SEECO, Inc. and Southwestern Energy Company v. K.T. Rock, LLC

416 S.W.3d 664, 2013 WL 5368746, 2013 Tex. App. LEXIS 12093
CourtCourt of Appeals of Texas
DecidedSeptember 26, 2013
Docket14-12-00357-CV
StatusPublished
Cited by11 cases

This text of 416 S.W.3d 664 (SEECO, Inc. and Southwestern Energy Company v. K.T. Rock, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SEECO, Inc. and Southwestern Energy Company v. K.T. Rock, LLC, 416 S.W.3d 664, 2013 WL 5368746, 2013 Tex. App. LEXIS 12093 (Tex. Ct. App. 2013).

Opinion

OPINION

SHARON McCALLY, Justice.

SEECO, Inc. entered into a three-year purchase agreement (the “Contract”) with K.T. Rock, LLC for the purpose of buying crushed rock primarily for its gas well development operations in central Arkansas. SEECO bought substantially less rock from K.T. than anticipated during the first two years of the Contract.

Shortly into the third year of the Contract, K.T. sued SEECO and Southwestern Energy Company, SEECO’s parent company, for breach of contract and fraudulent inducement. SEECO counterclaimed for breach of contract. After a trial, the jury found that SEECO complied with the Contract and that K.T. failed to comply with it. However, the jury awarded SEECO no damages for KT.’s failure to comply. Further, the jury found, by clear and convincing evidence, that SEECO fraudulently induced K.T. to enter into the Contract. The jury found that $2.5 million would compensate K.T. for its damages for SEE-CO’s fraud and that $500,000 should be assessed against SEECO and awarded to K.T. in exemplary damages. After a hearing, the trial court entered judgment (1) awarding K.T. actual damages from SEE-CO and Southwestern Energy, jointly and severally, 1 of $2.5 million and exemplary damages of $500,000, (2) that SEECO take nothing on its breach-of-contract claim, and (3) denying KT.’s and SEECO’s motions for recovery of attorney’s fees.

On appeal, SEECO challenges the legal and factual sufficiency of the evidence to support the jury’s fraudulent inducement finding and the jury’s damages and punitive damages awards upon which the trial court’s judgment is based. Because we agree that there is legally insufficient evidence to support KT.’s fraudulent inducement claim, we reverse and render a take nothing judgment on that claim. SEECO further contends that the trial court erred in denying its motion for attorney’s fees because it was the prevailing party under its Contract with K.T. Rock. SEECO was *667 entitled to recover attorney’s fees under the Contract because it was the prevailing party on KT.’s breach-of-contract dispute. We reverse the trial court’s judgment as to the attorney’s fees issue and remand that issue only for further proceedings consistent with this opinion.

BACKGROUND

SEECO is in the oil and gas exploration business in the Fayetteville Shale area of central Arkansas. As part of its operations, SEECO buys large quantities of rock to create well pads, roads, and related facilities. This dispute centers around SEECO’s DeSoto Project, a gas exploration and drilling project located in the Fayetteville Shale area. K.T., owned by Keith Waddell, Paul Hudson, and Ben Moorhead, was formed in 2007 after Wad-dell began discussions with SEECO’s De-Soto Field Manager in Arkansas, George Sheffer. Based on its drilling plans, SEE-CO estimated it would need approximately one million tons of rock from fall 2007 through mid 2008. Waddell suggested to Sheffer that K.T. could provide 600,000 tons of rock a year to SEECO.

After some initial negotiation with K.T., SEECO put out a request for bids; K.T. was the successful bidder. K.T. purchased rock-crushing equipment sufficient to operate crushing activities out of two quarries simultaneously. K.T. also hired numerous personnel so that it could begin its rock-crushing operations out of a quarry in the far-east area of the Fayetteville Shale area. SEECO and K.T. entered into the Contract in August 2007. The Contract provided that SEECO would buy at least 500,000 tons of material per year, although SEECO “at its option” could “defer purchase of any of its yearly requirement of 500,000 tons of [rock] so long as [SEECO] purchase[d] the deferred tonnage before the end” of the three-year term of the Contract. K.T. was required to make at least 2,000 tons of three-inch rock and at least 5,000 tons of SB2 rock available each day (the “daily tonnage”) at a quarry specified by SEECO. 2 SEECO could adjust the daily tonnage amounts at any time during the term of the Contract. K.T. agreed that SEECO could have access to and “load out capability” for the rock twenty-four hours a day, seven days a week. The Contract also provided that K.T. “occasionally” would be required to move its equipment from quarry to quarry at the request of SEECO. SEECO would specify from which quarry it would purchase rock by giving K.T. at least seven days’ notice before the date of purchase; K.T. was to move its equipment to the specified quarry and have its daily tonnage available for SEECO’s purchase within twenty-four hours after the end of the notice period.

The Contract also provided the following “early buyout” provision:

At its sole discretion, [SEECO] may at any time elect to terminate this Agreement during the Initial Term [the first three years of the Contract] by giving [K.T.] written notice of such termination as of the date provided in such notice.... In such event, [SEECO] shall pay [K.T.] the fee (“Early Buyout Fee”) as calculated in Exhibit “B” attached hereto. 3

If K.T. failed to make available to SEECO the daily tonnage at the specified quarry, SEECO was entitled, after notifying K.T., to suspend performance. Any rock that *668 SEECO purchased from a third-party supplier while performance was suspended was to be deducted from SEECO’s purchase obligations under the Contract. This remedy was in addition to SEECO’s right to terminate the Contract in the event of K.T.’s failure to perform its obligations (other than those excused by Force Majeure) under the Contract.

The Contract could not be amended unless in writing and executed by each party. All notices under the Contract were required to be in writing. Finally, the Contract contained the following attorney’s fee clause:

If any action at law or in equity, including an action for declaratory relief and collection of an account, is brought to enforce or interpret the provisions of this Agreement, the prevailing Party shall be entitled to recover reasonable attorney’s fees from the other Party, which fees may be set by the court in the trial of such action or may be enforced in a separate action brought for that purpose, and which fees shall be in addition to any other relief which may be awarded.

The Contract was executed and effective on August 15, 2007.

During the first year of the Contract, from August 15, 2007 to August 14, 2008, SEECO purchased 249,914 tons of rock from K.T. SEECO purchased over 1.5 million tons of rock from other quarries during that year. From August 15, 2008 to August 14, 2009, SEECO purchased 300,-585 tons of rock from K.T. and almost one million tons of rock from others. Thus, by the third year of the Contract, August 15, 2009 to August 14, 2010, SEECO needed to (1) purchase 1,019,681 tons of rock to fulfill its obligation or (2) exercise the buyout option before the end of the Contract’s term.

Sheffer and Larry Hadley, SEECO’s Energy Construction Superintendent, both explained that the largest reason for the shortfall in purchasing rock from K.T. during the first years of the Contract was K.T.’s quarry locations: contractors who built the well pads for SEECO used the closest quarry to the well sites, and KT.’s quarry locations were not the closest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
416 S.W.3d 664, 2013 WL 5368746, 2013 Tex. App. LEXIS 12093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seeco-inc-and-southwestern-energy-company-v-kt-rock-llc-texapp-2013.