Sepo v. Case

541 P.2d 1160, 25 Ariz. App. 176, 1975 Ariz. App. LEXIS 835
CourtCourt of Appeals of Arizona
DecidedNovember 6, 1975
Docket1 CA-CIV 3172
StatusPublished
Cited by4 cases

This text of 541 P.2d 1160 (Sepo v. Case) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sepo v. Case, 541 P.2d 1160, 25 Ariz. App. 176, 1975 Ariz. App. LEXIS 835 (Ark. Ct. App. 1975).

Opinion

*177 OPINION

STEVENS, Judge, Retired. 1

This special action has been presented to this Court following the entry of a summary judgment, being the third summary judgment in this litigation. The summary judgment here in question was preceded by an opinion of this Court and by an order in a subsequent special action which order is entitled “Prior Opinion Clarified.”

The opinion is the case of Sepo v. First National Bank of Arizona, 21 Ariz.App. 606, 522 P.2d 562 (1974), petition for review denied, Arizona Supreme Court cause number 11652-PR. The prior special action was determined by a memorandum decision in which Michael E. Sepo and Marie A. Sepo (Sepo) were the petitioners and the First National Bank of Arizona (Bank) was the respondent-real party in interest. The cause number is 1 CA-CIV 3068. The memorandum decision was filed on 22 May 1975 and will be hereinafter quoted in full. No motion for rehearing was directed to the memorandum decision and it became final. In fact, the Sepos and the Bank filed their separate motions with the trial court within days following the filing of the memorandum decision.

THE BACKGROUND

We refer to the above cited 1974 opinion for the background of this litigation. Since vital rulings were entered by summary judgment, “the facts” which we set forth herein have not been determined by a trial of the issues and are subject to proof on such a trial. “The facts” are sufficiently established to render summary judgment inappropriate under Rule 56, Rules of Civil Procedure, 16 A.R.S.

Briefly, Eaton established a subdivision trust with release prices for the various lots. Sterrer was a contractor who desired to improve the lots. Sterrer arranged with the Bank for financing. Sepo entered into an agreement with Sterrer to build a house and paid the release price in a sum in excess of $5,500 to the trust securing sufficient title to enable Sepo to secure mortgage construction financing from the Bank. There were specified time release payments to be made by the Bank to Sterrer and the Bank required that the Sepos constitute Sterrer their agent for the purpose of securing periodic draws as progress payments. This aspect of the case is considered in our opinion. Sepos became apprehensive concerning the progress of the construction of their house and complained to the Bank that the construction was not progressing properly and the Bank nevertheless continued to pay draws to Sterrer. Before the full amount of the mortgage had been drawn by Sterrer, Sterrer was unable to complete the house.

The Bank sued on the note and to foreclose the mortgage in February 1971. The Sepos defended and asserted a counterclaim. The Bank received a summary judgment of foreclosure. The trial court drastically limited the issues to be tried on the counterclaim and the Sepos recovered a judgment of $1,750 on their counterclaim.

The judgment of foreclosure and the judgment in favor of the Sepos were entered February and March of 1972. (These dates are stated as approximate dates as the original Superior Court record is not now before this Court.) There was a timely appeal by the Sepos from both judgments without the posting of a supersedeas bond. On 5 December 1972 the Bank sold the property in question to third parties, who are not parties to this litigation, for $15,000.

This Court rendered its opinion on the appeal on 21 May 1974 and, following the Supreme Court’s denial of the petition for review, issued its mandate on 11 December 1974. By its opinion this Court set aside the summary judgment of foreclosure and without specifying the details of the error in the restricting of the Sepo proof of *178 their counterclaim, granted the Sepos a new trial thereon.

As recited in the opinion, the Sepos and the Bank early in their relationship entered into an “Offer of Commitment” one portion thereof reading as follows:

“4. Sterrer Enterprise will furnish First National Bank of Arizona with a completion bond.”

Unilaterally, and without the knowledge of the Sepos, the Bank did not require Sterrer to comply with this provision of the offer of commitment. In our opinion we stated:

“The trial court found it (the above quoted paragraph) to be a condition precedent, and we accept that determination for the purposes of our analysis.” 21 Ariz.App. at 609, 522 P.2d at 565.

We further stated:

“The bond recited in the offer is not an indemnity bond to compensate only the bank for the losses suffered by Sterrer Enterprises’ failure to complete the building. It is a bond which would guarantee the completion of a building in which the Sepos had an executory interest. If such a bond had been obtained, the Sepos and the bank would have had a fund from which to complete the construction. The Sepos would have had an equitable interest in that fund. Restatement, Restitution § 125(2), Comment (b). We hold that the condition precedent of supplying the completion bond was for the mutual benefit of the parties and could not be waived by the bank without notice to the Sepos, and that the bank’s unilateral ‘waiver’ substantially vitiated the consideration to be received by the Sepos for their note.” (Emphasis added. Footnote omitted) 21 Ariz.App. at 610, 522 P.2d at 566.

After the mandate there was limited discovery by both parties. This discovery disclosed the 5 December 1972 sale by the Bank. We find the following question by the Bank and Sepo answer.

“(Question) (a) Whether you claim that the provision in the Construction Loan Agreement respecting a completion bond was a ‘mutual condition precedent’:
“(Answer) Defendants’ position is the same as that expressed by the Appellate Court, to-wit: That the requirement for a completion bond was a ‘condition precedent . . . for the mutual benefit of the parties and could not be waived by the Bank without notice to the Sepos, and that the Bank’s unilateral “waiver” substantially vitiated the consideration to be received by the Sepos for their note.’ ”

The Bank, persuading the trial court to enter a summary judgment in its favor against the various itemized claims of the Sepos, set forth in other answers to the Bank’s interrogatories, placed great reliance on that portion of our opinion quoted above from 21 Ariz.App. at 609, 522 P.2d 562 and the above Sepo answer to the Bank’s interrogatory.

This action by the trial court was the subject of the first special action, cause number 1 CA-CIV 3068. As we stated earlier we rendered a memorandum decision on 22 May 1975 which we now quote in full.

“This litigation is before this Court for the second time. See Sepo v. First National Bank of Arizona, 21 Ariz.App. 606, 522 P.2d 562 (1974) (review denied). The same will be referred to as the ‘Sepo decision.’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yard v. Perkins
Court of Appeals of Arizona, 2019
Sample v. Sample
731 P.2d 604 (Court of Appeals of Arizona, 1986)
Civil Rights Division of the Arizona Department of Law v. Superior Court
706 P.2d 745 (Court of Appeals of Arizona, 1985)
Scates v. Arizona Corp. Commission
601 P.2d 1357 (Court of Appeals of Arizona, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
541 P.2d 1160, 25 Ariz. App. 176, 1975 Ariz. App. LEXIS 835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sepo-v-case-arizctapp-1975.