Seneca Meadows, Inc. v. ECI Liquidating, Inc.

983 F. Supp. 360, 1997 U.S. Dist. LEXIS 18336, 1997 WL 722338
CourtDistrict Court, W.D. New York
DecidedNovember 14, 1997
Docket95-CV-6400L
StatusPublished
Cited by6 cases

This text of 983 F. Supp. 360 (Seneca Meadows, Inc. v. ECI Liquidating, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seneca Meadows, Inc. v. ECI Liquidating, Inc., 983 F. Supp. 360, 1997 U.S. Dist. LEXIS 18336, 1997 WL 722338 (W.D.N.Y. 1997).

Opinion

DECISION AND ORDER

LARIMER, Chief Judge.

This action is brought pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. §' 9601 et seq., and the Declaratory Judgment Act, 28 U.S.C. § 2201 et seq., and also raises New York common law causes of action. Pending before the Court is defendants’ motion for partial summary judgment.

*362 BACKGROUND

Plaintiff Seneca Meadows, Inc. (“SMI”) is the current owner of the Tantalo Landfill Site in Seneca Falls, New York (“Tantalo Site”). SMI purchased this site in 1968. Plaintiff Macedón Homes, Inc. (“MHI”) and SMI each own real property immediately adjacent to the Tantalo Site (“Adjacent Properties”). MHI and SMI purchased these properties in 1994 and 1995 respectively.

Land filling and other waste disposal practices occurred at the Tantalo Site from approximately 1958 until 1974. The New York State Department of Environmental Conservation (“DEC”) listed the Tantalo Site on its registry of Inactive Hazardous Waste Disposal .Sites in 1980. On August 19, 1992, SMI entered into a Consent Order with the DEC to investigate the contamination at the Tantalo Site and to develop remedial alternatives.

Plaintiffs commenced this action on August 18, 1995, alleging that defendants — the principal generators of the hazardous wastes— are responsible for the resulting contamination on both the Tantalo Site and the Adjacent Properties. In their complaint, plaintiffs assert, inter alia, state common law claims for property damage under theories of negligence, private nuisance, public nuisance, strict liability, and trespass (“common law claims”).

Defendants move for summary judgment on SMI’s common law claims regarding the Tantalo Site on the ground that they are time barred. Defendants also move for summary judgment on SMI and MHI’s common law claims regarding the Adjacent Properties on the ground that plaintiffs have not suffered any recoverable damages.

DISCUSSION

A. Summary Judgment Standard

Summary judgment will be granted if the record demonstrates that “there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(e). A genuine issue of material fact exists, only if the record, taken as a whole, could lead a reasonable trier of fact to find in favor of the nonmovant. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986).

The burden of demonstrating the absence of any genuine issue of material fact rests on the moving party, Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986), and all ambiguities and inferences that may be reasonably drawn from the facts must be viewed in the light most favorable to the non-moving party. Coach Leatherware Co. v. AnnTaylor, Inc., 933 F.2d 162, 167 (2d Cir.1991). To defeat summary judgment, the non-moving party must go beyond the pleadings and designate “specific facts showing that there is a genuine issue for trial.” Fed.R.Civ.P. 56(e).

“These principles apply equally whether summary judgment is granted on the merits of the claim, or on an affirmative defense such as the statute of limitations.” Buttry v. General Signal Corp., 68 F.3d 1488, 1492 (2d Cir.1995).

B. SMI’s Common Law Claims Regarding the Tantalo Site

Defendants move for summary judgment on SMI’s common law claims regarding the Tantalo Site on the ground that they are barred by the applicable statute of limitations. Specifically, defendants argue that SMI did not commence this action, as required by CPLR 214-e(2), within three years from the date SMI discovered or should have discovered the injury to the Tantalo Site. CPLR 214-e(2) provides that

the three year period within which an action to recover damages for ..-. injury to property caused by the latent effects of exposure to any substance or combination of substances ... must be commenced shall be computed from the date of discovery of the injury by the plaintiff or from the date when through the exercise of reasonable diligence such injury should have been discovered by the plaintiff, whichever is earlier.

N.Y. CPLR 214-c(2).

SMI maintains that defendants applied the wrong commencement date for statute of limitations purposes. SMI argues that this *363 action is governed by CERCLA § 9658, which delays the running of the statute of limitations on state law claims until the plaintiff discovers or should have discovered not only the injury, but also its cause. Section 9568 provides that the relevant limitations period begins to run on “the date the plaintiff knew (or reasonably should have known) that the ... property damages ... were caused or contributed to by the hazardous substance or pollutant or contaminant concerned.” 42 U.S.C. § 9658(b)(4)(A). According to SMI, its common law claims are timely under § 9658 because it did not know the cause of its injury more than three years before the commencement of this action. SMI maintains that to be charged with knowledge of the cause of its injury, it must have been aware of each defendant’s specific contaminants.

I find that SMI’s common law claims regarding the Tantalo Site are untimely under either the state or the federal statute. 1 SMI had actual knowledge of both the injury to the Tantalo Site and its cause more than three years prior to the commencement of this action.

SMI personally operated a landfill on the Tantalo Site for at least six years. During that time, SMI accepted wastes for disposal and treatment at the site. When SMI discovered that it had been injured — ie., that the property had been contaminated by hazardous substances — it also immediately knew the cause of that injury — i.e., the wastes that had been disposed of at the site. It simply defies logic that SMI was unaware of the causal connection between the property contamination and the waste disposal activities at the site.

There is ample documentary evidence before me to support this conclusion. For example, the DEC listed the Tantalo Site on its registry of Inactive Hazardous Waste Disposal Sites in 1980.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lucchesi v. Perfetto
72 A.D.3d 909 (Appellate Division of the Supreme Court of New York, 2010)
Abrams v. Ciba Specialty Chemicals Corp.
666 F. Supp. 2d 1267 (S.D. Alabama, 2009)
Lessord v. General Electric Company
258 F. Supp. 2d 209 (W.D. New York, 2002)
Seneca Meadows, Inc. v. ECI Liquidating, Inc.
121 F. Supp. 2d 248 (W.D. New York, 2000)
In Re Pfohl Bros. Landfill Litigation
68 F. Supp. 2d 236 (W.D. New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
983 F. Supp. 360, 1997 U.S. Dist. LEXIS 18336, 1997 WL 722338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seneca-meadows-inc-v-eci-liquidating-inc-nywd-1997.