Sema Construction v. City of Tustin CA4/3

CourtCalifornia Court of Appeal
DecidedMay 13, 2014
DocketG046874
StatusUnpublished

This text of Sema Construction v. City of Tustin CA4/3 (Sema Construction v. City of Tustin CA4/3) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sema Construction v. City of Tustin CA4/3, (Cal. Ct. App. 2014).

Opinion

Filed 5/13/14 Sema Construction v. City of Tustin CA4/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

SEMA CONSTRUCTION, INC.,

Plaintiff and Appellant, G046874

v. (Super. Ct. No. 30-2008-00101147)

CITY OF TUSTIN, OPINION

Defendant and Respondent.

Appeal from a judgment of the Superior Court of Orange County, Kim Garlin Dunning, Judge. Affirmed. Musick, Peeler & Garrett and Jack W. Fleming; Snell & Wilmer, Richard A. Derevan and Todd E. Lundell for Plaintiff and Appellant. Woodruff, Spradlin & Smart, M. Lois Bobak, Joseph W. Forbath and Magdalena Lona-Wiant for Defendant and Respondent.

* * * Plaintiff SEMA Construction, Inc. (SEMA) appeals from a judgment awarding it $486,555 in compensatory damages plus prejudgment interest against defendant City of Tustin (Tustin) in an action for breach of a public works contract. The judgment is based on Tustin’s underpayment for SEMA’s disposal of groundwater from a construction site. SEMA contends the trial court erred in limiting its recovery, arguing the terms of the parties’ contract and their conduct before any dispute arose entitled it to a much larger award. Finding no error, we affirm the judgment.

FACTS AND PROCEDURAL BACKGROUND

1. Background SEMA was the successful bidder on a $23.8 million contract to build roads on property within an area previously used by the United States Marine Corp. as a helicopter base. The area is referred to as the Tustin Legacy project. The work included “construction of sanitary sewers, storm drains, reclaimed water lines, [and] domestic water lines.” Irvine Ranch Water District (IRWD) was the entity that would take over operation of the completed pipelines and it entered into a contract with Tustin to reimburse it for certain construction related expenses. The contract consisted of six lettered sections and two appendices. Sections A and B covered Tustin’s notice to contractors of the project, plus blank contractor bid forms. Section C was the contract agreement containing SEMA’s successful bids for each item of work to be performed, its performance and labor and material bonds, and insurance certificate. Section D contained the contract’s general provisions. Sections E and EH covered special contract terms. The latter part, section EH, dealt with construction work in a portion of the project known to have soil contamination and described as the Area of Institutional Control (AIC). In part, the

2 contract required SEMA to obtain and bear the cost of “all permits . . . for this project” and to “comply with all rules and regulations included in [the] permits.” The contract’s general provisions also incorporated the most recent edition of the Standard Specifications for Public Works (i.e., “Greenbook”) and declared the Greenbook “will control . . . except as amended by the plans, these special provisions, or other contract documents.” The Greenbook provides that “[n]ew or unforeseen work will be classified as ‘extra work’ when the Engineer determines that it is not covered by Contract Unit Prices or stipulated unit prices.” In the event “extra work is deemed necessary, the scope of the work shall be documented under the terms and conditions of the City[’s] . . . Contract Change Order form . . . .” The portion of the agreement that covered installing drains and water lines required SEMA to remove groundwater seeping into the trenches during construction, a process known as dewatering. Payment for the cost of dewatering was covered in two separate contract sections. Under section C, SEMA agreed to receive a lump sum of $380,700 for sheeting, shoring, bracing and dewatering the sewer, storm, and water trenches. Section E-21 stated “the lump sum contract price[]” for this work “shall be considered full compensation . . . and no additional compensation will be allowed.” Section EH required SEMA to perform groundwater sampling in the AIC. Additive Bid Item A4, covering the treatment of contaminated liquids, specified “contaminated groundwater generated during dewatering activities, . . . be treated, if required by permit” through “a granular activated carbon (GAC) treatment system” before being “disposed into a sanitary sewer or off-site wastewater treatment facility.” SEMA was also directed to “obtain and pay for any permit required for disposal to the . . . sewer system from [IRWD].” The contract authorized SEMA to receive “payment for the actual quantities [treated] . . . multiplied by the unit price[] stated,” but specified the “[d]etermination[] of the actual quantities . . . will be made by the [City] Engineer,”

3 which after “review with the Contractor . . . will be final and binding.” SEMA agreed to charge a fixed unit price of 16 cents per gallon for this work. Tustin’s request for bids estimated the amount of contaminated liquids requiring GAC treatment at 500,000 gallons, but warned this figure was “approximate only.” In its April 2005 notice to proceed with the work, Tustin informed SEMA it had retained Washington Group International, Inc. (WGI) to administer the project and Arturo Diaz, WGI’s resident engineer, was the construction manager. SEMA was told to direct “[a]ll official correspondence and billing” to Diaz. After SEMA was awarded the contract, the parties learned IRWD either would not or could not allow the discharge of groundwater into its system. It was then decided to obtain a discharge permit from the Orange County Sanitation District (OCSD) and dispose of the groundwater through its facilities. OCSD required the permit application to be filed by Tustin. In addition, it agreed to issue the permit only if SEMA treated all groundwater removed from the entire project site through dewatering with the GAC process before discharging it into the sewer system. SEMA informed Diaz it expected to be paid for the treatment of all groundwater at the Bid Item A4 unit price. On September 2, 2005, Diaz sent SEMA a letter stating he would issue a contract change order (CCO 19) to use the Bid Item A4 method of payment for the treatment of liquids “processed through the treatment facility and disposed to the [s]ewer [s]ystem.” OCSD issued its permit four days later and Diaz issued CCO 19 the same day. However, CCO 19 listed the price adjustment as “0.00.” At trial Diaz testified, “This change order was just for modification to allow payment of hazardous and nonhazardous water, in that at that time it was not anticipated [the quantity treated] w[ould] exceed the quantity allowed in the contract . . . .” By September 20 SEMA had discharged 880,000 gallons of GAC treated groundwater through OCSD’s system. SEMA submitted an invoice to Tustin requesting payment for this work at the Bid Item A4 unit price. Tustin paid the invoice. However,

4 by October 4, SEMA had treated and discharged approximately 2.5 million gallons of groundwater. On September 26, a meeting was held between Diaz and city officials about the need to renegotiate the cost for the dewatering process. The next day, Diaz issued another contract change order (CCO 2). It stated, in part, “Quantity beyond 125% of the original Bid Item [A4] (i.e. 625,000 Gallons) will be subject to adjustment” under the Greenbook’s provisions governing changes in work initiated by a contracting agency. Under section 3-2.2.1 of the Greenbook, where “a change is ordered in an item of work covered by a Contract Unit Price . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foreman & Clark Corp. v. Fallon
479 P.2d 362 (California Supreme Court, 1971)
Nestle v. City of Santa Monica
496 P.2d 480 (California Supreme Court, 1972)
California National Bank v. Woodbridge Plaza LLC
164 Cal. App. 4th 137 (California Court of Appeal, 2008)
KATSURA v. City of San Buenaventura
65 Cal. Rptr. 3d 762 (California Court of Appeal, 2007)
Parsons v. Bristol Development Co.
402 P.2d 839 (California Supreme Court, 1965)
City of Manhattan Beach v. Superior Court
914 P.2d 160 (California Supreme Court, 1996)
P&D Consultants, Inc. v. City of Carlsbad
190 Cal. App. 4th 1332 (California Court of Appeal, 2010)
Burch v. Premier Homes
199 Cal. App. 4th 730 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Sema Construction v. City of Tustin CA4/3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sema-construction-v-city-of-tustin-ca43-calctapp-2014.