Seaboard Surety Co. v. Spear

119 F.2d 849, 1941 U.S. App. LEXIS 4666
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 15, 1941
DocketNos. 8649, 8650
StatusPublished
Cited by4 cases

This text of 119 F.2d 849 (Seaboard Surety Co. v. Spear) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Co. v. Spear, 119 F.2d 849, 1941 U.S. App. LEXIS 4666 (6th Cir. 1941).

Opinion

HICKS, Circuit Judge.

Plaintiffs below, and herein called plaintiffs, supplied lumber and materials to Arthur Storm Company, a Michigan corporation, herein called Storm, which contracted with the Government for the construction of certain buildings at four conservation camps in the State of Michigan. At the same time (1934) Storm had contracts with the Government for similar work at two camps in Illinois. Defendant, Seaboard Surety Company, herein called surety, was surety on the usual performance bonds furnished by Storm under the Hurd Act, 40 U. S.C.A. § 270, for each of the six jobs.

Final settlements under the Act were effective ' on October 15, 1934. Plaintiffs brought, or intervened in, two separate suits at law upon the bonds. The first was voluntarily dismissed on April 7, 1936, on the mistaken belief, that at the time it was instituted, settlement had not been made. The second, commenced April 13, 1936, was held by this court to have been brought too late. United States, for Use and Benefit of F. B. Spear & Sons, v. Arthur Storm Co., 6 Cir., 101 F.2d 524.

This suit in equity was commenced on November 26, 1935, and was held in abeyance until the determination of the second suit at law. It was brought against the surety to reach certain sums paid to it by the Government on the contracts, the contractor having executed a power of attorney to the surety authorizing it to receive, endorse and collect checks drawn on the Treasury of the United States and to give full discharge for the same. The Dis[850]*850trict Court found that the surety took the payments for the purpose of indemnifying itself but held that the plaintiffs had an equitable lien to the extent of their claims on all sums paid with respect to the four Michigan camps and entered a judgment against the surety for the amount of their claims:

The surety company appealed, and in addition to its defense upon the main cause of action, insisted that plaintiffs had an adequate remedy at law. Plaintiffs brought a cross appeal from that part of the decree which denied interest upon the amount of their recovery.

The character of plaintiffs’ claims as to each camp, the contract price, the amounts allocated to each camp by the Government in the settlement, and the amounts of the bonds upon each, are set forth in the following table:

MICHIGAN

Camp Claims Cont. Price Settlement Bond

Goodar ............ ....... $ 248.49 $ 1,974.00 $ 1,674.00 $ 1,000.00

Lake........ ....... 3,791.63 4,000.00 3.800.00 2,200.00

Kenton ....... 1,295.81 2,200.00 1.620.00 1,100.00

Newberry.......... ....... 3,115.71 3,950.00 3,550.00 1,975.00

Total .......... ....... $8,451.64 $12,124.00 $10,644.00 $ 6,275.00

ILLINOIS

Camp Cont. Price Settlement Bond

Havana ........... Pittsfield........... $17,761.44 \ 18,381.44 J $ 4,377.53 $ 8,850.00 8,950.00

Total.......... $36,142.88 $ 4,377.53 $17,800.00

The Government deducted from the amount of the settlement certain penalties for delays in completion of the work at the Michigan camps. It completed the Illinois camps itself. Pursuant to an authorization from the contractor to the Quartermaster dated September 19, 1934, settlement check was ordered sent to the surety at its Detroit office but on October 21, 1935, it was actually sent to the contractor, care of the surety at its New York office. The settlement totalled $15,021.53 for all claims of which the sum of $10,644 was allocated to the Michigan camps. The surety set up the amount of the settlement in a special account.

The Currier Lumber Company supplied materials in the amount of $19,264.01 of which only $2,283.49 in amount was supplied to the Michigan camps. On November 8, 1935, the surety paid the Currier Company $11,500 from the special account in full discharge of its claims. This payment was made in a roundabout manner. On November 5, 1935, the National Bank of Detroit issued a check for $11,500 from funds wired to it from the special account above indicated. The check was payable to A. Kurzman, Secretary to the surety’s attorney in Detroit, and was endorsed by her to the order of the Currier Company.

As pointed out above, the major part of the Currier Company claim was for materials supplied to the Illinois camps. The Government’s allocation for all work at the Illinois camps was but $4,377.33. Hence, in paying the Currier Company $11,500 from funds received in the settlement, the surety was clearly taking money, that had been earmarked by the Government for the Michigan camps, to discharge Illinois claims.

Plaintiffs sought by their bill to have the funds received by the surety on account of each camp paid to the creditors thereof and to no other creditor of the Storm Company. The surety answered that the Currier Company settlement was made at the request of the contractor and argued in its brief and here that it was the right of the contractor to apply payments in any manner it saw fit.

The court found that the surety took possession of the funds for the purpose of indemnifying itself and the evidence sustains the finding. The contractor was undoubtedly insolvent and the court so found. It failed to pay its annual franchise fee in 1-934 and 1935, and its attorneys wrote [851]*851counsel for plaintiffs on October 30, 1935, that it had practically gone broke and that if any money was paid it would have to come from the bonding company. The surety obtained the power of attorney above indicated on September 22, 1934, “to receive, endorse and collect for and on behalf of the corporation any checks drawn on the Treasurer of the United States and to give full discharge therefor.”

This power of attorney gave the surety full control of the contractor’s money. It is true that there was evidence that the contractor negotiated the Currier Company settlement and requested its payment, but on November 7 (apparently 1933) surety’s attorney wrote plaintiffs’ attorney that the money it received “is used for the purpose of indemnifying itself against the liability that it has on its bonds and these bonds total about $23,000.00.”

But only $4,377.53 of the Government’s settlement was allocable to the Illinois contracts, and when the surety paid $11,750 to the Currier Company from that fund the difference between $11,750 and $4,377.53, or $7,372.47, was necessarily made up from the Michigan camp moneys. Since the surety was not liable on its bonds (U. S. v. Storm, supra), by depleting the Michigan moneys by $7,372.47, it virtually wiped out its liability to that extent on the Michigan contracts. Thus, on the surety’s theory of the case, that it could disburse the settlement moneys at will, it reduced its liability on the Michigan contracts from the $10,644 allocated thereon, to $3,371.53, the balance left in the fund. In making the Currier Company settlement in the manner it did, the surety was clearly controlling payments to its own advantage.

The crux of the controversy is, whether, as between plaintiffs and the surety, the plaintiffs, as claimants, were entitled to an equitable lien upon that part of the settlement which came into the hands of the surety in payment for work and materials at the Michigan camps.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Potts
161 F.2d 597 (Sixth Circuit, 1947)
General American Life Ins. Co. v. Anderson
156 F.2d 615 (Sixth Circuit, 1946)
Abell v. Anderson
148 F.2d 372 (Sixth Circuit, 1945)
Anderson v. General American Life Ins.
141 F.2d 898 (Sixth Circuit, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
119 F.2d 849, 1941 U.S. App. LEXIS 4666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-co-v-spear-ca6-1941.