SE Enterprise Group, Inc. v. Skanska USA Building

209 F. App'x 880
CourtCourt of Appeals for the Eleventh Circuit
DecidedDecember 1, 2006
Docket05-15477
StatusUnpublished
Cited by1 cases

This text of 209 F. App'x 880 (SE Enterprise Group, Inc. v. Skanska USA Building) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SE Enterprise Group, Inc. v. Skanska USA Building, 209 F. App'x 880 (11th Cir. 2006).

Opinion

PER CURIAM:

The General Services Administration hired Skanska USA Building, Inc. as the general contractor for the construction of a new federal courthouse in Jacksonville, Florida. Skanska in turn contracted with Southeastern Enterprise Group, Inc. to build the roof of the courthouse. The subcontracting agreement required Southeastern to furnish and install a “complete roofing system” that had, among other things, a “watertight fit.”

Months into the roof construction, Skanska noticed that water was leaking into the fourteenth floor and asked Southeastern to fix the leak. After several attempts to fix the problem, Southeastern discovered, and relayed its discovery to Skanska, that it was the installation of the concrete on the parapet walls, and not the roof Southeastern had built, that was causing the leak. As to any other lingering issues about the roof, Southeastern told Skanska that it stood ready and willing to finish the job and awaited a final inspection of its work up to that date so that it could complete the project.

Skanska refused to schedule a final inspection and again insisted that Southeastern fix the leak. Because the leak was caused by a problem unassociated with the roof, however, it was outside the scope of Southeastern’s contract and expertise. Skanska thereafter terminated the subcontract.

In response, Southeastern sued Skanska for breach of contract and, pursuant to 40 U.S.C. § 3133(b), sought to collect its por *882 tion of the payment bond that Skanska had put up as the general contractor of the courthouse project. After a six day trial the jury found that Skanska had prevented Southeastern from fulfilling its contractual obligations and therefore breached the agreement. The jury awarded Southeastern $25,000.00 as damages for Skanska’s breach. The district court denied Skanska’s post-trial motions for judgment as a matter of law and a new trial, and it entered judgment in accord with the jury’s verdict.

The subcontract also required Skanska to pay all attorneys’ fees incurred in the prosecution of a breach of contract claim. 1 On Southeastern’s motion, the district court awarded it $229,697.50 in attorneys’ fees.

Skanska appeals the underlying judgment, focusing on the district court’s decision to deny its motions for judgment as a matter of law and a new trial, and also appeals the district court’s order awarding attorneys’ fees to Southeastern.

I.

Skanska contends that the district court should have granted its motion for judgment as a matter of law because, it argues: (1) Southeastern failed to present any evidence that Skanska wrongfully prevented Southeastern from substantially completing the roof; (2) Southeastern breached the subcontract by not providing a work schedule; (3) Southeastern breached the subcontract by not completing its work on time; and (4) Southeastern failed to establish its damages to a reasonable certainty. Skanska, however, is wrong on each of those arguments.

First, viewing the testimony and other evidence in favor of the nonmoving party, as we must, see Collado v. United Parcel Serv., Co., 419 F.3d 1143, 1149 (11th Cir.2005), there was sufficient evidence to support the jury’s finding that Skanska wrongfully prevented Southeastern from completing the roof. There was evidence that Southeastern told Skanska numerous times before termination of the subcontract that it was ready to fix any and all problems with the roof; that Skanska refused to give Southeastern specific directions or explanations so that it could fix the problem areas; and that Skanska further impeded the completion of the roof by causing damages to portions of it that had already been built by Southeastern.

In support of its position that Southeastern was not wrongfully prevented from completing the roof, Skanska points to Southeastern’s unwillingness to fix the leak. Southeastern, however, presented evidence that the leak came from the installation of the parapet walls and that there was nothing wrong with the roof itself that caused the leak. The jury, presented with that evidence, apparently accepted Southeastern’s version of the facts, and we cannot second guess the jury’s resolution of any conflict in evidence.

Second, the fact that Southeastern did not provide Skanska with a work schedule does not require judgment in *883 Skanska’s favor. As it was narrowed by the parties during the course of the litigation, the case was tried to the jury on one issue: whether “Skanska wrongfully interfere[d] with, or prevented] [Southeastern] from completing its obligations, under the contract.” That Southeastern did not provide a work schedule does not mean that it failed to complete its obligations under the contract or that any failure to complete them was not caused by Skanska.

Third, the fact that Southeastern did not complete the roof on time does not entitle Skanska to judgment as a matter of law. The district court found that Southeastern did not substantially complete the roof as required by the contract, and Southeastern does not dispute that finding here. The question is whether Skanska wrongfully prevented Southeastern from completing the roof on time. The jury found that it did, and there was evidence in the record to support that finding.

As to Skanska’s final point, there was sufficient evidence establishing to a reasonable certainty the jury’s $25,000 damage award. Skanska’s own witness, the project architect, testified that Southeastern “deserved the $25,000” for adjustments that Skanska required it to make to the roof design, which had increased Southeastern’s costs.

II.

Skanska next contends that the district court erred in denying its motion for a new trial because the testimony of John Reaves, Southeastern’s president, regarding Southeastern’s damages was not based on his personal knowledge and therefore was not competent to support the jury verdict. Skanska, however, did not object to the admission of Reaves’ damages testimony at trial, which precludes our review of the evidentiary error on appeal. Fed. R.Evid. 103(a)(1) (“Error may not be predicated upon a ruling which admits ... evidence unless a substantial right of the party is affected, and ... a timely objection or motion to strike appears of record. ...”); Christopher v. Cutter Labs., 53 F.3d 1184, 1192 (11th Cir.1995) (a party must object to a witness’s inadmissible testimony in order to preserve the issue of its improper admission on appeal). Not only that, but any error by the district court in admitting Reaves’ damages testimony was harmless. The jury’s $25,000 damages verdict shows that it disregarded Reaves’ account of Southeastern’s damages, which he estimated at a much higher amount, and instead credited the testimony of Skanska’s own witness — the project architect — that Southeastern was only entitled to $25,000 for the change in design of the roof. See Fed.R.Evid. 103(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
209 F. App'x 880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/se-enterprise-group-inc-v-skanska-usa-building-ca11-2006.