Senften v. Church of the Nazarene of Columbus

335 N.W.2d 753, 214 Neb. 708, 1983 Neb. LEXIS 1168
CourtNebraska Supreme Court
DecidedJune 24, 1983
Docket82-286
StatusPublished
Cited by6 cases

This text of 335 N.W.2d 753 (Senften v. Church of the Nazarene of Columbus) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Senften v. Church of the Nazarene of Columbus, 335 N.W.2d 753, 214 Neb. 708, 1983 Neb. LEXIS 1168 (Neb. 1983).

Opinion

Krivosha, C.J.

This appeal arises from a foreclosure action involving 12 mechanics’ liens claimed by as many sub *709 contractors and materialmen who furnished labor or materials in the construction of the Church of the Nazarene in Columbus, Nebraska (Church). Six of the liens were released prior to trial and the causes of action representing those liens were dismissed by the lienholders or their assignee. Appellant, David Senften, doing business as Metalcrafters Heating & Air Conditioning (Senften), is the claimant of one of the mechanics’ liens and the assignee of five others. Following the trial, the court found in favor of Senften on his third, sixth, and seventh causes of action and ordered a decree of foreclosure. On Senften’s first, fifth, and tenth causes of action, the trial court, however, found for the Church and dismissed those causes of action. It is from the action of the trial court in dismissing the first, fifth, and tenth causes of action that this appeal is brought.

With regard to the first and fifth causes of action, the trial court found that Senften had failed to introduce sufficient evidence to prove the reasonable value of the labor performed or material provided. With regard to the tenth cause of action, the trial court found that the evidence introduced to establish the fair and reasonable value of the labor and ma: terials was insufficient and, further, that the time for filing the lien had expired as to part of the work done prior to the date the lien was in fact filed. For reasons more particularly set out in this opinion, we reverse in part and in part affirm.

The basic evidence is not in dispute. In January of 1980 the Church accepted a proposal dated December 22, 1979, submitted by Stanley H. Kruse on behalf of Kruse Construction Company (Kruse) for the construction of a worship and classroom building in Columbus, Nebraska. In connection with the construction of the Church, Senften submitted a written proposal to Ronald L. Kruse, the son of Stanley H. Kruse, for the installation of heaters, air-conditioners, and ductwork in the building. Senften performed the work on the Church beginning on June 20, 1980, *710 and, except for the installation of some registers on the ductwork, completed his work on October 23, 1980. A mechanic’s lien was filed by Senften on January 23, 1981.

On October 7, 1980, M & O Metals, Inc., the materialman involved in the fifth cause of action, sold four door panic devices to Kruse for use in the Church’s building. M & O Metals filed a mechanic’s lien on January 7, 1981.

In connection with the tenth cause of action, Joe Moore, doing business as Central Insulation & Roofing, at the request of Kruse, tarred the footings of the Church building on April 9, 1980. Then, on October 2 and October 11, Central installed insulation in the attic of the Church building, also at the request of Kruse. The bill submitted for the tarring was the sum of $74, and for the insulation, the sum of $1,470. On January 9, 1981, Moore filed a mechanic’s lien in the total amount of $1,544.

A mechanic’s lien foreclosure is to be considered by the Supreme Court on appeal de novo on the record, giving credit to the fact that the trial court observed the witnesses and their manner of testifying. See, Modern Plumbing & Heating, Inc. v. Journey West Campground, Inc., 193 Neb. 781, 229 N.W.2d 192 (1975); Waite Lumber Co., Inc. v. Carpenter, 205 Neb. 860, 290 N.W.2d 655 (1980). The primary dispute common to all three causes of action is a question of law and whether a subcontractor can foreclose upon a mechanic’s lien to recover the reasonable value of labor performed or material furnished by offering in evidence the contract between the subcontractor and the prime contractor. As we have indicated, the trial court held that the subcontractor could not recover on that basis. In that regard we think the trial court was in error.

We should further note, before turning to discuss the various causes of action, that the statutes involved in this appeal are Neb. Rev. Stat. §§ 52-102 and 52-103 (Reissue 1978), which were repealed ef *711 fective January 1, 1982. Section 52-102 provided in part: “Any person or subcontractor who shall perform any labor for, or furnish any material, machinery, or fixtures . . . for any of the purposes mentioned in section 52-101, to the contractor, or any subcontractor who shall desire to secure a lien upon any of the structures mentioned in said section, may file a sworn statement of the amount due him from such contractor for such labor, material . . . together with a description of the land upon which the same was done or used, within four months from the performing of such labor or furnishing such material . . . with the register of deeds of the county wherein said land is situated.”

Section 52-103, after first describing the manner in which the lien is to be prepared and filed, concluded as follows: “Provided, nothing herein contained shall be taken to prevent the ascertainment by proceeding at law, or otherwise, of the amount actually due for such labor and material, and such lien shall be for no larger sum than the amount actually due therefor.”

Senften argues that he met his burden of proof as to his own lien by showing the existence of an oral contract entered into between Senften and the prime contractor, while the Church argues that evidence of a contract between the subcontractor and the prime contractor is not binding on the owner. While it is true that a contract, oral or written, between a subcontractor and a contractor is not binding upon the owner of the property, it is also true that, absent evidence to the contrary, the existence of such a contract does establish the fair and reasonable value of the services. Specifically, in the supplemental opinion in the case of Rosebud Lumber and Coal Company v. Holms, 155 Neb. 688, 689, 53 N.W.2d 82, 83 (1952), this court said: “[A]n owner may not be compelled to pay more than the reasonable value of labor or materials furnished, and is not bound by the agreed prices between the contractor and the lien *712 claimant, but such agreed prices may be taken as prima facie correct.” In the Rosebud Lumber case the subcontractor was found to have established the reasonable cost of material furnished the contractor merely by offering in evidence an itemized list of materials furnished the contractor and the charges made upon them. In approving such action this court, in the original opinion at 155 Neb. 459, 52 N.W.2d 313, said at 470, 52 N.W.2d at 319: ‘‘There was no objection to the showing that the prices set forth in the list were not correct, or that the items for profit or the discounts allowed were not reasonable and fair.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nore Electric v. S & H Holdings
316 Neb. 197 (Nebraska Supreme Court, 2024)
In Re Guardianship of Bloomquist
523 N.W.2d 352 (Nebraska Supreme Court, 1994)
Union Insurance v. Bailey
450 N.W.2d 661 (Nebraska Supreme Court, 1990)
J. Q. Office Equipment of Omaha, Inc. v. Sullivan
432 N.W.2d 211 (Nebraska Supreme Court, 1988)
JQ OFFICE EQUIPMENT v. Sullivan
432 N.W.2d 211 (Nebraska Supreme Court, 1988)
Crane Rental, Inc. v. Hunnicutt Land Co.
352 N.W.2d 888 (Nebraska Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
335 N.W.2d 753, 214 Neb. 708, 1983 Neb. LEXIS 1168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/senften-v-church-of-the-nazarene-of-columbus-neb-1983.