Seaboard Surety Co. v. LMAC, LLC

16 Mass. L. Rptr. 55
CourtMassachusetts Superior Court
DecidedMarch 11, 2003
DocketNo. 011993BLS
StatusPublished

This text of 16 Mass. L. Rptr. 55 (Seaboard Surety Co. v. LMAC, LLC) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Surety Co. v. LMAC, LLC, 16 Mass. L. Rptr. 55 (Mass. Ct. App. 2003).

Opinion

van Gestel, J.

This matter is before the Court after a juiy-waived trial on claims by the plaintiff, Seaboard Surety Company (“Seaboard"), against two of the defendants, LPR, Inc. (“LPR”) and Gerard R. O’Brien (“O’Brien”). The Court’s findings of fact, rulings of law and an order for judgment follow.

FINDINGS OF FACT

This case involves the actions by a surety on certain payment and performance bonds provided for the benefit of the defendant LMAC, LLC (“LMAC”), a Massachusetts limited liability corporation, in relation to work performed principally in Minnesota and Rhode Island, also for bonds issued for projects elsewhere.2 Much of what is involved in this proceeding relates to a payment bond and a performance bond issued for a project in Minnesota (the “Minnesota bonds”), although a third payment bond for an unrelated matter in Narragansett, Rhode Island (the “Rhode Island bond”) is also in issue.

The project in Minnesota involved a certain “Agreement to Develop and Operate Communications Facilities,” dated December 23, 1997 (the “State Agreement”) and an “Engineering, Procurement and Construction Contract” dated October 13, 1998 (the “EPC Contract”).

LMAC was to design, engineer and construct a fiber optic network throughout Minnesota on behalf of an entity named ICS/UCN (the “Project”). In a manner not clear or material to this case, ICS/UCN and the State of Minnesota were the owners of the fiber optic network.

The Rhode Island matter involved a sanitary sewer system in the town of Narragansett.

All three of the bonds here were issued pursuant to a General Agreement of Indemnity (the “Indemnify Agreement”) running in favor of Seaboard, signed on October 23, 1997, by LMAC as “Contractor” and, among others, the two defendants, O’Brien and LPR, as “Indemnitors.” The Indemnity Agreement was executed by all parties in Boston, Massachusetts.

The first three introductory paragraphs of the Indemnity Agreement read as follows:

WHEREAS, LMAC, L.L.C. of Boston, Massachusetts (hereinafter called Contractor) may from time to time request Seaboard Surety Company . . . (hereinafter called Surely) to execute as surety or guarantor for the Contractor, or procure the execution of, certain surety bonds, undertakings, guaranties, stipulations or other obligatory instruments (all such instruments being collectively called Bonds); and
WHEREAS, the undersigned Indemnitors by executing this instrument represent that they have a material and beneficial interest in the obtaining of such Bonds by the Contractor (the Indemnitors and the Contractor being hereinafter called the Undersigned);
NOW, THEREFORE, in consideration of the execution of any one or more of such Bonds, the Undersigned, for themselves, their respective personal representatives, successors and assigns, jointly and severally, covenant and agree, with respect to all Bonds heretofore or hereafter- executed for the Contractor, that. . .

In the Indemnity Agreement, after the foregoing, there follow 21 separate sections detailing the obligations of indemnification by the Indemnitors, some of which, or parts thereof, will hereafter be quoted where appropriate. Perhaps the most significant of the sections of the Indemnity Agreement is Section 13. It reads in its entirety:

If it becomes necessary or advisable in the judgment of the Surety to control, administer, operate or manage any or all matters connected with the performance of any Bonded Contract for the purpose of attempting to minimize any ultimate loss to the Surety, or for the purpose of discharging its obligations of suretyship, the Undersigned hereby expressly covenant and agree that such action on the part of the Surety shall be entirely within its rights and remedies under the terms of this instrument and as Surety, and do hereby fully release and discharge the Surety, in this connection, from liability for all actions taken by it or for its omissions to act, except for deliberate and willful malfeasance.

On May 1, 2000, Seaboard notified LMAC of a claim on the Rhode Island bond by J.H. Lynch & Sons, Inc. (“Lynch”) in the amount of $137,479.15 for labor and materials. LMAC responded on May 9, 2000, to the effect that there were some items in dispute with regard to the Lynch billings and that the parties were in the process of resolving the issues. Seaboard forwarded Lynch’s proof of claim to LMAC on June 6, 2000, and solicited LMAC’s “written position and [its] intentions regarding this claim at [its] earliest convenience.” A brief response from LMAC was sent to Seaboard on June 12, 2000.

The matter did not get resolved and, by check dated December 6, 2000, Seaboard paid Lynch the amount of $141,054.05. This check appears to have been cashed about a week later.3

On June 22, 2000, Seaboard notified LMAC of another claim on the Rhode Island bond, this claim by Inland Waters, Inc. (“Inland”) in the amount of $13,688.20 for labor and materials. Seaboard, as is its practice, asked for information from LMAC regarding this claim. The proof of loss on the Inland claim was sent by Seaboard to LMAC on July 18, 2000, with a [57]*57further request for LMAC’s position and intentions regarding the claim.

By letter of October 25, 2000, Seaboard further pressed LMAC for information regarding the Inland claim, observing that suit by Inland had by then been filed. By another letter, dated March 6,2001, Seaboard again sought information about the Inland claim and reminded LMAC, LPR and O’Brien of their respective obligations under the Indemnity Agreement.

On March 8, 2001, Seaboard advised LMAC, through its counsel, that it was making a payment of $13,688.20 to Inland on that day. There is some confusion about this letter. It is Exhibit 8E. It bears a date of March 8, 2001, but seems to have been sent by facsimile on March 27, 2001. Seaboard’s check to Inland is dated March 27, 2001, and seems to have been cashed on April 4, 2001.4 In any event, the letter dated March 8, 2001, after advising LMAC of the payment by Seaboard, asks LMAC to pay Seaboard the amount Seaboard had paid to Inland.

On October 20, 1999, Seaboard first learned of a claim by ICS/UCN against LMAC relating to the Minnesota project, involving the Minnesota bonds. This was shortly after LMAC exercised its claimed rights to stop work on the Project. Among other things, ICS/UCN claimed that it had overpaid LMAC in the amount of $3,596,457.63 on the Minnesota Project. This resulted in litigation in Minnesota brought by LMAC against ICS/UCN. ICS/UCN initiated counterclaims against LMAC.

Also in Minnesota, a company named Northern Pipeline Construction Company (“Northern”) brought suit against Seaboard on the Minnesota bonds, seeking payment of $1,471,844.

By letter dated October 12, 2000, Seaboard notified LMAC, LPR and O’Brien of their obligations under the Indemnity Agreement with regard to the ICS/UCN and Northern claims. In that letter Seaboard also advised that it had engaged the Minnesota law firm of Fabyanske, Westra & Hart (“FW&H”) to defend it in these matters. Attorney Gregory T. Spalj (“Mr. Spalj”) was the principal FW&H lawyer involved.

LMAC engaged Attorney David E. Wandling (“Mr. Wandling”) of the Minnesota law firm of Wandling, Uggen, Rugara, Fowikes, LLC (“WURF”) to represent it in the Minnesota matters.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peerless Casualty Co. v. MARINUCCI BROS. & CO. INC.
147 N.E.2d 751 (Massachusetts Supreme Judicial Court, 1958)
Fishman v. Brooks
487 N.E.2d 1377 (Massachusetts Supreme Judicial Court, 1986)
Bushkin Associates, Inc. v. Raytheon Co.
473 N.E.2d 662 (Massachusetts Supreme Judicial Court, 1985)
Cambridge Biotech Corp. v. Pasteur Sanofi Diagnostics
433 Mass. 122 (Massachusetts Supreme Judicial Court, 2000)
Sharon v. City of Newton
769 N.E.2d 738 (Massachusetts Supreme Judicial Court, 2002)
Hartford Accident & Indemnity Co. v. Millis Roofing & Sheet Metal, Inc.
418 N.E.2d 645 (Massachusetts Appeals Court, 1981)
American Employers' Insurance v. Horton
622 N.E.2d 283 (Massachusetts Appeals Court, 1993)
Doe v. Nutter, McClennen & Fish
668 N.E.2d 1329 (Massachusetts Appeals Court, 1996)
Bratcher v. Moriarty, Donoghue & Leja, P.C.
763 N.E.2d 556 (Massachusetts Appeals Court, 2002)
Ionics, Inc. v. Liberty Mutual Insurance
15 Mass. L. Rptr. 508 (Massachusetts Superior Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
16 Mass. L. Rptr. 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-surety-co-v-lmac-llc-masssuperct-2003.