Seward Park Housing Corp. v. Greater New York Mutual Insurance

25 Misc. 3d 772
CourtNew York Supreme Court
DecidedJuly 21, 2009
StatusPublished
Cited by1 cases

This text of 25 Misc. 3d 772 (Seward Park Housing Corp. v. Greater New York Mutual Insurance) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seward Park Housing Corp. v. Greater New York Mutual Insurance, 25 Misc. 3d 772 (N.Y. Super. Ct. 2009).

Opinion

OPINION OF THE COURT

Louis B. York, J.

[774]*774Plaintiff has moved to preclude defendant’s expert, William Berkowitz, from testifying as to whether the plaintiff rebuilt the collapsed garage “as soon as reasonably possible” as required by the insurance policy. The Appellate Division had modified the court’s decision with regard to this clause (43 AD3d 23 [2007]). It decided that the court had erred in finding that the defendant insurance company had repudiated the insurance policy and remanded on the issue, inter alia, whether the garage was rebuilt as soon as reasonably possible. Defendant has cross-moved to prevent plaintiffs expert, Jerome Haims, from testifying as to actual cash value.

The Appellate Division’s remand states that this is a question of fact that should have been submitted to the jury. If the jury determines that the garage was built as soon as was reasonably possible, the jury’s prior damages award on that issue has already decided the replacement cost. But if the jury decides that the rebuilding did not occur within a reasonable time, then the plaintiff is limited to the actual cash value which would have to be decided by the current jury.

In his “Expert’s Report,” Berkowitz opined on whether the reconstruction occurred within a reasonable time. To do this, he separated the plaintiffs efforts into five separate categories. They are (1) the forensic investigation of the entire garage to see if the uncollapsed portion could be salvaged; he asserts that this was delayed for IV2 months; (2) the selection of an architect to design the new garage, which he claims was delayed 41/2 months; (3) a delay of 2V2 months in the designing of the project; (4) an unreasonable delay of 6V2 months in the bid phase; and finally, (5) the actual construction of the new garage, which he opines was delayed three months. These delays add up to an unreasonable delay of 18 months.

There are a variety of reasons for granting plaintiffs motion to preclude this witness from testifying. First and foremost, the Appellate Division’s remand stipulated that the question of whether plaintiffs actions occurred within a reasonable time should go to the jury. Moreover, this is clearly an ultimate fact which is to be decided by the jury and the answer to it will directly impact the type of liability the defendant is exposed to and the measure of damages. By and large, expert witnesses should be prohibited from usurping the jury’s function (Nevins v Great Atl. & Pac. Tea Co., 164 AD2d 807, 809 [1st Dept 1990]), except in the most complicated, technical and scientific questions “beyond the ken” of the average juror (De Long v County of Erie, 60 NY2d 296, 307 [1983]), which this is not.

[775]*775Mr. Berkowitz’ resume states that he is a principal of Alliance Construction Consultants. For the past 20 years, he has been a professional consultant specializing in the resolution of construction disputes. Prior to his present professional involvement, he spent 16 years managing public and private construction projects. He was a project manager for a general contractor for five years. He has a B.S. degree in civil engineering and a M.S. degree in construction management, and is licensed as a professional engineer in New York State.

Modern juries are fully capable of making sensible decisions using their common sense and “practical experience” (Havas v Victory Paper Stock Co., 49 NY2d 381, 386 [1980]). Finally, the expert’s opinion should be derived from some objective criterion which allows others to duplicate the process by which he arrives at that opinion, not the ipse dixit conclusions reached by this expert.

Berkowitz certainly has the expertise to describe the process by which a collapsed job is rebuilt, and to break down that process into the categories he has described in his reports to the defendant. If he has participated in such a project, he may describe that and testify to the time it took to finish those categories in that project. But he cannot testify as to his opinion of the time it should have taken for plaintiff to rebuild, and he is precluded from offering his opinion as to whether the garage was rebuilt as soon as was reasonably possible.

We now turn to defendant Greater New York Mutual Insurance Co.’s (GNY) cross motion to preclude Jerome Haims, Seward’s real estate appraisal expert, from testifying on behalf of Seward regarding the actual cost value (ACV) of the garage at the time of collapse. In his expert report, Haims explains he relied on the “Cost Approach” method to determine his ACV figures for the collapsed garage. GNY argues that Haims’ testimony should be precluded because the replacement cost value (RCV) he relies on to make a determination of ACV is higher than the RCV determination made by the jury in the first trial. GNY argues that Haims then deducts values for depreciation and improvement that did not exist in the original garage. GNY further alleges that Haims’ ACV calculation relied on items not related to replacement cost because they did not exist before the collapse of the garage, and that Haims improperly relies on testimony of Seward’s other experts, Tal Eyal and Robert Lawless.

GNY argues that the RCV arrived at by the jury in the first trial should be determinative in Haims’ ACV computations. It [776]*776claims that collateral estoppel bars Seward from relitigating the RCV already determined by the jury. GNY argues that Haims’ analysis should not be permitted because he “rejects the jury’s determination of replacement cost and relies on evidence that has been rejected and discredited by the jury.” GNY contends that Haims should rely not on Eyal’s testimony, but rather on the determination of RCV made by the jury minus the property-not-covered portions of the jury award.

Seward, on the other hand, asserts that the jury award vacated by the Appellate Division has no preclusive effect on Haims’ testimony. Seward claims that collateral estoppel does not apply and that Haims’ testimony should be admitted under the “Broad Evidence” rule. Seward contends that ACV was not deliberated over or determined by the jury in the first trial. As support, Seward points to this court’s April 10, 2008 restitution decision to advocate that ACV was not considered at the first trial. Seward argues that the Appellate Division’s decision vacated the award in its entirety and ordered a new trial; therefore there are no limitations on the methods of proving the ACV damages. Seward argues that the court should allow the jury to hear a broad variety of evidence in order to determine the ACV including evidence such as the testimony of witnesses, cost of repair, and full replacement cost value.

The doctrine of collateral estoppel generally exists to reduce litigation in the courts and preserve judicial resources. (See Kaufman v Eli Lilly & Co., 65 NY2d 449, 455 [1985].) Collateral estoppel bars a party from relitigating an issue that has already been decided as a matter of fairness and as an attempt to avoid inconsistent results. (Id.) The courts generally demand two requirements be satisfied in order for collateral estoppel to apply: identity of issue, which issue has been decided in the prior action and is decisive in the present action, and the party to be precluded from raising the issue must have had a “full and fair opportunity” to litigate the issue. (Id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seward Park Housing Corp. v. Greater New York Mutual Insurance
70 A.D.3d 468 (Appellate Division of the Supreme Court of New York, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
25 Misc. 3d 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seward-park-housing-corp-v-greater-new-york-mutual-insurance-nysupct-2009.