SeaChange International, Inc. v. nCUBE Corp.

313 F. Supp. 2d 393, 2004 U.S. Dist. LEXIS 6479, 2004 WL 830968
CourtDistrict Court, D. Delaware
DecidedApril 7, 2004
DocketCIV.A.00-568-JJF
StatusPublished
Cited by1 cases

This text of 313 F. Supp. 2d 393 (SeaChange International, Inc. v. nCUBE Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SeaChange International, Inc. v. nCUBE Corp., 313 F. Supp. 2d 393, 2004 U.S. Dist. LEXIS 6479, 2004 WL 830968 (D. Del. 2004).

Opinion

MEMORANDUM OPINION

FAENAN, District Judge.

Presently before the Court is a Motion for a New Trial pursuant to Federal Rule of Civil Procedure 59 (D.I.178) filed by Defendant nCUBE Corporation (“nCUBE”). The Motion was denied by Orders of the Court (D.I.203, 209) dated September 30, 2002, for the reasons discussed below. 1

I. BACKGROUND

Plaintiff, Sea Change International, Inc. (“SeaChange”), filed its Complaint on June 13, 2000, alleging that nCUBE infringed SeaChange’s United States Patent No. 5,862,312 entitled “Loosely Coupled Mass Storage Computer Cluster” (“the ’312 Patent”).

SeaChange sought a preliminary injunction against nCUBE. On July 27, 2000, the Court conducted a hearing on the injunction motion. In response to the parties’ joint representation that the subject matter of this lawsuit was of substantial importance, the Court suggested that the matter proceed to a full trial within ninety (90) days. Both parties agreed, and, on July 28, 2000, a Scheduling Order was issued that provided for a pretrial conference and claim construction hearing on August 24, 2000, and a trial to commence on September 18, 2000 (D.I.41). Based on the expedited trial schedule, the Court denied the motion for preliminary injunction. Additionally, the parties requested, and the Court granted, bifurcation of the issues of damages and willfulness for discovery and trial until after the resolution of the infringement and validity issues. (D.I.54).

On August 29, 2000 the Court issued an Order construing the terms “interconnecting each one of said processor systems through a network for data communications with each other one of said processor systems” and “processor systems”. (D.I. 103). Shortly thereafter, SeaChange moved for summary judgment on the infringement issues and nCUBE conceded infringement of Claims 37, 38, 40, 41, 42, 52, 53, 57, 58. As a result, only the validity issues remained for trial and they were tried to a jury from September 18th through September 22, 2000. During trial, nCUBE requested the Court to construe the preamble term, “distributed computer system”, however, the Court declined this request. On September 25, 2000, the jury returned a verdict rejecting nCUBE’s claims of invalidity.

nCUBE cites three grounds for its Motion for a New Trial. First, nCUBE contends that the Court should have construed the term “distributed computer system.” nCUBE argues that the Court’s declining to construe the term constituted prejudicial error warranting a new trial. Second, nCUBE contends that the Court’s interpretation of the claim term “processor system” was erroneous and also warrants a new trial. Finally, nCUBE contends that a new trial is necessary because the verdict was against the great weight of the evidence.

II. LEGAL STANDARD

Federal Rule of Civil Procedure 59(a) permits the granting of a new trial but does not specify the grounds that may *396 support such a motion. Instead, the Rule permits the grant of a new trial for “any of the reasons for which new trials have heretofore been granted in actions at law in the courts-of the United States.” Fed R. Civ. P. 59(a). The ground cited by nCUBE and available before the promulgation of the Rules is where prejudicial error has been committed during the trial. Federal Rule of Civil Procedure 61 advises that prejudicial error exists when it appears to the court that the error is “inconsistent with substantial justice.” Fed.R.Civ.P. 61. With this standard in mind the Court will turn to a discussion of the errors claimed by nCUBE.

III. Claims of Error

. A. The Court Declined a Request to Interpret the Term “Distributed Computer System”

On page 4 of its Opening Brief nCUBE states: “[t]he preamble to claim 37 summarizes the invention as a ‘distributed computer system.’ ” (D.I. 179 at 4). nCUBE requested at the pretrial conference and during trial that the Court construe the term. nCUBE contends the term “distributed computer system” was integral to the jury’s ability to resolve nCUBE’s invalidity claims against the ’312 Patent. At the center of nCUBE’s argument is the testimony of SeaChange’s expert, Dr. Rhyne, who nCUBE asserts offered an opinion at trial different from the substance of his expert report. Specifically, nCUBE notes that at trial Dr. Rhyne testified that a distributed computer system “should be interpreted as a system where each of the computers that are there are independent and stand alone.” (Trial Tr. at 773). In Dr. Rhyne’s expert report, nCUBE says he defined “distributed system” as “[a] computer system in which several interconnected computers share the computing tasks assigned to the system.” (D.I. 179 at 4). nCUBE argues that if the jury had been instructed consistent with nCUBE’s position that “distributed computer system” does not require each computer to be wholly independent of the others, the jury would have been required to conclude, as nCUBE claimed, that the ’312 Patent was anticipated by the prior art. nCUBE further argues that the Court’s failure to construe the term in accordance with nCUBE’s instruction and the Court’s failure to instruct the jury of nCUBE’s interpretation permitted the jury to speculate on the meaning of the term when deliberating on the factual issue of whether the ’312 Patent was anticipated by the prior art. (D.I. 179 at 7, 8).

SeaChange responds to nCUBE’s contentions by asserting that the pretrial context of nCUBE’s request for an interpretation of the term “distributed computer system” was proper. SeaChange notes that the pretrial request was in the context of whether the constituent “processor systems” of the distributed computer system had to be real computers capable of running application software. SeaChange contends that, by the Court’s affirmative response to the question presented, the Court was correct to decline to give a general interpretation of the term since the Court had resolved the only relevant dispute. (D.I. 186 at 2, 3).

With regard to nCUBE’s request at trial for an interpretation of the term, Sea-Change contends that nCUBE’s request was no more than an effort to involve the Court in rebutting the opinion of Sea-Change’s expert, which was premised on his understanding of the ordinary meaning of the • term. SeaChange adds that by again declining to interpret the term, in the context of trial, the Court advised the parties that the Court’s interpretation of the term was consistent with the construction offered by SeaChange’s expert. (D.I. 186 at 3).

*397 nCUBE argues that the reason it sought an interpretation from the Court consistent with its interpretation of the term “distributed computer system” was so that the jury would have had to conclude that the ’312 Patent was anticipated by the prior art. (D.1.179 at 7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seachange International, Inc. v. C-Cor, Inc.
413 F.3d 1361 (Federal Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
313 F. Supp. 2d 393, 2004 U.S. Dist. LEXIS 6479, 2004 WL 830968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seachange-international-inc-v-ncube-corp-ded-2004.