Severin v. United States

86 Ct. Cl. 53, 1937 U.S. Ct. Cl. LEXIS 137, 1937 WL 3204
CourtUnited States Court of Claims
DecidedDecember 6, 1937
DocketNo. 42480
StatusPublished
Cited by1 cases

This text of 86 Ct. Cl. 53 (Severin v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Severin v. United States, 86 Ct. Cl. 53, 1937 U.S. Ct. Cl. LEXIS 137, 1937 WL 3204 (cc 1937).

Opinion

[73]*73OPINION

Whaley, Judge,

delivered the opinion of the court:

This suit is brought to recover upon a contract between the plaintiffs, doing business as N. P. Severin Company, and the United States, represented by U. S. Grant, 3d, Executive and Disbursing Officer, Arlington Memorial Bridge Commission, as contracting officer. Plaintiffs agreed to furnish all labor and material and perform all work required for the construction of the Boundary Channel Bridge of the Arlington Memorial Bridge Project, Washington, D. C., in accordance with their accepted bid and specifications, schedules, and drawings which were made a part of the contract, for the consideration of $338,000, together with certain unit prices for possible additional contract work. The work was to commence on or before January 28, 1929, and to be finished on or before February 2, 1930. The work was completed and accepted September 17, 1930.

In the aspect of the case, as it is presented, plaintiffs claim the right to recover cost, overhead, and profit on so much of the work as was due to changed conditions resulting from the actions of defendant in imposing certain obligations upon the plaintiffs which were not set forth in the specifications or the contract.

[74]*74The two main contentions are (1st) that, after the contract was entered into, the Government pumped filling material on Columbia Island on which the East end of the bridge was to be erected, resulting in a heavy layer of silt being deposited within the neat lines of the site, and also adjoining thereto, which required the plaintiffs to remove the same before work could be commenced, and (2nd) that the rock lines, as shown on the drawings, did not give accurate information as to true conditions, resulting in misleading the plaintiffs, because when the rock, as indicated on the drawings, was reached no bedrock was found but only rotten rock and gravel which necessitated plaintiffs’ excavating to a much greater depth, entailing the pouring of large quantities of concrete, delaying the work and retarding other work to the complete disruption of the progress schedule for the completion of the contract. There are other items of extra work and damages sustained, for which plaintiffs sue, but the two claims- mentioned above are the ones on which the case is mainly based.

A determination of this controversy requires reference to certain parts of the contract and specifications and the notice to bidders. It should be mentioned at this point that the plaintiffs were contractors who had undertaken large contracts for the erection of private residences, post-offices, and schools but had never before undertaken the construction of a bridge of any considerable size, and were unfamiliar, from inexperience, with contract work in rivers and harbors.

Under the terms of the contract it was provided that the contracting officer might, by written order, change the drawings or specifications within their general scope and the contract prescribed the method of determining the ultimate decrease or increase in prices. It further provided that, if subsurface conditions at the site materially differed from those shown on the drawings or indicated in the specifications, the contracting officer should immediately make the necessary changes in the drawings and specifications and the contract price should be adjusted by methods set forth therein; that no charge for extra work and material would be allowed unless such work was ordered in writing and [75]*75allowed by the contracting officer and the price stated in the order; that in case of delay, due solely to the fault of the contractors, liquidated damages were assessable, and the facts and the extent of the delay to be found by the contracting officer were to be final and conclusive on both parties, subject only to appeal to the head of the department.

The specifications were sent to the contractors for the purpose of having their bid made from the requirements thereof.

I. DREDGING ON COLUMBIA ISLAND

Article 10 of the specifications provides:

Bidders to visit site. — Bidders are expected to visit the site of. the work and to inform themselves as to all existing conditions, and also to inform themselves as to the progress and schedules of all work which may be under way or contemplated, such as the dredging operations on and around Columbia Island, etc. Failure to do so will in no way relieve the successful bidder from the necessity of furnishing all equipment and materials and performing all work required for the completion of the contract in conformity with the specifications.
No allowance will be made for the failure of a bidder correctly to estimate the difficulty attending the execution of the work. [Italics ours.]

There was also provided in Article 26 of Section II of the Specifications the following: .

Columbia Island and dredging operations. — Columbia Island has been built up to a height of 16 to 20 feet by dredging from the river channel. The dredging was discontinued during the summer of 1927, but it is likely to be resumed by the time the work of this contract is started or very shortly thereafter, and will be continued indefinitely until dredging work contemplated upon this project is completed. The dredging of the water gate at the Washington end of the bridge will also be started before the work of this contract is finished. The sched-dule of dredging operations can be obtained at the United States Engineer Office, Washington, D. C.
The contractor shall arrange his work so that the dredging may be done without interference from his operations; also he shall protect the dams and levees on Columbia Island against any damage due to the prose[76]*76cution of Ms work, and shall immediately make good at his own expense any damage which may be so occasioned. [Italics ours.]

Under Article 27 there is the following paragraph:

* * * The contractor shall so conduct his operations . as to allow all other construction work on the Arlington Memorial Bridge project, whether started previously to or after the 'beginning of the work contemplated herein, to proceed as easily as practicable, and he shall provide for and allow the joint occupancy and joint use of all Government-owned land and facilities by all other contractors and (or) agencies engaged in such construction work. * * * [Italics ours.]

Prior to making their bid, plaintiffs visited the site of the project, saw that dredging operations had been performed on Columbia Island and that the dredge was then in the river at the site but actual operations had been suspended. Subsequently, after the contract had been signed, dredging operations on Columbia Island were again commenced and there was poured and deposited upon the site and the surrounding land, a heavy layer of silt which it was found by the contractors necessary to be removed before actual operations on the East end of the work could be commenced. Plaintiffs protested to the contracting officer that the removal of this additional fill was outside of the contract, and the contracting officer authorized its removal. The contracting officer gave plaintiffs a written order to remove 3,618 cubic yards of earth at the East end of the bridge on Columbia Island and authorized payment under Article 33 of the Specifications reading as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

P.R. Burke Corp. v. United States
58 Fed. Cl. 549 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
86 Ct. Cl. 53, 1937 U.S. Ct. Cl. LEXIS 137, 1937 WL 3204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/severin-v-united-states-cc-1937.