Sewell v. Sewerage & Water Board of New Orleans

697 F. App'x 288
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 28, 2017
Docket17-30089 Summary Calendar
StatusUnpublished
Cited by11 cases

This text of 697 F. App'x 288 (Sewell v. Sewerage & Water Board of New Orleans) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sewell v. Sewerage & Water Board of New Orleans, 697 F. App'x 288 (5th Cir. 2017).

Opinion

PER CURIAM: *

This case arises out of the Southeast Louisiana (“SELA”) Drainage Project, a federally funded enterprise cosponsored by the Sewerage and Water Board of New Orleans (“SWB”) and the United States Army Corps of Engineers (“Corps”). The SELA Project involves extensive construction at multiple sites in Southeast Louisiana and is intended to improve flood control and drainage in these areas. The instant case involves eight consolidated lawsuits implicating seven phases of the SELA Project in Uptown New Orleans, where the Plaintiffs own of homes and businesses. Each Plaintiff sued SWB alleging various forms of damage resulting from the construction. SWB then filed third-party claims against three contractors who were selected to construct SELA projects in Uptown New Orleans: B & K Construction Company, LLC; Boh Bros. Construction Company, LLC; and Cajun Constructors, LLC (collectively, the “Contractors”). The Contractors removed to federal court pursuant to the federal officer removal statute. See 28 U.S.C. § 1442(a)(1).

In September 2016, the Contractors moved for summary judgment, raising government contractor immunity as a defense to all remaining claims. The district court heard oral argument on the Contrac *291 tors’ motions for summary judgment on September 28, 2016. At that time, the district court “believed the Contractors had established their immunity defense, at least in part, on six of the [SELA Project] phases and, in whole, on the seventh phase.” Nevertheless, pursuant to SWB’s motion under Federal Rule of Procedure 56(d) and in the interest of fairness, the district court granted SWB an additional thirty days of discovery “to persuade the Court that there ... exist[s] a genuine dispute of fact concerning the second and third prongs of the Boyle test.” SWB was unable to convince the court, however, and in December 2016, the district court granted summary judgment in favor of the Contractors on the basis of government contractor immunity. On January 5, 2017, the district court issued an order declining to exercise supplemental jurisdiction over the state law claims remaining in the litigation and remanding the case to state court. This appeal followed. 1

“We review a summary judgment de novo, ‘using the same standard as that employed by the district court under Rule 56.’ ” In re Katrina Canal Breaches Litig., 620 F.3d 455, 459 (5th Cir. 2010) (quoting Kerstetter v. Pac. Sci. Co., 210 F.3d 431, 435 (5th Cir. 2000)). Summary judgment is appropriate “if the movant shows that there is no genuine issue as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). We use an abuse of discretion standard, however, when reviewing a district court’s discovery-related rulings, such as a denial of a Rule 56(d) motion or a decision to limit discovery. Fed. Ins. Co. v. Singing River Health Sys., 850 F.3d 187, 194 (5th Cir. 2017); Crosby v. La. Health Serv. & Indem. Co., 647 F.3d 258, 261 (5th Cir. 2011); see also Fed R. Civ. P. 56(d) (allowing a court to defer a motion or grant additional discovery when the movant can show, “by affidavit or declaration that, for specified reasons, it cannot present facts essential to justify its opposition”).

Contractors hired by the federal government are shielded from liability subject to certain conditions. This defense is “derived from the government’s immunity from suit where the performance of a discretionary function is at issue.” Kerstetter, 210 F.3d at 435 (citing Boyle v. United Techs. Corp., 487 U.S. 500, 511, 108 S.Ct. 2510, 101 L.Ed.2d 442 (1988)). To establish government contractor immunity, a contractor must meet the test set out by the U.S. Supreme-Court in Boyle: “(1) the government must have approved ‘reasonably precise’ specifications; (2) the equipment must have conformed to these specifications; and (3) the supplier/contraetor must have warned of those equipment dangers that were known to the supplier/contractor, but not to the government.” Id. (citing Boyle, 487 U.S. at 512, 108 S.Ct. 2510). Although this appeal is nominally about whether the district court erred in applying government contractor immunity, SWB’s argument on.appeal relates mainly to discovery. Specifically, SWB argues that its due process rights were violated by the brevity of the pre-trial discovery process, that the district court should have afforded it more time to conduct discovery pursuant to Rule 56(d), and that the district court’s summary judgment ruling was premature in light of SWB’s specific requests for further discovery.

The district court did not abuse its discretion in issuing or making its discovery rulings. This case was first removed to federal court on July 30, 2015. In January 2016, SWB declined to participate in a discovery conference with the Plaintiffs, *292 contending that a conference would be premature. From April through August 2016, the magistrate and district court judges held a series of discovery scheduling and status conferences, eventually extending the deadline for the Contractors’ motions for summary judgment to September 6, 2016. Following oral argument on September 28, the district court granted SWB an additional thirty days to conduct discovery on the second and third prongs of the Boyle test.

It appears that the district court reasonably responded to SWB’s discovery requests while also trying to move the case along and accommodate the numerous parties in the litigation. From the time the case was removed to federal court, SWB had fourteen months to conduct discovery relating to the Contractors’ government contractor immunity defense. The district court ultimately made its summary judgment ruling with the benefit of hundreds of pages of detailed designs and specifications produced by the Corps regarding all of the SELA projects at issue, as well as the deposition testimony of John Fogarty, the Corps’s resident engineer and administrative contracting officer. Even without addressing the Contractors’ arguments that SWB was dilatory in performing discovery, we find that the district court did not abuse its discretion in setting discovery deadlines, nor did it rule prematurely.

Regarding the substantive issue of government contractor immunity, SWB only meaningfully challenges summary judgment on the first Boyle prong. “The first Boyle step requires that the government approved reasonably precise specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
697 F. App'x 288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sewell-v-sewerage-water-board-of-new-orleans-ca5-2017.