Seaman Unified School District No. 345 v. Casson Construction Co.

594 P.2d 241, 3 Kan. App. 2d 289, 3 A.L.R. 4th 1013, 1979 Kan. App. LEXIS 197
CourtCourt of Appeals of Kansas
DecidedMay 4, 1979
Docket49,215
StatusPublished
Cited by16 cases

This text of 594 P.2d 241 (Seaman Unified School District No. 345 v. Casson Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaman Unified School District No. 345 v. Casson Construction Co., 594 P.2d 241, 3 Kan. App. 2d 289, 3 A.L.R. 4th 1013, 1979 Kan. App. LEXIS 197 (kanctapp 1979).

Opinion

Meyer, J.:

This is an appeal from a judgment holding defend *290 ants jointly and severally liable for water damage caused to plaintiff’s (Seaman’s) gymnasium floor, on theories of express warranty and negligence, based on improper design and construction. Each defendant has appealed the court’s rulings.

The primary question is which, if any, of the defendants in this case is liable for such damage. We must thus determine whether defendant Casson Construction Company, Inc. (Casson) is liable under a theory of either express warranty or negligence, or both; whether defendants Glenn A. Horst, Joseph W. Terrill, and Gary G. Karst, d/b/a Horst, Terrill and Karst (Architects) are liable for faulty design or faulty follow-up procedure, or both; and whether defendant U. S. Engineering Company, Inc. (Engineering) is Hablé for specific acts of negligence.

The damage occurred when water from heavy rains entered the newly constructed gym (which was constructed partially below grade) from the northwest stairwell, flooding the wood floor. The first such rain was on April 18, 1970, at which time more than two-thirds of the gym floor was covered by water. On May 14, 1970, a rain of somewhat less intensity again resulted in flooding of the gym floor. During yet another rain, in June of 1970, water entered the areaway but did not reach the gym floor.

Engineering’s foreman had covered the top of a four-inch drain at the bottom of the stairwell with tape some time in October of 1969, but he had perforated the tape in a number of places prior to April 18, 1970. Casson completed the finish grading of the area surrounding the gym shortly before April 18,1970. Following the April 18 flooding, the Engineering foreman removed the tape completely. Nonetheless, on May 14, the gym floor flooded again. Following the May 14 incident, Architects tore out and replaced the ten feet of sidewalk closest to the stairwell, adding a step and sloping the walk away from the stairwell. Casson made some changes in the grading. The surrounding area was ultimately regraded after June, 1970.

Turning first to the question of Casson’s liability, we note the following express findings of the trial court:

“2. Plaintiff has sustained the burden of proving that Casson breached the express warranty that all work would be of good quality, free from faults and defects and in conformance with the contract documents in the following respects:
a. In failing to grade the area to the west of the gymnasium in conformance with the plans and specifications;
*291 b. In failing to grade the area immediately to the north of the gymnasium and east of the sidewalk leading to the northwest areaway in conformance with the plans and specifications;
c. In failing to backfill the loose laid stone wall next to the northwest areaway with the type of material specified by the plans and specifications (i.e. clay).
“3. Plaintiff has sustained the burden of proving that Casson was negligent in the following respects:
a. In failing to grade the area to the west of the gymnasium in conformance with the plans and specifications;
b. In failing to grade the area immediately to the north of the gymnasium and east of the sidewalk leading to the northwest areaway in conformance with the plans and specifications;
c. In failing to backfill the loose laid stone wall next to the northwest areaway with the type of material specified by the plans and.specifications (i.e. clay);
d. In failing to take all reasonable precautions to protect its work (i.e., the gymnasium floor) as required by Article 10.2.1 of the contract;
e. In failing to maintain northwest areaway free of debris on or about the 17th or I8th day of April, 1970.
“4. The foregoing acts of negligence on the part of Casson were direct, contributing and proximate causes of the damage to the gymnasium floor sustained by Seaman.
“5. Casson was not a ‘general contractor’ but merely a ‘prime contractor.’ The Court in construing the four corners of the contract in the instant case finds that such contract was a ‘specified manner and method’ contract as opposed to an ‘end result’ contract. (Kansas Turnpike Authority v. Abramson, 275 F.2d 711; par. 1, supra) Casson had fully completed the gymnasium floor in accordance with the plans and specifications and is, therefore, not liable to Seaman under a straight contract theory as set forth in the corrected memorandum decision and order filed September 21, 1976.
“6. The motion of Casson for involuntary dismissal at the close of plaintiff’s case on the ground of election of remedies should be overruled for the reason that the theories of negligence and breach of express warranty are not inconsistent as the issues are framed and presented in the instant case. (McFeeters v. Renollet, 210 Kan. 158, 163)”

Thorough examination of the record on appeal reveals substantial competent evidence to support the trial court’s finding that Casson’s finish grading of the area surrounding the gymnasium was negligent and that this negligence caused or concurrently caused the damage to Seaman’s gym. A survey on May 6, 1970, indicated that some 3,100 square feet of surrounding surface area drained into the stairwell; according to Architects’ plans, 412 square feet of ground water should have drained into that well. Thus it is clear that Casson is liable in this case, and it remains for us to decide whether either Architects or Engineering, or both, are also liable.

*292 As to Architects, the court made the following findings:

“8. Plaintiff has sustained the burden of proving that the Architects were negligent in requiring the sidewalk running south to the northwest areaway to slope to the south and thereby causing large amounts of water to collect in such areaway. Although Joe Shutter, the employee of Casson brought such obvious defect to the attention of Henry Lockard, the supervisor and employee of the Architects, the Architects refused to change their plans and specifications in this respect prior to the date the gymnasium floor was damaged by water on or about the 17th or 18th day of April, 1970.
“9. Such conduct on the part of Architects requiring the sidewalk to slope to the south directly into the areaway is negligence within the common knowledge of laymen and no expert testimony is required to establish such conduct constituted negligence on the part of Architects.
“10. Such negligence on the part of Architects was a direct, contributing and proximate cause of the water damage to the gymnasium floor on or about the 17th or 18th day of April, 1970.
“11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Arkansas City v. Bruton
166 P.3d 992 (Supreme Court of Kansas, 2007)
City of Arkansas City v. Bruton
137 P.3d 508 (Court of Appeals of Kansas, 2006)
Bi-State Development Co. v. Shafer, Kline & Warren, Inc.
990 P.2d 159 (Court of Appeals of Kansas, 1999)
In Re the Estate of Maxedon
946 P.2d 104 (Court of Appeals of Kansas, 1997)
New Dimensions Products, Inc. v. Flambeau Corp.
844 P.2d 768 (Court of Appeals of Kansas, 1993)
Gillespie v. Seymour
823 P.2d 782 (Supreme Court of Kansas, 1991)
McKee v. City of Pleasanton
750 P.2d 1007 (Supreme Court of Kansas, 1988)
Palmer v. AH Robins Co., Inc.
684 P.2d 187 (Supreme Court of Colorado, 1984)
Ingram v. Howard-Needles-Tammen & Bergendoff
672 P.2d 1083 (Supreme Court of Kansas, 1983)
Juhnke v. Evangelical Lutheran Good Samaritan Society
634 P.2d 1132 (Court of Appeals of Kansas, 1981)
Equity Investors, Inc. v. Academy Insurance Group, Inc.
625 P.2d 466 (Supreme Court of Kansas, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
594 P.2d 241, 3 Kan. App. 2d 289, 3 A.L.R. 4th 1013, 1979 Kan. App. LEXIS 197, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaman-unified-school-district-no-345-v-casson-construction-co-kanctapp-1979.