(D) clearly applies to the Sextons’ claims.

{¶ 21} In Hams, we held:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bend-Fast, Inc. v. SBA Monarch Towers III, L.L.C.
2024 Ohio 2036 (Ohio Court of Appeals, 2024)
Seymour v. Miller
S.D. Ohio, 2022
Naiman Family Partners, L.P. v. Saylor
2020 Ohio 4987 (Ohio Court of Appeals, 2020)
Darby v. Twinsburg Twp.
2020 Ohio 2702 (Ohio Court of Appeals, 2020)
McNabb v. Ottawa Cty. Commrs.
2019 Ohio 1487 (Ohio Court of Appeals, 2019)
Large v. Lilley
2018 Ohio 1017 (Ohio Court of Appeals, 2018)
Nottke v. Norfolk Southern Railway Co.
264 F. Supp. 3d 859 (N.D. Ohio, 2017)
Edwards v. Ohio Dept. of Transp.
2016 Ohio 5221 (Ohio Court of Claims, 2016)
Elmer v. S.H. Bell Co.
127 F. Supp. 3d 812 (N.D. Ohio, 2015)
Majesky v. Lawrence
2015 Ohio 49 (Ohio Court of Appeals, 2015)
Chernett Wasserman Yarger, L.L.C. v. ComScape Holding, Inc.
2014 Ohio 4214 (Ohio Court of Appeals, 2014)
Oaktree Condominium Assn., Inc. v. Hallmark Bldg. Co.
2014 Ohio 1937 (Ohio Supreme Court, 2014)
Brown v. Whirlpool Corp.
996 F. Supp. 2d 623 (N.D. Ohio, 2014)
Allen v. Andersen Windows, Inc.
913 F. Supp. 2d 490 (S.D. Ohio, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
883 N.E.2d 1013, 117 Ohio St. 3d 275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sexton-v-city-of-mason-ohio-2008.