Sevenson Environmental Services, Inc. v. New York State Thruway Authority

149 Misc. 2d 268, 561 N.Y.S.2d 523, 1990 N.Y. Misc. LEXIS 545
CourtNew York Court of Claims
DecidedOctober 17, 1990
DocketClaim No. 79858
StatusPublished
Cited by3 cases

This text of 149 Misc. 2d 268 (Sevenson Environmental Services, Inc. v. New York State Thruway Authority) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sevenson Environmental Services, Inc. v. New York State Thruway Authority, 149 Misc. 2d 268, 561 N.Y.S.2d 523, 1990 N.Y. Misc. LEXIS 545 (N.Y. Super. Ct. 1990).

Opinion

OPINION OF THE COURT

Louis C. Benza, J.

Defendant, by motion No. M-42668, has moved for summary judgment dismissing this claim on the various grounds asserted as the first, second, third and fifth defenses in its answer. The claimant, by cross motion No. CM-42791, has cross-moved for summary judgment, for dismissal of the above-mentioned defenses, and for other relief. The claimant, by motion No. M-42010, had previously moved to vacate or modify the defendant’s demand for a verified bill of particulars. That motion was adjourned without date and will be addressed herewith.

The claim arises from the rehabilitation by claimant of the northbound South Grand Island Bridge pursuant to a contract entered into on December 20, 1984 between claimant and the New York State Thruway Authority (hereinafter Authority). The contract was approved by the State Comptroller on March 12, 1985. The contract contained a policy statement of the Authority concerning the need for minority businesses to participate in Authority contracts. The contract also specified the minority business enterprise requirements to be met by [270]*270the contractor in order to qualify for an Authority contract. It also required the contractor to use "good faith” efforts to attain the minority/women’s business enterprise (M/WBE) goals of the contract.

Prior to the contract’s approval by the Comptroller, claimant submitted to the Authority documentation of its efforts in achieving the minority participation required by the contract.

This project proceeded rapidly, and claimant, pursuant to the contract, received a $500,000 early-completion bonus. During the course of the work, the Authority became aware of possible noncompliance by claimant with the M/WBE provisions of the contract. By letter dated October 15, 1985 the Authority notified claimant of this situation. It also advised claimant that it was withholding future estimates until claimant complied with the affirmative action provisions of the contract and that an investigation of claimant’s noncompliance was in progress. The Authority’s investigation concluded with a finding that claimant failed to maintain good-faith efforts to meet the affirmative action requirements of the contract concerning its minority subcontracts, and also that claimant did not comply with the minority representation requirements for women trainees. By letter dated December 27, 1985 the Authority’s Director of Affirmative Action notified claimant of this determination and afforded claimant the opportunity for a meeting in the form of a conciliation conference. The conference was held on January 7, 1986, and claimant appeared by Michael Elia, its vice-president. As a result of the meeting, the Authority found that claimant breached its contract by not exercising good faith in its subcontracting of the work to minority firms. By letter dated April 16, 1986 the Authority notified claimant of its determination and that it had recommended that the sum of $88,372.45 be deducted from the contract price to reflect the lost value of M/WBE subcontractor work on the project.

The defendant asserts that the claim should be dismissed as it fails to state a cause of action; that claimant’s only remedy is by seeking judicial review of the Authority’s decision pursuant to a CPLR article 78 proceeding, but that such review is now barred by the applicable Statute of Limitations. The defendant also asserts that the claim is barred by res judicata based upon the determination of the Authority, and that the court lacks subject matter jurisdiction over the claim.

The court finds and concludes that claimant has stated a [271]*271cause of action. Claimant alleges that a contract existed between the parties; that claimant completed its obligations under the contract, and that the defendant breached the contract by failing to pay claimant $88,372.45 due and owing to it under the contract. Upon a review of the pleadings and all the papers before the court, and after hearing oral argument on the motions, the determinative issue to be decided is whether the Authority had the contractual right to deduct money from claimant’s final payment as a charge for breaching the minority participation provisions of the contract.

Attached to the defendant’s motion papers are pages 199 through 207 of the contract, which contain State and some Federal requirements applicable thereto. On page 204, under the heading "Procedure”, the contract provides:

"A contractor’s failure to attain both the MBE and WBE goal, or to satisfactorily document their 'good faith efforts’* and failure to attain same can result in forfeiture of the amount of the deposit pursuant to Section 103-02 of the Standard Specifications * * *. In cases of a contractor’s failure to fulfill the requirements of this provision, the Department reserves the right to award the contract pursuant to Section 103-01 of the Standard Specifications.
" * Good faith efforts as operationally defined and interpreted by NYS DOT as provided in Form AAP-10.”

Further, on page 207, in paragraph 8, under that portion of the contract dealing with "Requirements, Terms and Conditions of Minority Business Enterprise Program”, the contract provides:

"Where the Director, T.A.A.P.O. [Transportation Affirmative Action Program Office] finds that the contractor has failed to comply with the requirements of this Minority Business Enterprise Program, said officer will immediately notify the contractor to take corrective action.
"Where the contractor has been found to have failed to exert every good faith effort * * * to involve minority business enterprise in the work provided, the [Authority] may declare that the contract is terminated by reason of the contractor’s default, and/or may declare that the contractor is ineligible to receive further [Authority] funds, whether as a contractor, subcontractor, or as a consultant, for a period of up to three years.”

Based upon these two above-quoted provisions of the con[272]*272tract, the court finds and concludes that the Authority had four options if it was found that claimant had failed to comply with the affirmative action provisions of the contract:

1. declare claimant had forfeited its bid deposit;

2. award the contract to another contractor;

3. declare the contract be terminated by reason of the default; and/or

4. declare the contractor ineligible to receive further Authority funds for a period of three years.

Attached to claimant’s cross motion, as exhibit A, is the agreement entered into between claimant and the Authority. Article 8 of the agreement provides that the Authority can withhold payment if a proper and lawful direction given by the Authority concerning the work or material supplied by the contractor is not complied with. The court finds and concludes that the affirmative action provision of the contract has no relation to the work or material supplied by the contractor. Article 8 is the only provision of the contract under which the Authority is authorized to withhold money from claimant. The Authority did not choose any of the four options available under that portion of the contract dealing with "Procedure” and "Requirements, Terms and Conditions of Minority Business Enterprise Program”; instead, it chose to deduct $88,372.45 which, it claims, is the lost value of M/WBE subcontractor work on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alvarado v. Alvarado
45 Misc. 3d 412 (New York Supreme Court, 2014)
Bausch & Lomb Inc. v. Bressler
977 F.2d 720 (Second Circuit, 1992)
Bausch & Lomb Incorporated v. Bernard Bressler
977 F.2d 720 (Second Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
149 Misc. 2d 268, 561 N.Y.S.2d 523, 1990 N.Y. Misc. LEXIS 545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sevenson-environmental-services-inc-v-new-york-state-thruway-authority-nyclaimsct-1990.