Sealund Sisters, Inc. v. Planning Board

737 N.E.2d 503, 50 Mass. App. Ct. 346, 2000 Mass. App. LEXIS 890
Massachusetts Appeals Court·Decided October 26, 2000·No. No. 98-P-1517·Published·Cited by 2 cases

Opinion

Jacobs, J.

The plaintiff appeals from a judgment of the Superior Court affirming the decision of the defendant planning board denying its application for subdivision approval of a fifteen lot project. At issue before us is the first of two grounds1 relied upon by the board in rejecting the plaintiff’s plan. That ground was stated as:

[347] “The amount of blasting on site is too extensive. The length of time to complete the blasting, the number of trucks used to haul the blast material, associated noise and dust will be detrimental to the neighborhood.”

We vacate the judgment. We also vacate the board’s decision insofar as it is based upon this ground.

Procedural background. The plaintiff sought review of the board’s decision in the Superior Court pursuant to G. L. c. 41, § 81BB. That review was conducted on the basis of the parties’ joint statement of agreed facts, which was submitted with a request that the court, “in lieu of a trial,” render a decision based on those facts.2 The joint statement presented the issue to be determined as “[wjhether blasting, for which ... the issuance of a permit rests with the discretion of the local fire department may be a factor in a local planning board’s decision to deny approval to a definitive subdivision plan.” The only facts in the submissions to the court bearing on that issue were that the board “expressed concerns relative to the amount of blasting that would have to take place in order for the applicant to complete the subdivision. From start to finish, it was estimated that twelve (12) to eighteen (18) months of blasting would have to occur.”

In his memorandum of decision affirming the board’s action, the judge concluded that the board had not exceeded its authority in denying the plaintiff’s subdivision plan. He reasoned that “[wjhile tile Fire Chief of the Town may issue a blasting permit this does not exclude the Board from evaluating the nature and effect of such blasting on the area and its residents.” He also recognized the centrality of a planning board’s rules and regulations to its review of subdivision plans by citing Castle Estates, Inc. v. Park and Planning Bd. of Medfield, 344 Mass. 329 (1962), and setting forth the following extract from the purpose clause of the town of Weymouth’s subdivision rules and regulations:

“The subdivision regulations are adopted for the purpose of protecting the safety, convenience, and welfare of the [348] inhabitants of the Town of Weymouth by regulating the laying out and construction of ways in subdivisions . . . insuring sanitary conditions in the subdivision . . . the powers of the Planning Board shall be exercised with due regard for . . . reducing danger of life and limb in the operation of motor vehicles . . . securing safety in the case of fire, flood, panic and other emergencies . . . securing adequate provision for water, sewage, drainage . . . and other requirements where necessary in a subdivision. Rules and Regulations Governing the Subdivision of Land, Weymouth, Massachusetts: § 1.1 Purposes.”

Relying exclusively on that provision, he concluded: “It is clear that the extensive blasting required to remove approximately 80,000 cubic yards of rock over a twelve to eighteen month period is a valid factor for the Board to consider in protecting the ‘safety, convenience and welfare of the inhabitants of the Town of Weymouth.’ ”

Discussion. “A planning board exceeds its authority if requirements are imposed beyond those established by the rules and regulations.” Beale v. Planning Bd. of Rockland, 423 Mass. 690, 696 (1996), and cases cited. “A planning board’s subdivision rules and regulations thus define the standards that owners must meet . . . , as well as the grounds upon which a planning board may disapprove a plan.”3 Ibid. Those rules and regulations must be “comprehensive, reasonably definite, and carefully drafted, so that owners may know in advance what is or may be required of them and what standards and procedures will be applied to them.” Castle Estates, Inc. v. Park and Planning Bd. of Medfield, 344 Mass. at 334.

The purpose section of the town of Weymouth subdivision rules and regulations mirrors the purpose provision of the subdivision control law as set out in G. L. c. 41, § 81M. Clearly contemplated by a subsequent section of that statute, § 81Q, is the adoption of comprehensive rules and regulations that are faithful to the fulfillment of that purpose, broadly stated as [349] “protecting the safety, convenience and welfare of the inhabitants of the cities and towns.”4 G. L. c. 41, § 81M.

Absent a specific provision in its duly enacted rules and regulations, a planning board may not reject a subdivision plan based upon the anticipated impact of the subdivision upon surrounding areas. See Massachusetts Broken Stone Co. v. Planning Bd. of Weston, 45 Mass. App. Ct. 738, 742 (1998) (“Where a subdivision’s impact on water quality was not a matter for consideration under the rules and regulations of the planning board, such impact could not provide the basis for disapproval of the plan”). See also Canter v. Planning Bd. of Westborough, 4 Mass. App. Ct. 306, 307-309 (1976); Fairbairn v. Planning Bd. of Barnstable, 5 Mass. App. Ct. 171, 176-179 (1977); Vitale v. Planning Bd. of Newburyport, 10 Mass. App. Ct. 483, 485-486 (1980). If a specific impact of a completed subdivision may not be considered by a planning board if it has not enacted regulations on the subject, it follows that the effect of a subdivision construction process may not be the basis for disapproval of an otherwise conforming subdivision plan unless it violates a “comprehensive, reasonably definite, and carefully drafted” regulation of the planning board. There is no need for us to decide, and we do not intimate, whether any aspect of a subdivision’s construction process may be the subject of a planning board rule or regulation.5 We hold only that a planning board may not base its disapproval of a definitive subdivision plan on the impact of the associated construction process absent [350] such regulation. It would defeat the established objective of permitting owners to “know in advance what is or may be required of them and what standards and procedures will be applied to them,” Castle Estates, Inc. v. Park and Planning Bd. of Medfield, 344 Mass. at 334, if a planning board were permitted to base its disapproval of a subdivision plan exclusively upon the “safety, convenience, and welfare” provision of the purpose clause of its regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Sealund Sisters, Inc. v. Planning Board, 737 N.E.2d 503, 50 Mass. App. Ct. 346, 2000 Mass. App. LEXIS 890 (Mass. Ct. App. 2000).

737 N.E.2d 503 (Sealund Sisters, Inc. v. Planning Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Collings v. Planning Board
947 N.E.2d 78 (Massachusetts Appeals Court, 2011)