Seaboard Pools, Inc. v. Freeman

46 Misc. 2d 508, 259 N.Y.S.2d 999, 1965 N.Y. Misc. LEXIS 1871
New York Supreme Court·Decided May 24, 1965·Published

Opinion

Joseph Lief, J.

In this Special Term action the plaintiff seeks to foreclose a mechanic’s lien which it filed for the work, labor, and services performed and materials furnished. The complaint alleges that the parties entered into a contract and that the defendants agreed to obtain the financing. The plaintiff alleges that it duly performed the conditions of the contract; that it did its work between June 7 and June 10. In a second cause of action, the plaintiff seeks to recover the loss of profits. The defendants’ answer contains a counterclaim in addition to denials.

The plaintiff, a corporation engaged in the construction of swimming pools, and the defendant Donald Freeman, a homeowner on the North Shore of Long Island, on May 15, 1961 executed a paper writing providing for the construction of a pool on the latter’s property. Indorsed on the printed form used by the plaintiff was the note: “Final Financing to be determined”, followed by the initials of the signatories to the document. This paper also provided ‘ ‘ approximate date of construction June 1st, 1961”. Discussions as to terms of financing preceded and followed the execution of the instrument. At plaintiff’s request the defendant Donald Freeman signed a [509] statement containing additional information which was to be submitted by the contractor on an application for credit to a finance company. This statement indicated that repayment was to be made in 60 equal monthly installments. Then on May 24, 1961 the same defendant, at the plaintiff’s request, executed a retail installment obligation and a promissory note. While the balance due on the contract was $5,000, the defendant was to pay $6,750, which sum of course included the time charges. Almost immediately the plaintiff learned that the application for credit had been rejected and that the so-called “ approval ” of the finance company was conditioned on the plaintiff’s obtaining the signatures not only of the defendant Donald Freeman, but also that of his wife, to the note and a mortgage on their home securing its payment. This the defendants refused to do.

On June 1, 1961, on plaintiff’s application, a permit for the construction of the pool was issued. On June 7 the excavation was begun, materials were delivered to the site, and a substantial part of the work was completed on June 10 when plaintiff stopped work. There is no doubt that prior to June 1, on the date when the application for the permit was made and before plaintiff began its work, it knew that its application for credit had been rejected and that the defendants had refused to comply with the conditions imposed by the finance company. It must be assumed that since the work was proceeding on the property owned by the defendants and in which they lived at the time, they knew that the work was being done. Had the plaintiff proceeded to completion of the work, the court might have come to a conclusion different from that reached here.

The plaintiff then made various proposals to the defendant Donald Freeman for terms of financing which varied from those to which the said defendant had agreed after signing the “contract”, all of which the defendant rejected. Thus the situation remained throughout the Summer. In a letter dated September 8, 1961, the plaintiff, among other things, advised the defendant that it had obtained an approval by a bank. The plaintiff did not attempt nor offer to complete the pool. The defendant, in an answering letter, indicated that he would execute the notes if payment were postponed until May of 1962, in view of the fact that he would not have the use of the pool until the Summer of that year, and informed plaintiff that its failure to arrive at an agreement would be treated as an abandonment of the contract and that the defendant would seek to recover the expense incurred for restoration of the premises.

On June 1, 1962 the defendant again wrote to the plaintiff advising it that the Building Inspector for the village had noti[510] fled him that the pool construction permit had expired; that in view of the abandonment of the project by the plaintiff the excavation was a danger to children and damaging to the appearance of his property; asked them to remove the materials and restore the premises and that he would hold them in damages for their failure to do so. Thereafter, the defendant filled in the excavation. The defendant offered no proof of his counterclaim and it is dismissed.

It is obvious from the phrasing used by the parties, “ Final Financing to be determined ’ ’, that it was an agreement to make an agreement in the future. The terms of payment were an important consideration to the parties and the instrument executed by the parties which lacked a material element was not a contract. (Ansorge v. Kane, 244 N. Y. 395.)

Free access — add to your briefcase to read the full text and ask questions with AI

Seaboard Pools, Inc. v. Freeman, 46 Misc. 2d 508, 259 N.Y.S.2d 999, 1965 N.Y. Misc. LEXIS 1871 (N.Y. Super. Ct. 1965).

46 Misc. 2d 508 (Seaboard Pools, Inc. v. Freeman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ansorge v. Kane
155 N.E. 683 (New York Court of Appeals, 1927)
New York Elevator Supply and Repair Company v. . Bremer
67 N.E. 1083 (New York Court of Appeals, 1903)
New York Elevator Supply & Repair Co. v. Bremer
74 A.D. 400 (Appellate Division of the Supreme Court of New York, 1902)
Jenkin Contracting Co. v. Sixth Avenue & 57th Street Corp.
282 A.D. 662 (Appellate Division of the Supreme Court of New York, 1953)
William Saloy, Inc. v. Luhrs
284 A.D. 908 (Appellate Division of the Supreme Court of New York, 1954)