Seligmann v. Hill & Combs

338 S.W.2d 178, 1960 Tex. App. LEXIS 2474
Court of Appeals of Texas·Decided July 20, 1960·No. 13609·Published·Cited by 5 cases

Opinion

POPE, Justice.

We grant appellees’ motion for rehearing, withdraw our former opinion, and affirm the trial court’s judgment with this substituted opinion.

Julius Seligmann, Jr., appealed from a judgment which denied his claim as assig-nee to funds due Zoller Electric Company, a building sub-contractor, and granted judgment for Aetna Casualty and Surety Company as assignee of the funds. Defendant Hill & Combs was the general contractor and is a mere stakeholder. The dispute is between Seligmann and Aetna. The legal problems in the case are: (1) Did Selig-mann have a statutory protected assignment to the funds retained by the contractor? (2) Did he have an assignment at all to the funds? (3) Did Aetna have an assignment to the same funds?

On October 1, 1954, Zoller Electric Company made an accounts receivable contract with Seligmann. On September 5, 1956, it made another accounts receivable contract by which Zoller agreed to assign its present and future accounts to Seligmann. Notice of this accounts receivable contract was recorded in the County Clerk’s office on September 7, 1956, and it, together with subsequent specific assignments, is the basis for Seligmann’s claim to a protected assignment under Article 260-1, Vernon’s Tex. Civ.Stats.

On October 25, 1956, Zoller made a subcontract to install the eletrical work in the Highland High School in San Antonio, on which he later defaulted and on which Aet-na suffered a loss of $51,348.45 on its performance bond. On April 17, 1957, Zoller contracted to install the electrical system in Terrell Plaza Shopping Center in Bexar County, and on that date executed an assignment to Aetna in consideration of Aet-na’s giving its performance and payment bond to the general contractor, Hill & Combs. Aetna relies upon this assignment. 1

*180 Between January and April, 1958, Zol-ler executed and delivered to Seligmann six specific assignments. 2 On June 23, 1958, Zoller defaulted on both the Highland High School and the Terrell Plaza jobs. Aetna completed the Highland High School job at a cost to it of $51,348.45. The general contractor completed the Terrell Plaza job at a small cost of $205.06, and after completion the general contractor still held $9,509.28, which had been retained and unpaid to Zoller. Out of those funds, the general contractor discharged mechanics’ liens totalling $4,671.33, and as stakeholder still retains $4,837.95, which both Seligmann and Aetna claim as assignees.

Seligmann did not have a protected assignment under Article 260-1, supra. His proof on this point is the accounts receivable contract dated September 5⅛ 1956, the notice filed two days later, and the six assignments given between January and April, 1958. Pro-' tected assignments of accounts receivable are governed by Article 260-1, Vernon’s Tex.Civ.Stats. The 1955 statute defined the terms “account” and “account receivable.” 3 As defined, the terms did not in *181 elude money accruing to a contractor ón a construction contract where the assignor had furnished a surety bond guaranteeing the performance of the contract. Selig-mann argues that the provision gave preference to a surety, which it did, and because it did, Seligmann’s assignment did not fall within the statutory definition. In 1957 the statute was amended, 4 perhaps because of an intent to remove the preference. However, by the new definition, an assignment to be protected must describe the land upon which the improvements are to be constructed. After the 1957 amendment, Zoller gave his six additional assignments to Seligmann, but they wholly failed to describe the land upon which the improvements were constructed. Hence, Sel-igmann failed to bring his assignments within either the 1955 or the 1957 definition of the term "account” or "account receivable,” and he did not have a protected assignment.

Alternatively, Seligmann asserts that the six assignments from Zoller, executed between January and April, 1958, entitled him to prior rights to the $4,837.95 in the hands of the stakeholder. Aetna attacks the form and sufficiency of the assignments, but we regard them as adequate. They each identify the creditor, the debtor, the amount due, the job on which the work was done, the name of the contractor, his street address, the date of the invoice and its number. This was sufficient identification. Aetna’s further objection that the body of the assignment states that it is for current accounts receivable for ■"merchandise” is also unfounded. Taken as a whole, the assignments sufficiently disclose what was assigned.

The pivotal point, however, is the determination of exactly what Zoller assigned by these instruments. Seligmann reasons that Zoller, by each assignment, assigned him all that was presently due as well as all funds which would become due on the Terrell Plaza job, including the funds retained by the general contractor. Aetna replies and the trial court held that the assignments reached none of the funds retained by the general contractor. An examination of the written documents rather clearly discloses that Zoller has never assigned to Seligmann any part of the funds retained by the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Seligmann v. Hill & Combs, 338 S.W.2d 178, 1960 Tex. App. LEXIS 2474 (Tex. Ct. App. 1960).

338 S.W.2d 178 (Seligmann v. Hill & Combs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Filley Enterprises, Inc. v. Youngstown Sheet & Tube Co.
441 S.W.2d 509 (Texas Supreme Court, 1969)
Creditors Exchange Service, Inc. v. United States
277 F. Supp. 885 (S.D. Texas, 1967)
South Main State Bank v. State
365 S.W.2d 946 (Court of Appeals of Texas, 1963)