Senters v. Elkhorn & Jellico Coal Co.

145 S.W.2d 848, 284 Ky. 667, 1940 Ky. LEXIS 562
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedDecember 6, 1940
StatusPublished
Cited by2 cases

This text of 145 S.W.2d 848 (Senters v. Elkhorn & Jellico Coal Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Senters v. Elkhorn & Jellico Coal Co., 145 S.W.2d 848, 284 Ky. 667, 1940 Ky. LEXIS 562 (Ky. 1940).

Opinion

Opinion of the Court by

Morris, Commissioner

Affirming.

On September 2, 1937, parties above, respectively plaintiffs and defendants below, executed tbe following writing:

“Whitesburg, Ky. Tbis agreement made and entered into by and between Elkhorn and Jellico Coal Co., and "Walter and Richard Senters * * *. Whereby Walter and Richard Senters agree to make opening and grade tram road on the head waters of Dry Fork Creek, for which the * * * company agrees to pay them fifty cents per cubic yard for the dirt and one dollar for the rock. The company to furnish the necessary explosives to do this work.”

In February, 1939, appellants filed petition seeking to recover of defendant a balance due for labor performed, and a further sum for alleged breach of contract. They set up the above writing and asserted that prior to its execution company’s engineer staked out the openings and two tram lines; made soundings and estimated that it would be necessary to remove (omitting decimals) 4,617 cubic yards of dirt and 768 yards of rock, which, had all been removed, would have entitled them to $3,076.26.

*669 Appellants entered upon and prosecuted the project, until they had removed 2,116 cubic yards of dirt, when, as they allege, the company notified them to cease operations. They professed ability and willingness to have completed the removal of the total estimated quantity of dirt and rock at contract prices.

They claim that while they removed the quantity of dirt mentioned, the company paid them $950 for only 1,900 cubic yards, but refused to pay them for 215.7, or $107.85, and $12 for explosives, paid for by them. They assert that there remained to be removed all rock and 2,500 yards of dirt, for which removal, had they been permitted to carry on, they would have been entitled to $2,018.35, and their net profit would have been $1,211.01. Summing up, appellants sought recovery of the last named amount for damages caused by the alleged breach, and the unpaid $107.85 for dirt removed.

By answer and amended answer, appellees admitted execution of the writing, but contended that • it was merely a memorandum by which the parties agreed on unit prices for removal of such dirt and rock as might be removed, and that essential terms and conditions were, by mistake of the draftsman, omitted from the contract. The purpose of the company was to make openings and two tramways at some distance apart, apparently on different sides of the mountain. At the time of the writing the company owned the land upon which one opening and tram grade were to be constructed, but the Kentucky River Coal Corporation owned the land upon which the other construction was proposed.

Further, they say that it was agreed and understood between parties that should the company purchase the other property, then the tram road should be built. If the company failed in purchase, it would not be built.

' After the memorandum was signed and work was begun on the proposed construction, the plan to purchase adjacent property failed, and appellants were notified of the fact. Appellants then completed the work on the first project, and were paid in full, but did some work on the other project. The pleadings by ap-pellee were met by replies in the form of denials.

Proof was heard, and a jury found for appellee; judgment was entered dismissing the petition, and mo *670 tion for a new trial was overruled. The motion was based on the following grounds, urged here:

(1) The verdict is not sustained by sufficient evidences, and is contrary to law.

(2) The court erred in refusing to instruct the jury on the whole law of the case.

(3) The court erred in admitting incompetent and irrelevant evidence, and in rejecting competent and relevant evidence.

Taking up the third ground, we find that in brief counsel for appellant has not pointed out any particular bit of testimony admitted over his objection, nor any offered in appellant’s behalf and rejected. Nevertheless we have gone through the transcript carefully, and find no basis for this ground of complaint. It is true the trial court remarked that the writing was indefinite, except as to unit prices, and permitted the proof to take a wide range, so as to get the entire picture before the jury.

Appellant’s contention is that all proof as to the writing being a memorandum, and that the real contract contemplated a possible failure of the company to buy property for the building one, or a part of one tram road, was incompetent. The argument is that it is well settled, “as a general proposition of law, that a written contract cannot be changed or modified by parol testimony when the contract is plain and certain in its terms, that it needs no citation of authority for this court.” This is a statemet of a sound principle of law with regard to construction of contracts. But the rule is otherwise when the issue is whether or not, because of mutual mistake, essential terms and conditions were omitted.

Appellant undertakes to blow hot and cold, since he was compelled (and permitted) to introduce proof endeavoring to show what the contract contemplated; his pleading did not pitch his cause solely on the terms of the writing, and his proof went to the extent of undertaking to show that surveys and soundings were made, stakes driven and an agreement as to the general layout of the proposed excavations.

An exhaustion of the resources of the written document does not express the purport of the contract from *671 the viewpoint of either party. It simply says, if we read it correctly: “Senters agrees to make opening and grade tram road on the head of Dry Fork Creek, for which company agrees to pay 50 cents per yard for removal of dirt, and $1 per yard for rock,” the company to furnish exlposives. The'proof evidences a mutual mistake.

The writing did not fix the place, time for beginning the work, nor length, depth or width of the opening or tram bed; no time was fixed for payment, so we have no difficulty in concluding that this was not a complete agreement. Ordinarily parol evidence is not admissible to contradict the terms of a writing, unless the party complaining alleges that the terms of the executed contract are different from the terms of the actual contract intended to be performed, and that the omission was due to fraud on the part of the adversary, by mistake on his part and fraud on the part of the adversary, or by mutual mistake. Barret v. Clarke, 226 Ky. 109, 9 S. W. (2d) 1091, and cases cited. In Bullock v. Young, 252 Ky. 640, 67 S. W. (2d) 941, 946, we wrote what is fittingly applicable here:

“In ascertaining their intentions, the chief and most satisfactory index is found in the circumstances whether or not the particular element of the alleged extrinsic negotiations is dealt with in the writing. ‘If it is mentioned, covered or dealt with in the writing, then presumably the writing was meant to represent all of the transaction on that element; if it is not, then probably the writing was not intended to embody that element of the negotiation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horn v. Ranier
560 S.W.2d 233 (Court of Appeals of Kentucky, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
145 S.W.2d 848, 284 Ky. 667, 1940 Ky. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/senters-v-elkhorn-jellico-coal-co-kyctapphigh-1940.