Sette-Juliano Contracting, Inc. v. Aetna Casualty & Surety Co.

246 A.D.2d 142, 674 N.Y.S.2d 654, 1998 N.Y. App. Div. LEXIS 7450
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 23, 1998
StatusPublished
Cited by3 cases

This text of 246 A.D.2d 142 (Sette-Juliano Contracting, Inc. v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sette-Juliano Contracting, Inc. v. Aetna Casualty & Surety Co., 246 A.D.2d 142, 674 N.Y.S.2d 654, 1998 N.Y. App. Div. LEXIS 7450 (N.Y. Ct. App. 1998).

Opinion

OPINION OF THE COURT

Mazzarelli, J.

In 1991, the City of New York awarded a public-improvement construction contract (Contract) to defendant Sette-Juliano Construction Corp ./Land-Site Contracting Corp. (S-J Land) for the reconstruction of Hudson Street in Manhattan. The project included water main work, and S-J Land hired plaintiff Sette-Juliano Contracting, Inc./Halcyon Construction Corporation (S-J Halcyon) as a subcontractor to perform this and other work.1 The project also required S-J Halcyon to perform certain [145]*145“utility interference work.”2 Pursuant to the Contract, defendants-appellants The Aetna Casualty and Surety Company and United States Fidelity and Guaranty Co. (Sureties) issued a performance bond and a payment bond on behalf of S-J Land, and the City as obligee, guaranteeing performance of the work and payment for labor and materials furnished by persons performing work under the contract. The amount of each bond was $23,667,940, the same amount as the contract.

In April 1994, plaintiff filed a “notice under mechanic’s LIEN LAW FOR ACCOUNT OF PUBLIC IMPROVEMENT” pursuant to Lien Law § 5, in the amount of $1,346,328. Plaintiff alleged that it was owed this amount for work it had performed and the materials it had furnished to S-J Land in the performance of the contract. By letter dated April 13, 1994, plaintiff also submitted a claim against the payment bond for the same amount. To discharge the mechanic’s lien, the Sureties posted an undertaking in the amount of $1,467,497.50 (lien-discharge bond) pursuant to Lien Law § 21 (5). The lien-discharge bond obligated the Sureties to pay “any judgment which may be rendered in an action for the enforcement of said lien, not exceeding the sum of [$1,467,497.50].”

In October 1994, Aetna’s counsel informed plaintiff that it considered the amounts claimed in the mechanic’s lien and on the payment bond “wildly exaggerated,” and that Aetna would not make any payments until the dispute between S-J Land and plaintiff was “judicially determined.” Pursuant to the terms of the subcontract, plaintiff commenced an arbitration proceeding in November 1994, seeking an unpaid balance of $1,347,328, plus interest and damages in an undetermined amount. The Sureties were apprised of the pendency of the arbitration proceedings, but were not made parties thereto. At the arbitration hearing, plaintiff contended that it had performed the water main and utility interference work and was owed $3,948,748.84. Plaintiff acknowledged it had been paid $2,778,114.48, leaving an unpaid balance of $1,170,634.36, plus $78,885.46 in lost profits. On June 12, 1996, the arbitrators awarded plaintiff a lump sum of $1,099,994.94, without any explanation as to the basis for such award. Plaintiff commenced a proceeding in the Supreme Court to confirm the award, and judgment was entered against S-J Land, on default, in the amount of $1,099,994.94, plus interest.

[146]*146In May 1995, S-J Land advised the Sureties that it could no longer perform its obligations under the main contract. S-J Land assigned the contract to another contractor, Judlau Contracting, with the Sureties’ consent. In May 1996, plaintiff commenced the instant action, alleging that S-J Land’s default prevented plaintiff from completing performance of the work, and that plaintiff was owed $1,023,901.81 for unpaid amounts for labor and materials. Plaintiff’s first cause of action sought to foreclose the mechanic’s lien and for judgment against the Sureties under the lien-discharge bond. The second cause of action sought recovery from Aetna under the payment bond.3

In November 1994, plaintiff moved for partial summary judgment on its first and second causes of action in the amount of $1,021,109.48, plus interest. The amount requested represented the amount of the arbitration award ($1,099,994.94), minus the amount of “lost profits” sought in the arbitration proceeding ($78,885.46), as plaintiff conceded that there might be a question as to whether this portion of the arbitrator’s award was covered by the lien-discharge bond and the payment bond.

The Sureties opposed the motion, arguing that in order to recover under the lien-discharge bond, the plaintiff had to establish the validity of the mechanic’s lien and that the items and amounts for which recovery was sought were properly chargeable against the Sureties. The Sureties contended that because the $1,099,994.94 arbitration award was made in lump-sum form, without any explanation as to what work or materials it represented, it was impossible for the court to summarily determine that the validity of the lien had been established, and that the entire amount of the award was chargeable against them under the lien-discharge bond and payment bond. Additionally, the Sureties argued that plaintiff sought recovery at the arbitration for utility interference work that, it asserted, was not covered by the mechanic’s lien or the payment bond. Since the possibility existed that the arbitration award included amounts for this utility interference work, the Sureties claimed that summary judgment should not be granted on the basis of that award.

The IAS Court granted plaintiff’s motion for partial summary judgment on its first and second causes of action. Initially, the court found that the Sureties had “sufficiently participated” in the arbitration proceeding so as to bind them [147]*147to the determination. However, the court acknowledged that the arbitrator’s decision was not conclusive as to the mechanic’s lien itself, or whether the amount of the award is chargeable against the Sureties under the payment bond, but was only conclusive as to the value of the labor and materials. The court rejected the Sureties’ claim that the award included amounts for work not covered by the lien and the payment bond (i.e., utility interference work) as “conclusory,” in the absence of supporting documentation. The court further determined that the utility work was “inseparable” from the water main work covered by the Contract.

Based on these determinations, the IAS Court found that the validity of the mechanic’s lien had been established based upon S-J Land’s nonperformance, and its failure to oppose the instant motion or the proceeding to confirm the arbitration award. The court noted that the judgment against S-J Land, even upon default, constituted “ ‘prima facie’ ” evidence against the Surety. The court also found the Sureties liable under the payment bond which, by its terms, gave plaintiff a direct right of action against the principal or Surety for the cost of labor and materials incurred during the performance of the Contract.

On appeal, the Sureties argue that the Supreme Court erred in granting plaintiffs motion for partial summary judgment based on the arbitration award. The Sureties contend that plaintiff made a $1,014,097.79 claim for utility interference work in arbitration; that such work is not covered by the payment bond, and may not be the subject of a public improvement lien, because the City is not liable for the cost of such work under the Contract; that such work was actually performed pursuant to a separate agreement between the utility companies and S-J Land; and that therefore the arbitration award likely included amounts not properly chargeable against the Sureties. We agree.

At the outset, we reject plaintiffs assertion that the arbitration award did not include any sums due for the utility work, but rather consisted only of costs that were bonded by the Sureties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flowcon, Inc. v. Andiva LLC
2021 NY Slip Op 06756 (Appellate Division of the Supreme Court of New York, 2021)
RRN Associates, Inc. v. Aetna Casualty & Surety Co.
263 A.D.2d 501 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
246 A.D.2d 142, 674 N.Y.S.2d 654, 1998 N.Y. App. Div. LEXIS 7450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sette-juliano-contracting-inc-v-aetna-casualty-surety-co-nyappdiv-1998.