This text of 124 Misc. 622 (Segfried Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering City of New York Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Segfried Construction Co. v. City of New York, 124 Misc. 622, 209 N.Y.S. 429, 1925 N.Y. Misc. LEXIS 768 (N.Y. Super. Ct. 1925).

Opinion

Prince, J.:

The plaintiff owns the property at the southeast corner of One Hundred and Sixty-ninth street and Haven avenue, in the city of New York. It paid the defendant, the city of New York, $206.18, the amount of. an assessment levied against its property for the paving of Haven avenue, between One Hundred and Sixty-ninth and One Hundred and Seventieth streets. It claims that the assessment was illegal and seeks to recover this payment. If the assessment was illegal, the plaintiff is not barred from a recovery because the payment was voluntary. The assessment was regular on its face, constituted a cloud on plaintiff’s title, subjected it to penalties and interest and the risk of a sale of its property upon default in payment. These conditions constituted a duress under pain of which the payment was made.

On April 8, 1921, after proceedings regularly had, the board of estimate and apportionment of the city of New York adopted a resolution authorizing the president of the borough of Manhattan to regulate, reregulate, grade and regrade, curb and recurb, and flag and reflag, with a permanent sheet asphalt pavement on a concrete foundation, Haven avenue between One Hundred and - Sixty-ninth and One Hundred and Seventieth streets. The borough president, on October 13, 1921, entered into a contract with the Asphalt Construction Company for this pavement. It is claimed that this contract, and the assessment made against the property deemed to be benefited for the money expended thereunder, are illegal and void. That contract obligated the contractor not only to construct the pavement, but within a period of five years to “ repair and make good * * * all disintegrations, cracks, bunches, defects, open joints * * * which shall occur at any time in the pavement.”

Clearly, a portion of the contract price represents the value of the undertaking of the contractor to so maintain and keep in repair the pavement during the period of five years after completion. The contract does not, however, indicate what portion of the consideration is attributable to the construction of the pavement, and what portion for the repair during the five-year period of maintenance. It provides that ninety per cent of the contract price shall be paid upon completion of the work, and that the remaining ten per cent shall be retained and one-fifth thereof paid to the contractor at the end of each year during the period [624]*624of maintenance. TMs would- seem to indicate that the cost of maintenance was ten per cent of the contract price, but it is insufficient to predicate such a finding thereon.

Under the provisions of section 948 of the Greater New York charter, only the cost of the original pavement can be charged to the abutting owners. The city at large must pay the expense of keeping the pavement in repair. After the pavement was completed and accepted by the city, the board of assessors of the city levied and confirmed an assessment against the abutting owners for the entire cost to the city under this contract, and plaintiff’s share was $200, which, with interest, amounts to $206.18, which the plaintiff paid under compulsion of law and to recover which this action was brought.

But for the decision of the Court of Appeals in the case of People ex rel. North v. Feather stonhaugh (172 N. Y. 112), it would be clear that the city exceeded its powers in assessing against the property benefited the entire cost of paving and maintaining this street. The defendant did not prove what portion of the contract price represents the cost of paving. The contract being indivisible and tainted with illegality, is void in its entirety, and an assessment made thereunder is with equal taint.

The case of People ex rel. North v. Featherstonhaugh (supra) is not in point. That was also a paving case. The contractor guaranteed that he would keep the pavement in repair for a period of eight years, and it was held that that provision was not in contravention of the - prohibition that the cost of maintenance shall not be charged to the abutting owners, on the theory that that undertaking was nothing more than a warranty of good workmanship and fitness of material, and that the period of maintenance was no longer than the ordinary durability of the pavement when laid with proper material and workmanship. The Court of Appeals, through Haight, J. (at p. 124), says in part as follows: There does not appear to be any controversy that the asphalt pavement, properly constructed with proper material upon a concrete base, will remain in good condition for the period named in the specifications, or even- for a longer time. And we think the repairs required by the contract have reference to making good the imperfect work done, or the defective material used therein. In other words, that it is in effect a guaranty as to the quality and character of the pavement. If we are correct as to this construction of the specifications, it follows that no additional burden was imposed upon the abutting property owners by reason of the eight-year requirement.”

Thus it is apparent that included in the record in the North case was evidence that, had the pavement been properly con[625]*625structed, it would not have developed the defects during the period of maintenance, which the contractor agreed to repair at his own expense. In other words, it appeared affirmatively in the North case that, in effect, the contractor assumed no obligation beyond the construction of a proper pavement, because if properly constructed, there would be no repairs during the maintenance period.

In the case at bar there is no such proof, and the obligation assumed by the contractor is beyond that of a mere warranty. It undertook to repair “ all disintegrations, cracks, bunches, defects, and open joints.” It is not intimated that such defects would not develop within a five-year period after completion notwithstanding the most perfect workmanship and material. The inference to be drawn from this contract, in the light of everyday experience, is that the contractor assumed more than to make good those imperfections developing only from initially imperfect work or material. It is common knowledge that “ disintegrations, cracks, bunches, defects and open joints ” develop in our city streets which are subjected to strains from heavy traffic and ever-increasing building operations, notwithstanding the utmost care in the use of material and workmanship in the original construction. To provide for the repair of these defects, the city secured the obligation of the contractor to make good, but for that the city, and not the adjacent owners, must pay.

I find that embraced in the contract under consideration, and included in the price paid by the city to the contractor is the cost of maintaining the street in repair, after completion, that that obligation vitiated the contract and that the assessment imposed on plaintiff’s property was void and illegal and that the board of assessors was without jurisdiction or authority to levy or confirm that assessment. (See Bradshaw v. City of Jamestown, 125 App. Div. 86.)

In that case the court said (at pp. 87-88), in part as follows: “ The charter only requires the cost of the original pavement to be paid by the abutting owners, leaving the city at large to bear the expense of keeping the pavement in repair. * * *. In the Featherstonhaugh case it was made to appear that, with proper material and workmanship, the pavement would remain in good condition for at least the period named in the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brink v. Kansas City
198 S.W.2d 710 (Supreme Court of Missouri, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
124 Misc. 622, 209 N.Y.S. 429, 1925 N.Y. Misc. LEXIS 768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/segfried-construction-co-v-city-of-new-york-nynyccityct-1925.