Security Banking & Investment Co. v. Flanagan

241 S.W. 702, 1922 Tex. App. LEXIS 909
CourtCourt of Appeals of Texas
DecidedApril 21, 1922
DocketNo. 2531.
StatusPublished
Cited by16 cases

This text of 241 S.W. 702 (Security Banking & Investment Co. v. Flanagan) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Security Banking & Investment Co. v. Flanagan, 241 S.W. 702, 1922 Tex. App. LEXIS 909 (Tex. Ct. App. 1922).

Opinions

On the 29th day of April, 1919, the appellee, Flanagan, entered into a written contract with the appellant Security Banking Investment Company, an unincorporated association, to complete the drilling of a well in Jones county, Tex. The well was at the time 620 feet deep, and the appellee was to drill it, if necessary, to the depth of 3,000 feet and to receive as compensation therefor the sum of $7 per foot. This suit was later instituted by him against the Security Banking Investment Company, and *Page 704 H. L. Houghton, H. E. Trowbridge, and F. C. Shoemaker, as trustees of the company. The suit is based upon the alleged breach of the written contract above referred to. The contract provided that the appellants were to furnish certain equipment and material to be used in the drilling operations. It contains, among others, this clause:

"It is further provided that, if the party of the second part (Flanagan) should discover a paying sand, that the party of the first part (Security Banking Investment Company) will pay to the party of the second part the sum of $10 per foot while drilling in and through said sand; it being further understood that, if the said party of the second part shall be delayed in the drilling of said well on account of the failure of the party of the first part to carry out their part of this contract, that for such delays, which are the necessary cause and within the control of the said parties of the first part, the said party of the second part is to receive the sum of $100 per day; provided however, that the last above provision shall not be applicable in event of strikes, insurrections, riots, acts of Providence, martial law, or anything beyond the control of the said parties of the first part. It being understood between the parties hereto that the party of the second part is to do all of his own underreaming, the party of the first part to furnish the underreamer."

It was alleged by the appellee that, about May 1, 1919, he entered upon the discharge of his duties under the contract and drilled about 2.205 feet; that, when that depth was reached, the appellants wrongfully discharged him and forcibly compelled him to abandon the premises, thus rendering it impossible for him to complete the well to a depth of 3.000 feet. He claims, under the terms of the contract of $7 per foot, that he is entitled to $15,405. He also alleges that, on account of the failure of the appellants to furnish water, fuel, suitable rigging, and tools, and, on account of the defective casing, he was delayed 151 days. These items are set out in a statement attached to his petition. He alleges that, on account of such delays, he is entitled to the further sum of $15,100, under the provisions of the contract allowing him $100 per day. He further alleges that, if he had been permitted to complete the well, he would have been entitled to $1,225 additional, and this could have been done at a cost of $550. He admits the payment of $6,400 by the appellants upon their contract. He asks judgment for the aggregate sum of $30,659 and for the foreclosure of the lien on the leasehold, oil well, rig, tools, casing, and other equipment.

The appellants answered generally and specially, putting in issue the grounds of liability contained in the appellee's petition.

The case was submitted on special issues, and a verdict returned in which the jury found, in substance, that the failure of the appellee to drill the well to the depth of 3.000 feet was caused by the wrongful acts of the appellants, committed in violation of their contract; that the appellee did not voluntarily abandon his contract, and that he was delayed 86 1/2 days by reason of the failure of the appellants to perform their contract duties, and that he was entitled to the stipulated damages for that time. The court rendered a judgment in favor of the appellee against the appellants the Security Banking Investment Company, and against each of the trustees jointly and severally, for the aggregate sum of $18,703.97.

Most of the questions raised in this appeal relate to the claim of the appellee for damages resulting from what the parties call "shut down time," that is, damages resulting from delays in the prosecution of the drilling operations, for which the appellants were held responsible. The appellee alleged that he had lost 151 days, and the jury found that he had lost 86 1/2 days, because of the failure of the appellants to comply with the terms of their contract. The fact that the delays complained of occurred is not here contested, but appellants deny that those delays resulted from the failure of the appellants to comply with the terms of their contract.

While the appellee was on the stand, he was permitted to testify as follows, over the objection of the appellants:

"I didn't have any understanding with him [F. C. Shoemaker] about finances or paying me some money; I could not get any satisfaction out of him, or get the boys down here and get this matter straightened up; I wanted him to give me money enough to pay off the tool dressers; I was having trouble with the tool dressers; they wanted their money so I could go ahead and get some of this shut down time and go ahead. I never finally came to any understanding with him [Shoemaker]. He wanted me to take $1,500 for my shut time, and I refused to do it. Finally he came to $2,000, and I told him, `Nothing doing.' Then he said, `I can't settle with him;' and he says to Mr. Houghton, `You settle with him.' He says, `I can't.' He wanted me to take $1,500 for my shut down time, and I refused to do so. Mr. Houghton and I came to terms in a little hit, and he went and saw Mr. Shoemaker, and Mr. Shoemaker refused to come through. Mr. Houghton was his associate there in business. So he finally offered me $2.000 and I says, `There's nothing doing,' and I caught the train and came back home."

The appellants objected to that testimony upon the ground that it related to an offer of compromise made by them to the appellee in settlement of his claim of damages for "shut down" time. The objection was overruled, and that ruling is assigned as error.

It is well established that concessions made as offers to compromise and settle disputed claims cannot be introduced in evidence for the purpose of showing as admission of liability on the part of the debtor. The record does not, in this *Page 705 instance, disclose the existence of any previously pending controversy concerning this demand for "shut down" time. The pleadings of the appellee, which set out a claim for damages resulting from those delays, were composed of a number of distinct items. These consisted of different delays, occurring at different times and caused by differing conditions. It did not appear that, at the time this conversation between the appellee and Shoemaker took place, the latter denied all liability whatever on that account. Prior to that time Flanagan had, according to his own testimony, sent in bills for such delays, but these were ignored. On that occasion he was insisting on the payment of $5,000; Whether or not that was all he then claimed is not shown. No particular item seems to have been in dispute. Shoemaker's offer of $2,000 was rejected apparently because it was not sufficient to meet appellee's entire demand, not because it eliminated any particular item. The offensive testimony was harmful to the appellants only as tending to show as admission by Shoemaker of some liability on the claim for "shut down" time. Assuming that such a result might have made the admission of the evidence reversible error, subsequent proceedings show that the appellants condoned the offense by voluntarily offering testimony to the same effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Houston v. Howe & Wise
323 S.W.2d 134 (Court of Appeals of Texas, 1959)
United Sales Company v. Curtis Peanut Co.
302 S.W.2d 763 (Court of Appeals of Texas, 1957)
Minchen v. First Nat. Bank of Alpine
263 S.W.2d 601 (Court of Appeals of Texas, 1953)
Vise v. Foster
247 S.W.2d 274 (Court of Appeals of Texas, 1952)
Tunstill v. Pelton
155 S.W.2d 653 (Court of Appeals of Texas, 1941)
Desdemona Gasoline Co. of Texas v. Garrett
90 S.W.2d 636 (Court of Appeals of Texas, 1936)
Texas & N. O. R. v. Singler
28 S.W.2d 946 (Court of Appeals of Texas, 1930)
Longhart Supply Co. v. Keystone Pipe & Supply Co.
26 S.W.2d 389 (Court of Appeals of Texas, 1930)
Long Bell Lumber Co. v. Hampton
20 S.W.2d 1081 (Court of Appeals of Texas, 1929)
Hewitt v. Buchanan
4 S.W.2d 169 (Court of Appeals of Texas, 1927)
Slaton State Bank v. Amarillo Nat. Bank
288 S.W. 639 (Court of Appeals of Texas, 1926)
St. Louis Southwestern Ry. Co. of Texas v. Adcock
269 S.W. 144 (Court of Appeals of Texas, 1924)
Lipshitz v. Earl Fruit Co. of Northwest
265 S.W. 1048 (Court of Appeals of Texas, 1924)
Security Banking & Investment Co. v. Flanagan
262 S.W. 741 (Texas Commission of Appeals, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
241 S.W. 702, 1922 Tex. App. LEXIS 909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/security-banking-investment-co-v-flanagan-texapp-1922.