Service Elec. Supply v. Hazlehurst Lumber

932 So. 2d 863, 2006 Miss. App. LEXIS 143, 2006 WL 464249
CourtCourt of Appeals of Mississippi
DecidedFebruary 28, 2006
Docket2004-CA-02135-COA
StatusPublished
Cited by7 cases

This text of 932 So. 2d 863 (Service Elec. Supply v. Hazlehurst Lumber) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Service Elec. Supply v. Hazlehurst Lumber, 932 So. 2d 863, 2006 Miss. App. LEXIS 143, 2006 WL 464249 (Mich. Ct. App. 2006).

Opinion

932 So.2d 863 (2006)

SERVICE ELECTRIC SUPPLY COMPANY, INC., Appellant,
v.
HAZLEHURST LUMBER COMPANY, INC., Appellee.

No. 2004-CA-02135-COA.

Court of Appeals of Mississippi.

February 28, 2006.
Rehearing Denied June 27, 2006.

*865 Derek Andrew Henderson, attorney for appellant.

Dennis L. Horn, Shirley Payne, Madison, attorneys for appellee.

EN BANC.

CHANDLER, J., for the Court.

¶ 1. Service Electric Supply Company, Inc. sold electrical parts to Magnum Industrial and Controls, Inc. for use in a building project owned by Hazlehurst Lumber Company, Inc. (HLC). Magnum was the general electrical contractor on the project. On October 1, 2002, Service Electric filed suit against HLC for the value of certain materials which Service Electric had delivered to the job site. HLC moved for summary judgment. Service Electric filed a response and a cross-motion for partial summary judgment.

¶ 2. The trial court granted summary judgment in favor of HLC and denied Service Electric's cross-motion for partial summary judgment. Service Electric appeals, arguing (1) that a letter from HLC to Magnum and Service Electric created a contractual relationship between HLC and Service Electric; (2) alternatively, that HLC is estopped from denying its liability to Service Electric; and (3) that the trial court should have granted Service Electric's motion for partial summary judgment *866 and entered a judgment for Service Electric in the amount of $13,787.05.

¶ 3. We find that Service Electric was not entitled to recover payment from HLC for any materials which Service Electric sold to Magnum. Therefore, we affirm the grant of summary judgment to HLC.

FACTS

¶ 4. HLC planned to add updated equipment to its lumber milling operation. On February 11, 1998, HLC contracted with Magnum to perform the electrical work for the project on a cost-plus basis, with the total cost of Magnum's work not to exceed $240,000. HLC agreed to pay Magnum for all materials used in the project at cost plus ten percent. The construction contract was memorialized as HLC's Purchase Order No. 24234.

¶ 5. Shortly thereafter, Ronnie Rogers, the owner of Magnum, informed Starke Albritton, HLC's operations manager, that he wished to purchase electrical supplies for the project from Service Electric. Rogers told Albritton that Larry Stickell, the owner of Service Electric, refused to sell to Magnum unless HLC promised to pay for electrical supplies by joint check payable to Magnum and to Service Electric. In response, Albritton executed the following letter:

February 20, 1998
TO: Terry Stickels [sic] and Ronnie Rogers
Hazlehurst Lumber Company agrees to pay for materials used on our project NO. 699-01 by joint check. The check will be made to Service Electric Supply and Magnum Industrial Power and Controls. This in no way affects the responsibility of Magnum to perform to the bid specifications (Dated 1/20/98) and does not in any way alter the purchase order currently in place.
Sincerely, s/Starke Albritton Starke Albritton, Operations Manager Hazlehurst Lumber Company

¶ 6. Rogers gave a copy of the letter to Stickell. According to Albritton, Stickell called him and asked if HLC was agreeing to pay for any and all materials ordered by Magnum. Albritton said HLC did not agree to pay for any and all materials ordered by Magnum, but only agreed to pay Magnum for parts with joint checks payable to Magnum and to Service Electric. Albritton emphasized that his contract for parts was with Magnum and that the total cost of parts and labor for the project was not to exceed $240,000. Stickell stated that Service Electric never would have sold materials to Magnum without the letter from Albritton agreeing to issue joint checks.

¶ 7. Magnum began ordering parts from Service Electric for use on the HLC project. Service Electric shipped the parts to Magnum at the HLC job site. A statement from Service Electric reveals that Service Electric billed Magnum for the parts. Albritton testified that, as the project progressed, Magnum submitted bills to HLC that included parts accountings from Service Electric. HLC paid several such bills by joint check made payable to Magnum and to Service Electric. The amount of each check reflected Magnum's cost for the parts plus his ten percent profit. Magnum endorsed each check and sent it to Service Electric, which endorsed and cashed the check. Per agreement with Magnum, Service Electric kept Magnum's ten percent profit as payment toward Magnum's debt to Service Electric for parts supplied on a prior construction *867 job.[1]

¶ 8. In April 1998, HLC noticed that Service Electric had overcharged Magnum for certain electrical parts. Magnum contacted Service Electric, which admitted having inadvertently overcharged Magnum. Service Electric issued credit memorandums for the overcharges. At the end of April, HLC instructed Magnum to cease ordering electrical supplies from Service Electric. For the next couple of months, previously ordered parts and their associated invoices continued to arrive from Service Electric.

¶ 9. In June 1998, HLC paid one of Magnum's bills for Service Electric parts with a check made payable to Magnum alone. This check was in the amount of $13,787.05. Albritton admitted that the check was supposed to have been made jointly payable to Magnum and to Service Electric. He averred that HLC's accounting office had inadvertently left Service Electric's name off the check. Magnum cashed the check. Rogers told Stickell that he planned to send the money to Service Electric. Stickell called Albritton and explained the situation. According to Albritton, he told Stickell that HLC would withhold payments from Magnum until Magnum paid the $13,787.05 to Service Electric.[2] In July 1998, Stickell told Albritton that Magnum had paid it, and HLC resumed payments to Magnum. Later, Stickell told Albritton that, in fact, Magnum had given him a bad check and Service Electric remained unpaid. Service Electric never recovered the $13,787.05 from Magnum.

¶ 10. In late spring and summer 1998, Magnum's work on the HLC project slowed and, by fall 1998, had stopped entirely. Several HLC employees observed Magnum employees removing electrical supplies from Magnum's on-site storage trailer. One of Magnum's employees stated that Magnum was transporting the supplies to other construction sites.

¶ 11. Due to Magnum's failure to perform, HLC was forced to hire other electrical contractors to complete the project. HLC stopped paying Magnum at the time it became apparent that Magnum was not going to complete the work. Albritton was uncertain whether its total payments to Magnum had met the contract price of $240,000.

¶ 12. Magnum never paid several of Service Electric's materials invoices. Service Electric sued to recover $33,420.35, the amount of the unpaid invoices, from HLC in contract or quantum meruit. Additionally, Service Electric moved on the ground of estoppel for a partial summary judgment in the amount of $13,787.05, for the check which HLC had made payable to Magnum alone. In its bench opinion granting summary judgment to HLC, the trial court found that Service Electric could not recover in quantum meruit because it had failed to show that it had a reasonable expectation that HLC would pay Service Electric for the materials. Rather, the court found, HLC had a contract with Magnum under which Magnum was to pay materialmen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKenzie v. Mississippi Municipal Service Co.
193 So. 3d 676 (Court of Appeals of Mississippi, 2016)
Noatex Corp. v. King Construction of Houston, LLC
864 F. Supp. 2d 478 (N.D. Mississippi, 2012)
Heritage Building Property, LLC v. Prime Income Asset Management, Inc.
43 So. 3d 1138 (Court of Appeals of Mississippi, 2009)
Sukup Manufacturing v. Rushing
634 F. Supp. 2d 694 (S.D. Mississippi, 2009)
Durose v. Grand Casino of Mississippi Inc.
251 F. App'x 886 (Fifth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
932 So. 2d 863, 2006 Miss. App. LEXIS 143, 2006 WL 464249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/service-elec-supply-v-hazlehurst-lumber-missctapp-2006.