Seal Harbor III Condominium Trust v. Kaplan

7 Mass. L. Rptr. 292
CourtMassachusetts Superior Court
DecidedMay 1, 1997
DocketNo. 9304535
StatusPublished

This text of 7 Mass. L. Rptr. 292 (Seal Harbor III Condominium Trust v. Kaplan) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seal Harbor III Condominium Trust v. Kaplan, 7 Mass. L. Rptr. 292 (Mass. Ct. App. 1997).

Opinion

Hinkle, J.

Plaintiffs are trustees of the Seal Harbor III Condominium Trust for a residential building in Winthrop, Massachusetts. The plaintiffs brought this action against various parties in connection with the design, construction, marketing and sale of the condominium building, including defendant architect ADD, Inc., defendant site engineer Vanasse Hangen Brustlin, Inc., and defendant subcontractor E-Poxy Industries, Inc.1

On February 16, 1995, I allowed the motions for summary judgment of defendants ADD, Inc. and Vanasse. The plaintiffs’ appeal of this decision was denied. Seal Harbor III Condo Trust v. Sanford A. Kaplan, Civ. No. 95-J-185 (App.Ct. April 4, 1995) (Dreben, J.). Now before me is plaintiffs’ motion under Mass.R.Civ.P 54(b) to revise and vacate that order. For the reasons set forth below I ALLOW that motion. Also before me is defendant E-Poxy’s motion for summary judgment on statute of limitations and economic loss doctrine grounds, which, for the following reasons, is DENIED.

BACKGROUND

Construction of Seal Harbor III began in the spring of 1986, and unit owners began occupying the building in August 1987. The general contractor, Sanford Construction Co., Inc., is a defendant in this case. Defendant ADD, Inc. was retained to provide design services, including preparation of plans and specifications for construction of the condominium building. ADD, Inc. retained the site engineering services of Vanasse, who also provided permit procurement services. ADD, Inc. certified the date of substantial completion to be August 11, 1987. Plaintiffs charge ADD, Inc. and Vanasse with negligence in designing and/or selecting materials for use in construction of the building.

Sanford Construction purchased an expansion/contraction joint system for use in the construction of the underground parking garage from defendant E-Poxy. The plaintiffs allege that E-Poxy (1) negligently breached its duty to use reasonable care [293]*293in selecting materials for and/or constructing and installing portions of the condominium building and (2) breached an express warranty “that the Condominium would be habitable in its location adjacent to the sea” as well as an implied warranty of “generally acceptable quality consistent with the intended residential use” of the building.

Within months of completion of the building, it leaked air and water. The plaintiffs allege that “[c]ontributing systems included the roof and related systems, the windows, the sliding glass doors, the masonry, sealant and flashing systems, the indoor pool and spa, the underground membrane and expansion joints.” The seawall failed; the roof on the underground garage leaked; and the joints connecting the garage to the condominium building, as well as to the neighboring property, failed. The plaintiffs brought this action on July 29, 1993.

DISCUSSION

The court allows summary judgment where there are no genuine issues of material fact and the summary judgment record entitles the moving party to judgment as a matter of law. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976); Mass.R.Civ.P. 56(c). A parly moving for summary judgment who does not bear the burden of proof at trial must demonstrate the absence of a triable issue either by submitting affirmative evidence negating an essential element of the nonmoving party’s case or by showing that the nonmoving party is unlikely to submit proof of that element at trial. Flesner v. Technical Communications Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). In considering a motion for summary judgment, this court “view[s] the facts in the light most favorable to the party opposing summary judgment.” Graham v. Quincy Food Service Employees Assoc. & Hospital, Library & Public Employees Union, 407 Mass. 601, 603 (1990).

1. Plaintiffs’ motion to revise and vacate summary judgment

Plaintiffs request that I revise and vacate, under Mass.R.Civ.P. 54(b), my February 16, 1995 order against them. By that order I granted summary judgment for defendants ADD, Inc. and Vanasse on the ground that the economic loss doctrine operated to bar such an action for costs of repair and replacement of defective property. The economic loss doctrine “provides that, when a defendant interferes with a contract or economic opportunity due to negligence and causes no harm to either the person or property of the plaintiff, the plaintiff may not recover for purely economic losses.” Garweth Corp. v. Boston Edison Co., 415 Mass. 303, 305 (1993).

The plaintiffs make the following arguments: (1) Whether a building defect is sufficiently extensive to constitute property damage under the economic loss doctrine is a question of fact; (2) newly discovered evidence shows that window specifications and architectural certification caused a risk of personal injury to building occupants and property damage within units and common areas; (3) newly discovered evidence may show that the defendants’ negligence caused and may cause damage to building systems not included in the plaintiffs’ claim of deficiency, such as walls and ceilings. Plaintiffs contend that on the record developed through discovery since my February, 1995 order, summary judgment is inappropriate because material facts are now in dispute, and thus judgment cannot be entered as a matter of law.

In a case involving multiple claims or multiple parties, any order or other form of decision “which adjudicates fewer than all claims or the rights and liabilities of fewer than all the parties ... is subject to revision at any time before the entry of judgment adjudicating all the claims and the rights and liabilities of all the parties.” Mass.R.Civ.P. 54(b). My February 1995 order stated that, absent evidence that defects in the design “created a dangerous condition posing risk of accidental injury to person or to property other than the physical deterioration attributable solely to the failure of the products of construction themselves,” the plaintiffs’ claims were barred by the economic loss doctrine. I am now persuaded that newly discovered evidence and recent case law warrant a reversal of that order.

The recent depositions of Michael Hass, Sanford A. Kaplan, and James Kfoury, together with the affidavits of Joyce Aldrich and Arthur J. Hayes, raise substantial questions of damage to individual units and personal properly in common areas, as well as the roles of ADD, Inc. and Vanasse in such damage. There is evidence in the summary judgment record that the negligent acts of the defendants caused physical harm, principally the result of rain penetration, to the building, individual units, and cars parked in the garage. The summary judgment record also suggests a possible risk of personal injury from structural or material failure.

Further, since my prior decision, the Appeals Court has held that a plaintiff could recover under a negligence theory where he suffered economic losses as a result of damage to property in his possession but not his own. Priority Finishing Corp. v. LAL Construction Co., 40 Mass.App.Ct. 719 (1996). In that case, the plaintiff was in the business of custom dyeing and finishing raw fabrics for which he was the bailee. ”[P]laintiff not only sustained damage to the bailed fabrics in its possession but also reimbursed the owners of the fabrics for their replacement value.” Id. at 721.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garweth Corp. v. Boston Edison Co.
613 N.E.2d 92 (Massachusetts Supreme Judicial Court, 1993)
FMR Corp. v. Boston Edison Co.
613 N.E.2d 902 (Massachusetts Supreme Judicial Court, 1993)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Cameo Curtains, Inc. v. PHILIP CAREY CORP.
416 N.E.2d 995 (Massachusetts Appeals Court, 1981)
Marcil v. John Deere Industrial Equipment Co.
403 N.E.2d 430 (Massachusetts Appeals Court, 1980)
Priority Finishing Corp. v. LAL Construction Co.
667 N.E.2d 290 (Massachusetts Appeals Court, 1996)
Gailunas v. SPQR Management Associates, Inc.
6 Mass. L. Rptr. 311 (Massachusetts Superior Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
7 Mass. L. Rptr. 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seal-harbor-iii-condominium-trust-v-kaplan-masssuperct-1997.