Security Bank & Trust Co. v. Pocono Web Press, Inc.

441 A.2d 1321, 295 Pa. Super. 455, 1982 Pa. Super. LEXIS 3507
CourtSuperior Court of Pennsylvania
DecidedFebruary 26, 1982
Docket1436
StatusPublished
Cited by3 cases

This text of 441 A.2d 1321 (Security Bank & Trust Co. v. Pocono Web Press, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Security Bank & Trust Co. v. Pocono Web Press, Inc., 441 A.2d 1321, 295 Pa. Super. 455, 1982 Pa. Super. LEXIS 3507 (Pa. Ct. App. 1982).

Opinion

HESTER, Judge:

This appeal involves what appears to be a question of First impression in this Commonwealth, to-wit:

“Under the Mechanics’ Lien Law of 1963, Act of August 24, 1963, P.L. 1175, No. 497, as amended, 49 P.S. Section 1101 et seq, if a contractor files a waiver of liens and commences work on a structure prior to the recording of a mortgage, may other contractors who thereafter contract directly with the owner of the property obtain priority over the mortgage, on the basis of a Mechanics’ Lien claim, in the distribution of the proceeds of a Sheriff’s Sale?”

The basic facts are not in dispute. On September 14, 1977, Robert N. Hartman, a foundation contractor, filed a Waiver of Liens in the Prothonotary’s Office of Monroe County, waiving for himself and for his subcontractors the right to file any Mechanics’ Lien claims concerning the construction of a commercial building. On or about the same date, “visible commencement” of the excavation work *457 for the commercial building began on property owned by Pocono Web Press, Inc. On October 6, 1977, appellant Bank recorded a construction mortgage from Pocono in the amount of $310,000.00.

Appellee Lawton-Huffman, Inc. entered into a separate and independent contract with the owner, Pocono, to provide heating and air conditioning services and materials. Lawton began work on December 1, 1977, finished its work on December 29, 1977, and was not paid. Lawton filed a Mechanics’ Lien on March 9, 1978 in the amount of $6,095.00 against Pocono.

Appellee Marshalls Creek Electric, Inc. entered into a separate and independent contract with the owner to provide services and materials. Marshalls began work on November 12, 1977, finished on January 4, 1978, and was not paid. Marshalls subsequently filed a Mechanics’ Lien claim in the amount of $1,500.00 against Pocono.

Both mechanics’ lien claims were perfected and taken to judgment in due course, and not challenged below in any respect, except as to their priority over the construction mortgage. 1

A Sheriff’s Sale was held on June 20, 1979 on the basis of a default judgment obtained by the Bank in its mortgage foreclosure action against Pocono. The Bank made the highest bid of $20,000.00 plus costs, and when the Sheriff published his schedule, by which he indicated that costs had been collected and the balance covered by the receipt of counsel for the Bank, appellees Lawton and Marshalls filed written exceptions, requesting the appointment of an auditor pursuant to Pa.R.C.P. 3136.

The auditor filed a report, including findings of fact and conclusions of the law, granting appellees’ exceptions to the proposed Sheriff’s distribution, finding that the Mechanics’ Lien claims of appellees were entitled to priority over the Bank’s mortgage. The Court of Common Pleas of Monroe *458 County approved the auditor’s report by Order dated April 10, 1980.

The Bank advances two alternative arguments in support of its contention that the lien of its mortgage is entitled to priority over appellees’ mechanics’ liens. First, the Bank contends that appellees’ claims should be subordinated since they had notice of the Bank’s mortgage. Secondly, the Bank contends that the Mechanics’ Liens should be subordinated to its mortgage since both appellees contracted directly and independently with the owner and did not perform any work under the original contract with Hartman. 2

We disagree and, therefore, affirm the lower court’s order.

First, the Bank concedes that both appellees are “Contractors”, as defined by 49 P.S. Section 1201(4), as opposed to “Subcontractors”, as defined by 49 P.S. Section 1201(5). 3

Since both appellees are “contractors” and since both appellees performed labor and services relating to the “erection and construction” (49 P.S. Section 1201(10)) of an “improvement” (49 P.S. Section 1201(1)) for the owner of the property, both appellees have a right to a lien pursuant to Article III of the Act, 49 P.S. Section 1301 et seq.

However, a claimant (contractor or subcontractor) may waive his right to file a lien pursuant to Article IV of the Act, 49 P.S. Section 1401 et seq.

Section 401 of the Act states:

“A contractor or subcontractor may waive his right to file a claim by a written instrument signed by him or by any conduct which operates equitably to estop such contractor or subcontractor from filing a claim.”
49 P.S. Section 1401.

Section 402 of the Act states:

*459 “A written contract between the owner and contractor or a separate written instrument signed by the contractor, which provides that no claim shall be filed by anyone, shall be binding; but the only admissible evidence thereof, as against a subcontractor, shall be proof of actual notice thereof to him before any labor or materials were furnished by him; or proof that such contract or separate written instrument was filed in the office of the prothonotary prior to the commencement of the work upon the ground or within ten days after the execution of the principal contract or not less than ten days prior to the contract with the claimant sub contractor, indexed in the name of the contractor as defendant and the owner as plaintiff and also in the name of the contractor as plaintiff and owner as defendant...”
49 P.S. Section 1402.

The priority of the lien is determined by Section 508 of the Act, which states:

“The lien of a claim filed under this act shall take effect and have priority: (a) in the case of the erection or construction of an improvement, as of the date of the visible commencement upon the ground of the work of erecting or constructing the improvement; ...”
49 P.S. Section 1508. 4

Section 402 of the Act, 49 P.S. Section 1402, is not applicable to the instant case since Hartman’s waiver of liens, which was filed on September 14, 1977, waived the right to file a Mechanics’ Lien claim only for himself and his “subcontractors”. The Bank concedes that the appellees are not “subcontractors”. 5

*460 Concerning Section 401 of the Act, 49 Pa. Section 1401, it is clear that neither appellee explicitly waived its right to file a claim by any written instrument. The question thus becomes whether there was “. .. any conduct which operates equitably to estop such contractor or subcontractor for filing a claim”.

In Wood v. United States Steel Corporation, 383 Pa. 158, 118 A.2d 199, 200 (1955), the Supreme Court stated “. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commerce Bank/Harrisburg, N.A. v. Kessler
46 A.3d 724 (Supreme Court of Pennsylvania, 2012)
FEDERAL LAND BANK OF BALT. v. Sustrik
533 A.2d 169 (Supreme Court of Pennsylvania, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
441 A.2d 1321, 295 Pa. Super. 455, 1982 Pa. Super. LEXIS 3507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/security-bank-trust-co-v-pocono-web-press-inc-pasuperct-1982.