Selvage v. Fred J. Maurer & Son

272 P. 1092, 95 Cal. App. 566, 1928 Cal. App. LEXIS 561
CourtCalifornia Court of Appeal
DecidedDecember 18, 1928
DocketDocket No. 6585.
StatusPublished

This text of 272 P. 1092 (Selvage v. Fred J. Maurer & Son) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Selvage v. Fred J. Maurer & Son, 272 P. 1092, 95 Cal. App. 566, 1928 Cal. App. LEXIS 561 (Cal. Ct. App. 1928).

Opinion

*567 KOFORD, P. J.

Plaintiff recovered a judgment for $2,251.81 for performing certain excavation work. Trial was by jury. Defendant appeals from the judgment, assigning errors which largely involve questions of fact.

Maurer & Son were awarded a contract by the United States government to construct a United States Coast Guard station consisting of a marine ways, a building and the excavation of a land approach on the ocean shore at Pt. Reyes, California. They sublet to Selvage, the plaintiff and respondent herein, the construction of the substructure (pile driving) and launchways for the sum of $3,000. This subcontract was in writing and provided, among other things, for partial payment of seventy-five per cent of the work completed on the 1st of each month at the request of Selvage. Selvage came to the scene and commenced to make ready for this work. It appeared that it was necessary for the land excavation to be completed before the pile driving for the substructure should be commenced. A. L. Maurer, the son mentioned in the corporate name of appellant, was acting as general superintendent - of the entire work covered by the government contract with Maurer & Son. Appellant asked Selvage to give a bid upon the excavation part of the work because the person' whom appellant had relied npon to do this work had failed to appear. Selvage bid $2,000 for the excavation work. A verbal agreement was made with Maurer & Son, accompanied by a brief written bid, signed by Selvage only, specifying the price and a very general description of the excavation work to be done. At the trial the parties differed materially upon what the verbal understanding was between them regarding progress payments on this work, regarding the furnishing of materials and equipment and as to whether Selvage had agreed to perform the work to the final satisfaction of the government engineer or only to carry out the orders and directions of A. L. Maurer. This subcontract was the basis of the complaint in the action. There were three counts. One for $2,000 as for the agreed price on an express contract, one for the same $2,000 as for the reasonable value of the same work and a third for $251.81 consisting of $150 for excavating rock, $66.06 for material paid for by Selvage which should have *568 been paid for by appellant and the balance for extra labor and excavation caused by appellant’s misdirections for the doing of the excavation.

Selvage’s testimony was to the effect that neither by contract nor by actual practice did he have anything to do with the government engineer. That the engineer would not recognize him as subcontractor, but dealt only with Maurer, the general contractor. That the engineer laid out lines and established stakes indicating to Maurer the extent and nature of the excavation required and Maurer, in turn, placing his own interpretation on these directions, indicated to Selvage in more detail how the work was to be done. That owing to mistakes of Maurer, Selvage was required to finish the surface of the cut twice, but that finally he finished the job to the last finishing touch to the expressed satisfaction of Maurer. Thereupon, being greatly dissatisfied because he had been unable to obtain any progress payments on the work, he demanded his pay. He testified that the verbal contract was that he should have seventy-five per cent progress payments monthly just as provided in his written contract for the substructure. Appellant positively declared that no payments would be made until it had received payment from the government. His pay not being forthcoming upon the $2,000 contract, Selvage declared he would not commence with the performance of his $3,000 contract for the substructure and launchways until paid for his excavation work to date.

It was appellant’s claim and testimony that Selvage was required to finish the excavation to the satisfaction of the government engineer and the plans and specifications of the government contract; that Maurer’s acceptance of the work was necessarily conditioned upon the final approval of the government engineer; that eventually the government engineer came and decided that the grading was not executed up to the lines designated by him; that Selvage was entitled to no payment until Maurer had received payment from the government; that Selvage therefore failed to complete the excavation according to contract, but that he had abandoned it uncompleted; that he also unjustifiably abandoned the contract for the substructure and launchways. Defendant claimed damages by way of counterclaim and cross-complaint for these alleged breaches by Selvage. The *569 jury found a verdict for the plaintiff for the full amount sued for and allowed defendant nothing upon the offsets pleaded.

At the conclusion of plaintiff’s case in chief defendant moved for a nonsuit upon the second cause of action which was for quantum meruit, claiming that plaintiff’s case rested upon an express contract, This motion was denied. Defendant then immediately moved for a non-suit upon the first cause of action, claiming that the court had decided by the last-mentioned ruling that there was no express contract or that the first cause of action had not been proven. Appellant disclaims any motion to compel an election, but claims that his motions for nonsuit presented a pure question of law for the court. If the law did not require respondent to make an election it is difficult to see how the court was obliged to do so for him by granting one of defendant’s motions for nonsuit. The testimony on behalf of the plaintiff would have sustained a verdict upon either count, the one sustained depending upon what view, of the testimony the jury approved. This was a question of fact for the jury and' not for the court to decide. The court did not err in submitting both counts to the jury under proper instructions. Where no election was required both issues could go to the jury. (1 Bancroft’s Code Pleading, secs. 108, 655; Cowan v. Abbott, 92 Cal. 100 [28 Pac. 213] ; Estrella Vineyard Co. v. Butler, 125 Cal. 232 [57 Pac. 980]; Tanforan v. Tanforan, 173 Cal. 270 [159 Pac. 709].)

Appellant next claims that Selvage abandoned his grading contract before completion and hence should not recover at all or at least not the full contract price. This is entirely a question of fact well within the jury’s province under the testimony. There was ample evidence to support the decision of fact that Selvage had fully completed his contract with appellant even though the excavation did not fully satisfy the plans and grade lines of the appellant’s contract with the government. The evidence does not compel the conclusion that the requirements of the two contracts with respect to excavation or grading were identical.

Appellant’s last point is that damages should have been awarded it because plaintiff failed to commence the *570 performance of the substructure and launchways contract. Appellant testified that the cost of the labor in doing this work himself was $4,652.29.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tanforan v. Tanforan
159 P. 709 (California Supreme Court, 1916)
Cowan v. Abbott
28 P. 213 (California Supreme Court, 1891)
Estrella Vineyard Co. v. Butler
57 P. 980 (California Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
272 P. 1092, 95 Cal. App. 566, 1928 Cal. App. LEXIS 561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/selvage-v-fred-j-maurer-son-calctapp-1928.