Sewerage & Water Board v. Thelan

4 Teiss. 322, 1907 La. App. LEXIS 81
CourtLouisiana Court of Appeal
DecidedMay 6, 1907
DocketNo. 4102
StatusPublished

This text of 4 Teiss. 322 (Sewerage & Water Board v. Thelan) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sewerage & Water Board v. Thelan, 4 Teiss. 322, 1907 La. App. LEXIS 81 (La. Ct. App. 1907).

Opinion

DUFOUR, J.

On February 18th, 1903, plaintiff accepted defendant’s bid to furnish all labor and material for the alteration of the steam pipe system at the Central Power Station in accordance with certain specifications for the sum of $6340 to be completed on or before April 1st, 1903.

Thelan made arrangements with the Fairbanks Co. to furnish him such material as he might need to carry out his contract, and, on March 4th, 1903, sent the following communication to the engineer of the Drainage Commission:

“I hereby authorize you to pay such bills of the Fairbanks Company for material furnished for work at the Central Power Station, under my contract, as I may approve, and charge the same to my account with the Drainage Commission.”

On the same day, the engineer wrote as follows to the Fairbanks Company enclosing a copy of Tlielan’s letter:

“When he (Thelan) has completed his work satisfactorily he will have to his credit in this office the above amount (over $6000), out of which I will pay you such bills as he approves as being correct for material for this work. I would further state that this office withholds from the contractor an amount equal to all claims filed in this office before his final pay[324]*324ment becomes due until such time as these claims are satisfactorily settled.”

On August 24th, 1903, the Fairbanks Co. served on the Sewerage Board an itemized account of the goods sold to Thelan amounting to $4991.64, and a notice that a lien against this- material had been placed on record in May.

When Thelan’s contract was terminated and the work had been accepted the Board filed a concursus proceeding or inter-pleader acknowledging a net liability to Thelan of $4985.20 under the contract and for extra work. It was further alleged that one Koib claimed $600 by virtue of an assignment by Thelan and that the Fairbanks Co. also made a claim on the fund and all three were cited to litigate their respective claims. The Fairbanks Company answered and asserted its right to receive from the funds the sum already mentioned as claimed by it. Thelan’s answer admitted the correctness of Kolb’s claim and asserted that the Fairbanks Co. had overcharged him bv the sum of $1350.32 for which a judgment was asked.

On February 6th, 1906, 'em joint motion of all parties in interest, the excess of the sum deposited in the registry of the '"ourt over the $1350.32, amount of Thelan’s counterclaim, was paid to the Fairbanks Co. Before the cause was tried, Thelan, who had an additional claim against the Sewerage Board for extra work which for reasons personal to himself, he had not previously presented, submitted to the Board a detailed bill therefor. The Board, after due consideration, concluded that the clami was excessive, and, on March 20th, 1906, filed a supplemental petition alleging the amount due for the extra work to be $438.25, which it deposited in the registry of the Court, and which, together with the previous deposit, discharged the Board’s debt. This suit, therefore, presents two distinct and separate controversies, one between the Sewerage Board and Thelan, the other between Thelan and the Fairbanks Co.

It was argued in this Court, as a preliminary issue that the proceeding of the Board by interpleader was improper and in ■opposition to the Code of Practice, the district judge overruled the exception on the ground that the concursus, under the circumstances of the case, was recognized and sanctioned by our jurisprudence. Without questioning the correctness of that view, [325]*325we shall rest our affirmance of the ruling on the ground that the filing of an answer to the merits, before presenting the exception, must be deemed a waiver of objection to the mode of procedure.

10 An. 20, 18 An. 65, 31 An. 679.

It is admitted that the only two items in dispute between the Board and Thélan are:

First — The item for changing eight inch valves on nine boilers, to bring same off boilers and butting on steam header, mechanics time and helpers; for which Thelan claimed $1350, and the Board allowed him $450.

Second — Taking down old sixteen inch steam header, eighteen inch pipe from boiler to engines and holders, mechanics time and helpers, for which Thelan claimed $616, and the Board allowed him $169.97.

The amount in dispute is, therefore $1346.03.

Thelan testified to the correctness of his claim by referring to a book in which he made, every week, entries based on information furnished him by his foreman.

Then was not on the scene all of the time, though he says he was there most of the time. He did not know the facts and could not assert that the statement was true, merely that he believed the bill to be correct because he had confidence in his foreman. The foreman was not produced as a witness. An objection made to Thelan’s use of the book and to his testimony based thereon was overruled and a bill reserved. The ruling was erroneous.

“Where the witness neither recalled the fact, nor remembered to have recognized the written statement as true, and the writing was not made by him, his testimony; so far as it is founded upon the written paper, is but hearsay; and a witness can no more be permitted to give evidence of his inference from what a third person has written, than from what a third person has said.”

1 Greenleaf on Ev. p. 486.

The testimony should have been excluded and we shall not consider it. Jules Simmon, an employe of the Board and an engineer, who was on duty at the Central Power Station during the time Thelan was working on the header, kept, under instruc[326]*326tions, a book in which he entered every day, the time of the men engaged in the work. _His report gives the names of the workmen and shows that during the months of October, November and December, the machinists worked 128 hours and the laborers 410 hours.

Kirkland, another engineer of the Board in charge of the matter, basing himself on Simmon’s figures, allowed Thelan 128 hours of mechanics at 35 cents per hour, total, $44.80, and 410 hours for laborers at 18 1-3 cents per hour, total, $75.17, for a foreman and as profit on the work he allowed $50 more.

These figures aggregate $169.70, the amount tendered by the Board for the header.

As to the first item (i. e. changing valves on boilers), Kirkland says he allowed $450, in accordance with the custom, which is to pay the cost of the work and a margin of about 15 or 20 per cent for the profit, when no price has been agreed upon in advance.

Robert E. Lee, a well-known machinist to whom the Board submitted Thelan’s charges for an opinion, testifies that a fair remuneration for removing the boilers would be $375, and that $75 more would be a liberal profit.

Other witnesses corroborate the views of Kirkland Lee, at least to the extent that it should have taken less working time and fewer workmen than Thelan claims. Certain witnesses say that Thelan’s work was worth the amount he charged and even more, for instance, one, Cunningham thinks that Thelan was entitled to $25 a day for supervision; another, Gueydan, states that he would not have done the work for less than $10,000, and a third, McCorkingdale;. that the charge was moderate, though he could and did not make any specific calculation or estimate.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
4 Teiss. 322, 1907 La. App. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sewerage-water-board-v-thelan-lactapp-1907.