IN THE COURT OF APPEALS OF NORTH CAROLINA
No. COA24-191
Filed 5 February 2025
Mecklenburg County, No. 22 CVS 3540
SOUTHEASTERN PUBLIC SAFETY GROUP, INC. d/b/a SOUTHEASTERN COMPANY POLICE, Plaintiff,
v.
NORTH CAROLINA DEPARTMENT OF JUSTICE, CRIMINAL STANDARDS DIVISION, and RANDY MUNN, in his official capacity as the NORTH CAROLINA COMPANY POLICE ADMINISTRATOR, Defendants.
Appeal by defendants from decision and declaratory judgment entered 10
August 2023 by Judge Steven R. Warren in Mecklenburg County Superior Court.
Heard in the Court of Appeals 22 October 2024.
Everson Law Office, PLLC, by Cynthia E. Everson, for plaintiff-appellee.
Attorney General Jeff Jackson, by Solicitor General Fellows Mary Elizabeth Reed and Trey A. Ellis, Deputy Solicitor General James W. Doggett, and Assistant Attorney General Kristen Mallett, for defendants-appellants.
ZACHARY, Judge.
This case arises from the construction of express toll lanes on the I-77
interstate highway (“the I-77 HOT Lanes Project”). Sugar Creek Construction, LLC
(“SCC”) hired Plaintiff Southeastern Public Safety Group, Inc.—a company police
agency commissioned under the Company Police Act (“the Act”)—to provide policing
services in conjunction with SCC’s construction work on the I-77 HOT Lanes Project. SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
Opinion of the Court
During the course of construction, Defendant Randy Munn—the North Carolina
Company Police Administrator—received information that Plaintiff was utilizing
blue lights to block free-flowing traffic lanes on I-77. Thus arose the question of law
that this case presents: did the Act authorize Plaintiff’s activities?
Defendants considered Plaintiff to be in violation of the Act, and the
administrative law judge agreed. Plaintiff then filed a petition for judicial review with
the Mecklenburg County Superior Court; the superior court agreed with Plaintiff,
vacated the administrative law judge’s decision, and replaced it with the court’s own
order. Defendants now appeal from the decision and declaratory judgment of the
superior court. After careful review, we vacate and remand.
I. Background
The facts of this case are not in dispute. We therefore recite only those facts
necessary to resolve the question of law presented.
A. The Company Police Act
The Act “regulates private police agencies, giving them authority similar to
municipal or county police forces.” Pinnacle Special Police, Inc. v. Scottsdale Ins. Co.,
607 F. Supp. 2d 735, 740 (E.D.N.C. 2009); see also N.C. Gen. Stat. § 74E-1 et seq.
(2023). The Act provides company police officers with limited jurisdiction, as
determined by the real property owned by or in the possession and control of their
employer or a party who contracted with their employer:
Company police officers, while in the performance of their
-2- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
duties of employment, have the same powers as municipal and county police officers to make arrests for both felonies and misdemeanors and to charge for infractions on any of the following:
(1) Real property owned by or in the possession and control of their employer.
(2) Real property owned by or in the possession and control of a person who has contracted with the employer to provide on-site company police security personnel services for the property.
(3) Any other real property while in continuous and immediate pursuit of a person for an offense committed upon property described in subdivisions (1) or (2) of this subsection.
N.C. Gen. Stat. § 74E-6(c).
Pertinent to the case before us, company police officers are prohibited—with
limited exception—from utilizing blue lights to obstruct free-flowing traffic on a
public highway unless they are within the jurisdiction provided by § 74E-6(c). The
Office of the Attorney General has promulgated regulations that prohibit company
police officers from conducting the following activities:
(4) [A]ctivating or operating a blue light in or on any vehicle in this State except when operating a motor vehicle used primarily by company or railroad police in the performance of his official duties:
(a) when in property jurisdiction limitations specifically described under [N.C. Gen. Stat. §] 74E-6;
(b) when in continuous or immediate pursuit of a person for an offense committed upon real property owned by or in the possession or control
-3- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
of his employer or real property or in the possession and control of a person who has contracted with the employer to provide on-site police security personnel services for the property; or
(c) during the transportation of an arrestee, which the company police agency has taken into custody;
(5) activating or operating a siren when operating any motor vehicle used primarily by any company police agency in the performance of his official duties when outside of the property jurisdiction limitations specifically described under [N.C. Gen. Stat. §] 74E-6 unless in immediate and continuous pursuit;
....
(7) impeding traffic, stopping motorists or pedestrians, or in any manner imposing or attempting to impose his will upon another person as police authority unless:
(a) he is on the property specifically described under [N.C. Gen. Stat. §] 74E-6; or
(b) when in immediate and continuous pursuit of any person for an offense which occurred within the property jurisdiction limitations specifically described under [N.C. Gen. Stat. §] 74E-6 . . . .
12 N.C. Admin. Code 2I.0304(4)–(5), (7) (2024).
B. The I-77 HOT Lanes Project
The North Carolina Department of Transportation (“NCDOT”) contracted with
I-77 Mobility Partners (“Mobility”)—a consortium of corporate entities organized for
the purpose of the I-77 HOT Lanes Project public-private partnership—to finance,
design, build, operate, and maintain express toll lanes along a 26-mile stretch of I-77
-4- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
between Statesville and Charlotte. The I-77 HOT Lanes Project was governed by a
Comprehensive Agreement, in which NCDOT granted Mobility and its
subcontractors a limited concession to enter the I-77 HOT Lanes Project property, but
expressly provided Mobility “no fee title, leasehold estate, possessory interest, permit,
easement or other real property interest of any kind”:
2.1.2 From and after issuance of any NTP1,1 [Mobility] and its authorized Developer-Related Entities shall have the right to enter onto the Project Right of Way owned by, or subject to the control of, NCDOT and, with the reasonable consent of NCDOT, other lands owned by NCDOT necessary for the purposes of carrying out the NTP1 Work. From and after issuance of NTP2, [Mobility] and its authorized Developer-Related Entities shall have the right to enter onto the Project Right of Way owned by NCDOT and, with the reasonable consent of NCDOT, other lands owned by NCDOT for the purposes of carrying out its obligations under the [Comprehensive Agreement] Documents. Absent agreement by the Parties as to a later date, [Mobility]’s rights to enter and use the Project Right of Way shall automatically terminate at the end of the Term.
2.1.3 Subject to Section 2.1.2, [Mobility] has no fee title, leasehold estate, possessory interest, permit, easement or other real property interest of any kind in or to the Project or the Project Right of Way by virtue of this Agreement, any of the other [Comprehensive Agreement] Documents or otherwise.
2.1.4 Subject to Section 2.1.2, [Mobility]’s property interests under this Agreement are limited to contract rights constituting intangible personal property (and not real estate interests). [Mobility]’s property interests under
1 The Comprehensive Agreement defines “NTP1” and “NTP2” as written notices issued by
NCDOT to the developer authorizing the developer to proceed with its contracted work.
-5- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
this Agreement are solely those of an independent contracting party, and NCDOT and [Mobility] are not in a relationship of co-venturers, partners, lessor-lessee or principal-agent (except to the extent the [Comprehensive Agreement] Documents expressly appoint [Mobility] as NCDOT’s agent for specified purposes).
Mobility identified SCC as the Design-Build Contractor in the Comprehensive
Agreement. Consistent with applicable federal guidelines, NCDOT policy for the I-77
HOT Lanes Project required each contracted developer, such as SCC, to “[f]urnish
Law Enforcement Officers and marked Law Enforcement vehicles to direct traffic in
accordance with the contract.” Specifically, the policy required the use of “uniformed
Law Enforcement Officers and marked Law Enforcement vehicles equipped with blue
lights mounted on top of the vehicle, and Law Enforcement vehicle emblems to direct
or control traffic as required by the plans or by the Engineer.”
C. Plaintiff’s Policing Services for SCC
On 19 July 2016, SCC entered into a contract with Plaintiff to provide policing
services in accordance with the Act “[t]o any [NCDOT] property related to” the I-77
HOT Lanes Project in which SCC had “contracting or subcontracting authority.”
Plaintiff agreed to provide SCC “with policing/law enforcement services under” the
Act, including “traffic control/enforcement[.]” In the project statement between SCC
and Plaintiff, SCC identified the physical address of the I-77 HOT Lanes Project as:
“I-77 from I-277 to Exit 36, and I-277 from I-77 to Exit 3A/B[.]”
On 27 March 2017, Defendant Munn received an email from Adam Tranum,
-6- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
the operations manager for a private security agency in Charlotte, “about a violation
that [he] witnessed.” Tranum had noticed a pair of Plaintiff’s marked vehicles with
flashing blue-and-red lights on the sides of the travel lanes at various points of the I-
77 HOT Lanes Project construction area. Based on his experience in private security,
Tranum understood this to be a violation of the Act because “company police [are] not
allowed to . . . direct traffic on public roadways.”
Defendant Munn began investigating Tranum’s complaint and contacted both
Plaintiff and SCC. Plaintiff’s Chief of Police Keith Williams and SCC’s Safety
Manager Jim Quinn each informed Defendant Munn that Plaintiff was under
contract to provide policing services, including blocking the travel lanes in the I-77
HOT Lanes Project construction area. Defendant Munn informed both Plaintiff and
SCC that Plaintiff’s officers were limited to working inside of any barricaded work
zones of the construction area and that it would violate the Act for a company police
agency to utilize blue lights to block the travel lanes on a state-maintained highway.
Defendant Munn also warned that the potential punishment for such a violation
could include an immediate revocation of Plaintiff’s certification as a company police
agency under the Act. Chief Williams “agreed . . . to pull his folks off the job until
DOJ came down with a ruling.”
D. Procedural History
The foregoing facts have led to multiple lawsuits in state and federal courts.
On 18 December 2017, Chief Williams filed a claim for damages under the Tort
-7- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
Claims Act, but the Industrial Commission dismissed the matter for failure to state
a claim upon which relief could be granted. Williams v. N.C. Dep’t of Justice, Crim.
Standards Div., 273 N.C. App. 209, 210–11, 848 S.E.2d 231, 234 (2020). This Court
affirmed the dismissal. Id. at 218, 848 S.E.2d at 239. Also, Plaintiff filed suit against
Defendant Munn and others in federal court, which was likewise dismissed. Se. Pub.
Safety Grp. Inc. v. Munn, No. 3:20-CV-00203-FDW-DCK, 2021 WL 3561184, at *1
(W.D.N.C. Aug. 11, 2021), affirmed in part, vacated in part, and remanded, No. 22-
1114, 2024 WL 4625079 (4th Cir. Oct. 30, 2024) (unpublished).
Additionally, Chief Williams filed a foreign subpoena in Washington State
directing Microsoft to produce certain logs for four DOJ email accounts. Williams v.
Custodian of Pub. Records NC Dep’t of Justice, 28 Wash. App. 2d 1022, 2023 WL
6214542, at *1 (2023) (unpublished). When Microsoft “completed its search for
responsive records and found none[,]” Chief Williams filed a motion to compel and a
motion for reconsideration, which were both denied. Id. Chief Williams’s appeal was
similarly unsuccessful. Id.
Plaintiff initiated the case before us on 20 March 2020 by filing a petition for a
contested case hearing in the Office of Administrative Hearings. Plaintiff claimed
that Defendant Munn deprived Plaintiff of rights and property; exceeded the scope of
his authority; acted arbitrarily, capriciously, and erroneously; and failed to act as
required by law.
In August 2020, the matter came on for hearing before an administrative law
-8- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
judge. At the hearing, the administrative law judge made a series of rulings
preventing Plaintiff from engaging in certain lines of questioning, such as asking
Defendant Munn about the contract between NCDOT and SCC in order to determine
the boundaries of the property that Plaintiff claimed it was authorized to police. The
administrative law judge reasoned that Defendant Munn could not “testify about the
contract” because Plaintiff could not obtain by contract any authority that it could
not lawfully obtain under the Act, such as the authority to block the travel lanes of a
public highway:
Because you cannot -- because the issue is blocking the road. And if the law says you can’t block the road it doesn’t matter if a contract -- if you sign a contract -- let’s take this and do something imaginary. Let’s say there’s a law that says you cannot own a purple kangaroo. Okay? You can’t show me a contract that says, Well, I’m giving you a purple kangaroo because the law says no. So he can’t talk about the contract. He can just talk about what’s in the statute that’s his area of responsibility.
The administrative law judge also prevented Plaintiff from introducing into evidence
certain federal regulations that Plaintiff contended would support its argument
concerning the definition of the “work zone” that it had contracted to police for SCC.
On 19 November 2020, the administrative law judge entered a final decision,
determining that Plaintiff “admits and the evidence shows that [it] engaged in acts
that are listed as prohibited acts in [12 N.C. Admin. Code 2I.0304(4), (5), and (7)] and
that [Plaintiff] failed to show that its actions on the public highway of [I-77] complied
with N.C. Gen. Stat. § 74E-6(c).” Accordingly, the administrative law judge concluded
-9- SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
that Plaintiff had failed to meet its burden of proof for its claims.
On 13 January 2021, Plaintiff filed a petition for judicial review in
Mecklenburg County Superior Court. In part, Plaintiff alleged that it had discovered
new evidence through a public-records request: an email sent on 17 July 2017 from
Defendant Munn to his supervisor at DOJ, in which Defendant Munn detailed his
phone conversation with a DOJ attorney. In this email, Defendant Munn explained
that the DOJ attorney had suggested that NCDOT’s contract with Mobility might
allow a company police agency to perform policing services along the entire 26-mile
stretch of the I-77 HOT Lanes Project; nevertheless, Defendant Munn cautioned his
supervisor that DOJ attorneys had yet to fully complete their assessment. On 8 July
2021, the superior court entered an order vacating the final decision and remanding
the matter to the administrative law judge to allow Plaintiff to present additional
evidence related to this email.
This matter came on for hearing on remand before the administrative law
judge on 2 December 2021. The additional evidence included not only the 17 July
2017 email but also an email that Defendant Munn sent to his supervisor the next
day, in which Defendant Munn summarized a follow-up conversation with the DOJ
attorney. In the 18 July email, Defendant Munn stated that “after much thought and
conversation the conclusion is that [Plaintiff] would violate the Act if it work[ed] the
I-77 construction zone and its duty included blocking travel lanes or any other police
action on the [traveled] portion of the highway.” The administrative law judge also
- 10 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
admitted into evidence the portion of the Comprehensive Agreement containing
definitions and diagrams, as well as affidavits from SCC’s Safety Manager Quinn and
the DOJ attorney who consulted with Defendant Munn addressing the boundaries of
the construction zone for the I-77 HOT Lanes Project.
On 3 February 2022, the administrative law judge entered a new final decision
on remand. The administrative law judge found that the newly introduced emails
were “part of an on-going discussion between [the DOJ attorney] and Defendant
Munn about whether [Plaintiff] was in violation of” the Act, and that the additional
evidence did “not support the argument that [Plaintiff] was not in violation of” the
Act. Further, the administrative law judge determined that none of the additional
evidence “refute[d] the conclusions of law” made in the previous final decision, and
concluded that Plaintiff “still failed to meet its burden of proving that [Defendants]
took any action that has substantially prejudiced [Plaintiff]’s rights by exceeding its
authority or jurisdiction, acting erroneously, failing to use proper procedure, acting
arbitrarily or capriciously, or failing to act as required by law or rule.”
On 24 March 2022, Plaintiff filed a petition for judicial review of this final
decision, as well as a complaint for declaratory judgment. On 10 July 2023, the matter
came on for hearing in Mecklenburg County Superior Court. The superior court
entered a decision and declaratory judgment in Plaintiff’s favor on 10 August 2023.
The superior court first concluded that the administrative law judge erred by
limiting Plaintiff’s evidence and lines of questioning at the hearings, because the
- 11 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
contract between NCDOT and SCC was necessarily relevant to determining
Plaintiff’s jurisdiction:
10. All the jurisdictional limits, and regulatory prohibitions, of company police agencies and officers are established by the real property owned or possessed and controlled by their employers or entities with whom they have contracts for law enforcement services. N.C. Gen. [Stat. § 74E-6(c)(1)– (3)].
11. At no point in [the Act] or in 12 [N.C. Admin. Code 2I.0304] are company police officers prohibited from impeding traffic, operating sirens, or operating blue lights, as long as they are within their real property jurisdictions as defined by their respective contracts.
12. It was impossible for the Administrative Law Judge to ascertain whether Plaintiff was complying with the provisions of Chapter 74E without admitting the full contract between . . . NCDOT and SCC, to determine whether . . . NCDOT had possession and control over I-77 and whether . . . NCDOT relinquished that possession and control to SCC for purposes of completion of the construction project between Exits 36 and 3A/3B on I-77.
13. The Administrative Law Judge’s refusal to admit and consider the contract between . . . NCDOT and SCC, as well as her refusal to allow Plaintiff to question Defendant Munn about his review of the contract, was arbitrary and capricious, and was further based on unlawful procedure, since the contract itself sets forth the real property jurisdictional boundaries of Plaintiff and its law enforcement officers.
Because the administrative law judge considered the DOJ attorney’s opinion
“about the language of the contracts at issue, without admitting the actual primary
- 12 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
contract itself,” the superior court concluded that the administrative law judge’s
decision “violated Plaintiff’s rights to Due Process and Equal Protection, was
arbitrary and capricious, was an abuse of discretion, violated the best evidence rule
of civil procedure, and was further based on unlawful procedure.”
The superior court further concluded that the federal regulations proffered by
Plaintiff were relevant and material to this case, and thus the administrative law
judge’s “refusal to consider federal law violated Plaintiff’s rights to Due Process and
Equal Protection, was arbitrary and capricious, and was further based on unlawful
procedure.” The superior court then concluded that Defendant Munn improperly
interfered with Plaintiff’s contract, due to his failure to consider the contract and the
federal regulations:
The uncontroverted evidence in the record is that Defendant Munn told Plaintiff that it could not block travel lanes in the project area on I-77 because, without consideration of the [federal regulations], he believed the parameters of the work zone were limited to the barricaded areas, despite his review of the contract language indicating otherwise. Since blocking travel lanes was required by Plaintiff’s contract with SCC, Plaintiff was unable to continue working and, thus, lost property in that it ceased earning revenue on this and other NCDOT projects because of Defendant Munn’s interpretation of Chapter 74E.
The superior court consequently determined that Plaintiff was an “aggrieved
party” for purposes of the North Carolina Administrative Procedure Act (“APA”), and
that the administrative law judge’s conclusion otherwise was “unsupported by
- 13 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
substantial evidence, [wa]s arbitrary and capricious, and was an abuse of discretion.”
Additionally, the superior court determined that “[n]othing in Chapter 74E gives
Defendant Munn the authority to interpret or invalidate a contract. As such, he acted
outside the scope of his authority in interpreting the contracts at issue in this case
and telling Plaintiff that its contract with SCC was invalid.”
As to whether Plaintiff violated the Act, the superior court concluded that the
Act (1) “does not prohibit company police agencies and officers from providing
contract law enforcement services on streets, roads, or highways, as long as those
streets, roads, or highways are within the ownership or possession and control of the
entities with whom they have contracts for law enforcement services”; and (2) “does
not prohibit company police agencies and officers from providing contract law
enforcement services on federally-funded NCDOT work zones, including the free-
flowing travel lanes, as long as those lanes are within the actual work zone as defined
by the” Code of Federal Regulations (“CFR”). Finally, the superior court concluded
that the pertinent federal regulations apply in this case:
In interpreting Chapter 74E, Defendant Munn must defer to the definitions included in the [CFR] for federally- funded highway construction projects. As long as the company police agencies and its officers are working within the work zone as defined in the CFR, they are within their jurisdiction, and Defendant Munn cannot take any investigative or other action against them for this work.
Consequently, the superior court vacated the administrative law judge’s final
opinion in its entirety, and entered a new order “replac[ing]” the administrative law
- 14 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
judge’s decision. Defendants timely filed notice of appeal.
II. Discussion
On appeal, Defendants argue that the superior court erred by concluding that
Plaintiff did not violate the Act. Specifically, Defendants contend that Plaintiff’s
“officers acted outside of their jurisdictional bounds,” and that “[c]ontrary to the
superior court’s understanding, no federal law gave [Plaintiff] or its contractor [SCC]
the possession and control of the highway needed for [Plaintiff] to have jurisdiction.”
For the reasons that follow, we agree with Defendants that the superior court’s
findings of fact do not support its conclusions of law regarding Plaintiff’s alleged
violations of the Act. Consequently, we vacate the superior court’s decision and
declaratory judgment.
Further, although Plaintiff raised additional procedural and evidentiary issues
before the superior court, on appeal, Defendants only challenge the superior court’s
ultimate conclusions of law concerning whether Plaintiff violated the Act. Therefore,
we remand to the superior court with instructions that the case be remanded to the
administrative law judge for consideration of (1) the contract between NCDOT and
SCC, and (2) the federal regulations, to the extent that they apply.
A. Standard of Review
A party aggrieved by the final decision of an administrative law judge in a
contested case has a right to judicial review by the superior court. N.C. Gen. Stat.
§ 150B-43. On review of a final decision of an administrative law judge, the superior
- 15 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
court has a limited scope of review under the APA. Id.
The APA sets the boundaries of the superior court’s review of a final decision:
The court reviewing a final decision may affirm the decision or remand the case for further proceedings. It may also reverse or modify the decision if the substantial rights of the petitioners may have been prejudiced because the findings, inferences, conclusions, or decisions are:
(1) In violation of constitutional provisions;
(2) In excess of the statutory authority or jurisdiction of the agency or administrative law judge;
(3) Made upon unlawful procedure;
(4) Affected by other error of law;
(5) Unsupported by substantial evidence admissible under [N.C. Gen. Stat. §§] 150B-29(a), 150B-30, or 150B-31 in view of the entire record as submitted; or
(6) Arbitrary, capricious, or an abuse of discretion.
Id. § 150B-51(b).
The APA provides a reviewing court with two different standards of review,
depending on the nature of the challenge being addressed:
With regard to asserted errors pursuant to subdivisions (1) through (4) of subsection (b) of this section, the court shall conduct its review of the final decision using the de novo standard of review. With regard to asserted errors pursuant to subdivisions (5) and (6) of subsection (b) of this section, the court shall conduct its review of the final decision using the whole record standard of review.
Id. § 150B-51(c).
When applying de novo review to alleged errors of law, a reviewing court
- 16 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
“considers the matter anew and freely substitutes its own judgment for that of the”
administrative law judge. Blackburn v. N.C. Dep’t of Pub. Safety, 246 N.C. App. 196,
207, 784 S.E.2d 509, 518 (citation omitted), disc. review denied, 368 N.C. 919, 786
S.E.2d 915 (2016). “Under the whole record test, the reviewing court must examine
all competent evidence to determine if there is substantial evidence to support the
administrative [law judge]’s findings and conclusions.” Id. at 207, 784 S.E.2d at 517–
18 (citation omitted).
“A party to a review proceeding in a superior court may appeal to the appellate
division from the final judgment of the superior court as provided in [N.C. Gen. Stat.
§] 7A-27.” N.C. Gen. Stat. § 150B-52. “The scope of review to be applied by the
appellate court under this section is the same as it is for other civil cases. In cases
reviewed under [N.C. Gen. Stat. §] 150B-51(c), the [superior] court’s findings of fact
shall be upheld if supported by substantial evidence.” Id.
“[O]ur appellate courts have recognized that the proper appellate standard for
reviewing a superior court order examining a final agency decision is to examine the
order for errors of law.” Harnett Cty. Bd. of Educ. v. Ret. Sys. Div., Dep’t of State
Treasurer, 291 N.C. App. 14, 20, 894 S.E.2d 275, 280 (2023) (cleaned up), disc. review
denied, 386 N.C. 348, 901 S.E.2d 790 (2024). “[T]his twofold task involves: (1)
determining whether the [superior] court exercised the appropriate scope of review
and, if appropriate, (2) deciding whether the court did so properly.” Id. (cleaned up).
B. Analysis
- 17 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
As an initial matter, we note that the superior court appears to have applied
the correct standard of review—de novo—to the question of whether Plaintiff violated
the Act by utilizing blue lights to block free-flowing traffic on a public highway, an
alleged error of law. See N.C. Gen. Stat. § 150B-51(c). However, because the superior
court did not correctly interpret the Act and its application to the facts of this case,
we cannot say that the superior court properly applied the de novo standard of review.
See Harnett Cty. Bd. of Educ., 291 N.C. App. at 20, 894 S.E.2d at 280.
Fundamentally, this case concerns the jurisdictional provisions of the Act.
There is no dispute that if Plaintiff exceeded its jurisdictional limits, as specifically
set forth in the Act, then it would have been engaged in policing activities prohibited
by 12 N.C. Admin. Code 2I.0304. Thus, the crux of the matter is whether Plaintiff
acted within the real-property jurisdiction limitations of the Act.
In that Plaintiff has never claimed that it owned or had possession and control
of the relevant portion of I-77, this case necessarily hinges upon whether the party
with whom Plaintiff contracted—namely, SCC—owned or had possession and control
of that property. See N.C. Gen. Stat. § 74E-6(c)(1)–(2). Significantly, however, the
superior court never expressly found or concluded that SCC had such ownership,
possession, or control, although the court made a series of findings and conclusions
regarding other important procedural and legal issues in this matter.
Rather than focusing on the dispositive issue of whether Plaintiff or SCC
owned, possessed, or controlled the free-flowing traffic lanes of the pertinent portion
- 18 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
of I-77, as required by N.C. Gen. Stat. § 74E-6(c)(1)–(2) in order to determine whether
Plaintiff’s actions violated 12 N.C. Admin. Code 2I.0304, the superior court instead
focused primarily on two decisions below: the administrative law judge’s failure (1) to
allow Plaintiff to question Defendant Munn about the contract between NCDOT and
SCC, and (2) to consider the various federal regulations proffered by Plaintiff in
support of its jurisdictional argument. However, the superior court’s analysis of these
procedural issues—which Defendants do not challenge on appeal and therefore is not
before us—is insufficient on its own to resolve the dispositive question of law and
indicates that the superior court may have misinterpreted the jurisdictional
requirements of the Act.
1. Federal Regulations
By the express terms of the Comprehensive Agreement that governs the I-77
HOT Lanes Project, NCDOT granted Mobility a concession. See Concession, Black’s
Law Dictionary (12th ed. 2024) (defining a “concession” as a “government grant for
specific privileges”). Pursuant to this concession, Mobility and its subcontractors
obtained a right of entry to designated areas of the I-77 HOT Lanes Project work
zone. Nevertheless, the Comprehensive Agreement plainly states that the I-77 HOT
Lanes Project property—including both the existing I-77 right-of-way and the
additional property purchased for the project—is “owned by, or subject to the control
of, NCDOT” and that Mobility received “no fee title, leasehold estate, possessory
interest, permit, easement or other real property interest of any kind in or to” the
- 19 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
highway property. This language strongly suggests that neither Mobility nor SCC, as
Mobility’s design-build contractor, obtained the rights of ownership, possession, or
control over the I-77 HOT Lanes Project that the Act requires in order to sanction
Plaintiff’s policing activity in this case.
However, the superior court accurately recognized that the Act “does not define
real property[.]” Consequently, the superior court turned to the host of federal
regulations proffered by Plaintiff to assist in its analysis and determined that they
were relevant to this issue. The superior court then summarized these regulations in
its conclusions of law:
16. For federally-funded highway constructions projects, the real property interest acquired by the contractor from the State department of transportation or other entity “must be adequate to fulfill the purpose of the [project].” 23 C.F.R. § 710.305(b).
17. For federally-funded highway constructions projects, a Right of Way Agreement must exist between the grantee of the federal funds, usually a State department of transportation, and any contractors or subcontractors. 23 C.F.R. § 710.405. These agreements must provide safety measures. One of those measures is a traffic management plan. 23 C.F.R. § 630.1012(b).
18. The cost of providing and paying uniformed law enforcement officers is generally to be borne by the contractor on the highway construction project. 23 C.F.R. § 630.1108(d)(2).
These conclusions concerning the applicability of the federal regulations to the
case at bar formed the basis of the superior court’s conclusion that the “refusal to
- 20 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
consider federal law violated Plaintiff’s rights to Due Process and Equal Protection,
was arbitrary and capricious, and was further based on unlawful procedure.” But the
superior court neglected to extend its analysis to reach the dispositive issue of
whether (or how) federal law vested SCC with the necessary ownership, possession,
or control of the highway property in question.
Indeed, it is not readily apparent how germane these conclusions of law
regarding the federal regulations are to the legal question of whether Plaintiff
exceeded its lawful jurisdiction under the Act. As Defendants observe in their
appellate brief, “none of these cited regulations gave away NCDOT’s possessory
interests in the land or required NCDOT to do so.”
For instance, Defendants note that the requirement that the contractor obtain
an adequate property interest from NCDOT was satisfied by the concession granted
to Mobility and its subcontractors, thereby entitling them to a right of entry to
perform their contractual duties. But that concession was merely a right of entry, and
by its own terms would not include any possessory interest that Mobility could have
granted to SCC in turn. More to the point, the superior court never concluded that
the application of this federal regulation to the facts of this case vested SCC with the
ownership, possession, or control over the free-flowing traffic lanes of I-77 at issue
necessary to authorize Plaintiff’s actions under the Act.
Similarly, the fact that the federal regulations required NCDOT to have a
Right of Way Agreement setting forth a traffic management plan does not, in and of
- 21 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
itself, provide blanket authorization for a company police agency to provide that
traffic management, if providing such a service would violate the Act. As Defendants
explain: “Because these regulations do not demand the use of private law enforcement
agencies, the court erred in holding that they somehow required that [Plaintiff] be
allowed to manage traffic.” The superior court did not square the federal requirement
for a traffic management plan with the Act’s jurisdictional limitations when it
evidently—but implicitly—concluded that Plaintiff had not exceeded its jurisdiction
under § 74E-6(c).
The superior court’s findings of fact do not explain whether or how the federal
regulations proffered by Plaintiff could vest either SCC or Plaintiff with the
ownership, possession, or control over the pertinent area of I-77 and therefore provide
Plaintiff with the jurisdiction necessary to satisfy § 74E-6(c). Nor could the
regulations provide an alternative basis for Plaintiff to satisfy the jurisdictional
requirements of the Act, as explained above. Accordingly, the superior court’s findings
of fact regarding the cited federal regulations do not support the implicit conclusion
that Plaintiff did not violate the Act.
2. Contracts
Just as the superior court’s analysis of the federal regulations failed to resolve
the dispositive question of law, so too did the superior court’s contractual analysis.
The superior court reasoned that Defendant Munn’s admonition to Plaintiff that its
officers “could not block the free-flowing travel lanes on I-77 but were restricted to
- 22 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
working in the barricaded-off areas” was apparently “inconsistent with Plaintiff’s
contractual obligations to SCC and essentially gutted the contract” between Plaintiff
and SCC, because “under SCC’s contract with . . . NCDOT and the governing federal
regulations, SCC was required to provide traffic control on the free-flowing travel
lanes of I-77 in the project area.”
The same gap in the superior court’s logic discussed above applies here: SCC’s
contractual obligation to provide traffic control does not furnish blanket
authorization for any agency with whom SCC contracted to provide that traffic
control. If a company police agency was engaged to provide such services, it would
still have to comply with the limited jurisdictional authority granted by the Act.
Accordingly, it does not necessarily follow that the contract did (or could) authorize
Plaintiff’s actions in this case.
It is well settled that a contract cannot authorize a party to violate the law.
See, e.g., Duke Power Co. v. Blue Ridge Elec. Membership Corp., 253 N.C. 596, 602,
117 S.E.2d 812, 816 (1961) (“When called upon to interpret a contract, courts seek to
ascertain and give effect to the intent of the parties if that intent does not require the
performance of an act prohibited by law.”). Because Plaintiff’s actions would have
violated 12 N.C. Admin. Code 2I.0304(4)–(5) and (7) if the jurisdictional provisions of
N.C. Gen. Stat. § 74E-6(c) were not satisfied, the only relevance of any contract in
this matter would be to aid the tribunal in determining whether SCC obtained the
requisite ownership, possession, or control over the 26-mile stretch of I-77 at issue.
- 23 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
But the superior court made no such determination; rather, it only concluded that the
“refusal to admit and consider the contract between . . . NCDOT and SCC, as well as
[the] refusal to allow Plaintiff to question Defendant Munn about his review of the
contract, was arbitrary and capricious” and “based on unlawful procedure, since the
contract itself sets forth the real property jurisdictional boundaries of Plaintiff and
its law enforcement officers.” This conclusion—and particularly, any blanket
assertion that a contract alone might define a company police agency’s jurisdictional
limitations without determining whether the agency or its employer had sufficient
ownership, possession, or control of the property that the agency was hired to police—
does not resolve this case’s dispositive question of law: namely, Plaintiff’s jurisdiction
Ultimately, neither the federal regulations nor any contract can overcome the
jurisdictional requirements set out by the plain text of the Act. Consequently, the
superior court erred as a matter of law when it concluded:
The uncontroverted evidence in the record is that Defendant Munn told Plaintiff that it could not block travel lanes in the project area on I-77 because, without consideration of the [federal regulations], he believed the parameters of the work zone were limited to the barricaded areas, despite his review of the contract language indicating otherwise. Since blocking travel lanes was required by Plaintiff’s contract with SCC, Plaintiff was unable to continue working and, thus, lost property in that it ceased earning revenue on this and other NCDOT projects because of Defendant Munn’s interpretation of Chapter 74E.
- 24 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
This conclusion—along with others like it in the superior court’s decision and
declaratory judgment—demonstrates a flawed reading of the Act and the effects, if
any, that regulations and contracts have on the jurisdictional requirements of N.C.
Gen. Stat. § 74E-6(c). The polestar of the jurisdictional analysis for the question
presented by this case is whether SCC had the requisite ownership, possession, or
control of the I-77 HOT Lanes Project work zone sufficient for SCC to permit Plaintiff
to provide the policing services in question consistent with the Act. Because the
superior court did not answer this question and, as a result, demonstrated a
misunderstanding of the law at issue in this case, we cannot say that the court
properly applied the de novo standard of review. See Harnett Cty. Bd. of Educ., 291
N.C. App. at 20, 894 S.E.2d at 280.
III. Conclusion
In sum: although the superior court applied the proper de novo standard of
review upon review of the administrative law judge’s decision, we cannot say that the
superior court applied that standard of review correctly. See id. The superior court’s
findings of fact and conclusions of law are insufficient to support its determination
that Plaintiff was an “aggrieved party” under the APA. N.C. Gen. Stat. § 150B-43.
And because the superior court erred as a matter of law in interpreting the Act, the
superior court’s decision and declaratory judgment must be vacated and remanded.
In light of the superior court’s unchallenged determinations regarding the
administrative law judge’s evidentiary and procedural rulings, however, the proper
- 25 - SE. PUB. SAFETY GRP., INC. V. N.C. DEP’T OF JUSTICE
disposition is for the superior court to further remand this matter to the
administrative law judge for reconsideration. On remand, the administrative law
judge shall consider the contract between NCDOT and SCC, as well as the applicable
federal regulations, in determining the scope of Plaintiff’s jurisdiction pursuant to
We therefore vacate the superior court’s decision and declaratory judgment,
which itself vacated the final decision of the administrative law judge, and remand
to the superior court with instructions that the matter be remanded to the
administrative law judge for further proceedings consistent with this opinion.
VACATED AND REMANDED.
Judges ARROWOOD and GORE concur.
- 26 -