775 A.2d at 366. Although Persson is not completely analogous to the situation in
this case, it is similar in that the court, in each case, contributed to the confusion
leading to the violation.
Here, the court itself sowed the seeds of confusion when it ordered SMPI's
"Petition to be Accepted for filing" on May 20,2009. See supra n. 2. When the
court clerk presented SMPI's May 19th filing to the court, the issue presented was
the timeliness of filing. Had the court recognized that Scott Hatch was not an
attorney, the filing would have been rejected which would have provided SMPI
and the final agency action or agency inaction which they wish reviewed. It shall also contain a concise statement as to the nature of the action or inaction to be reviewed, the grounds upon which relief is sought and a demand for relief, which may be in the alternative." with an opportunity to obtain legal representation. See e.g., Kawka v. Coyne, 2000
Me. Super. LEXIS 107, * 1. At the time the court made that order, SMPI still had
seven days to obtain representation. Because the court accepted the May 19th
filing, SMPI was never put on notice of the need for legal counsel.
The Respondents' reliance on Land Management can be distinguished in
this case. The plaintiff's claim in Land Management was dismissed by the
Superior Court without prejudice. 6 Land Management Inc. v. Dept. of
Environmental Protection, No. CV-76-183 (May 19, 1976) (order dismissing action).
In other words, the plaintiff in Land Management would have had the opportunity
to obtain counsel and refile his claim. Here, dismissing the action would put an
end to SMPI's appeal because the statutory appeal period has run. Such a result
would be unjust given the circumstances.
DECISION
Therefore, the entry is:
Respondents' Motion to Dismiss is DENIED
<::/4 Dated at Portland, Maine this _--,t2-.""-- , day of --......=......\~"-:l6'-,=£.~-~f..~t-,-,,-I/ ... 2009.
/; -- ;:~(~~?(/ Rq ert E. Crowley --- Justice, Superior Court
6 "Unless otherwise specified in the order, a dismissal under [Rule 41] is without prejudice." M.R. Civ. P. 41 (a)(2). Date Filed 05-19-09 CUMBERLAND Docket No. _ _A_P_-_0_9~-~16 __. County
Action - -80C - Appeal
SCRIBNER'S MILL PRESERVATION MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION C/O SCOTT D. HATCH MAINE BOARD OF ENVIRONMENTAL PROTECTION 232 SCRIBNER MILL RD. HARRISON, ME 04040 vs. Plaintiff's Attorney Defendant's Attorney
PRe-&E JANET MCLINTOCK AAG SCOTT D. ANDERSON ESQ DEPARTMENT OF THE ATTORNEY GENERAL VERRILL & DANA 6 STATE HOUSE STATION PO BOX 586 AUGUSTA ME 04330 PORTLAND ME 04112-0586
Date of STATE OF MAINE SUPERIOR COURT CUMBERLAND, ss CIVIL ACTION DOCKET NO. AP-09-016i !?,E/C-Cu(y) - 3/· f J . SCRIBNER'S NlILL PRESERVATION, INC. Petitioner ORDER ON PETITIONER'S v. SOC APPEAL
MAINE DEPARTMENT OF ENVIRONMENT AL PROTECTION, ET AL., Respondents
BEFORE THE COURT
Pursuant to Rule SOC of the Maine Rules of Civil Procedure, Petitioner
Scribner's Mill Preservation, Inc. (SMPI) appeals the Maine Board of
Environmental Protection's (the "Board" or "BEP") April 16, 2009 decision,
denying SMPI's application to construct and operate a hydro-mechanical dam on
the Crooked Ri ver for the Scribner's Mill Project. The BEP denied SMPI a Maine
Waterway Development and Conservation Act ("MWDCA") permit pursuant to
3S M.R.S. § 636, and a water quality certification pursuant to Section 401 of the
Clean Water Act ("CWA"), 33 USc. § 1341 and 3S M.R.S. § 464. The court
accepted an Amicus Curine Brief in support of the Respondent on February 11,
2010. 1
BACKGROUND AND PROCEDURAL HISTORY
I. The Scribner's Mill Project
I The Amicus Curiae Brief was filed on behalf of the following interested parties: Natural Resources Council of Maine, Maine Rivers, Sebago Lake Anglers Association, Friends of the Presumpscot, Lakes Environmental Association, Maine Congress of Lakes Associations, Maine Council of Trout Unlimited, Western Foothills Land Trust, Donald Gossett Jr., Greg Murrer, and Jonathan Peterson. Through the Scribner's Mill Project, SMPI aims to restore and operate a
water-powered sawmill using original 19th century equipment as part of an
education center and museum. Under its current plan, SMPI's project requires
constructing and operating the Scribner's Mill Dam on the Crooked River in the
Towns of Harrison and Otisfield. The dam is located about 21 miles upstream
from Sebago Lake. The Scribner's Mill originally operated from 1851 to 1962,
and was used to cut timber and lumber, and to manufacture other wood
products such as shingles, barrels, and wooden handles. A dam existed at
Scribner's Mill until 1972, when it was breached to improve passage for
landlocked salmon. 2 If SMPI's project were completed, Scribner's Mill would
operate as one of the last remaining historic sawmills in the United States.
II. Procedural History
On November 15, 2002, SMPI submitted its initial application for a
MWDCA permit and a Water Quality Certification. In accordance with the
established procedure for review of hydropower projects pursuant to 38 M.R.S. §
634(3), the Department of Environmental Protection circulated SMPI's
application to State agencies and interested non-governmental organizations,
including the Department of Inland Fisheries and Wildlife ("IF&W"). In
response to agency and public comments on the initial application, SMPI
submitted a revised application for the project on August 27,2007. The
Commissioner treated this application as a replacement for the initial
application. As revised, the application called for:
2 These background facts are from the findings of the Commissioner of the Department of Environmental Protection's December 31, 2008 Department Order.
2 [T]he reconstruction of the breached Scribner's Mill Dam with an integrated rock ramp fishway, completion of the on-going reconstruction of the historic mill building, and the construction, installation and operation of water intake structures, penstocks and water wheels to power the sawmill equipment. The reconstructed dam would create an impoundment with a surface area of 10.8 acres at a [sic] full pond elevation .... The impoundment would extend upstream about 1.1 miles.:> The affected area of the Crooked River is classified as Class A. 4
SMPI also further revised the project by reducing the slope of the proposed
fishway to a 2.6% slope, compared to a 5% slope included in the original
proposal. On October 24, 2008, the Commissioner issued a draft order denying
SMPI's application. The Commissioner received comments on the draft order
from SMPI, the IF&W, and the Natural Resources Council of Maine. The
3 In their Reply Brief, Petitioners allege that the BEP relied on misleading information from the IF&W to describe the impact of the proposed dam. SMPI Reply Brief, pp. 6-7. The BEP's reference to 10.8 acres and the distance upstream that would be affected by the impoundment appear to be misstated. According to the report prepared by SMPI's consultant, 1.1 miles upstream is the theoretical upper limit of the area affected by the impoundment and water elevation will only increase by approximately three inches. R. Tab 314, p. 238k.k., Woodlot Report. Additionally, the wetted surface area of the area upstream from Scribner's Mill is currently 8.9 acres during normal flow conditions, and with the dam the wetted area will increase by 1.9 acres to a total of 10.8 acres. Id. However, this misstated information was only in the BEP's description of the project under "Procedural History," and neither of these figures appears to have directly factored into the BEP's consideration of the permitting criteria pursuant to 38 M.R.S. § 636.
4 As pointed out by the amicus parties, a recent amendment to Maine's water quality laws establishes "the Crooked River and its tributaries, except as otherwise provided, excluding existing impoundments" as a Class AA waterway. 38 M.R.S. § 467(9)(B)(2) (2009). Prior to this amendment, and the standard in effect when SMPI tiled its application, the entirety of the Crooked River and its tributaries were classified as Class AA, with the exception of existing impoundments on the river and the area of the river previously impounded at Scribner's Mill, which were classified as Class A. 38 M.R.S. § 467(9)(B)(2) (2008). Class AA waters are the highest water quality classification, which is "applied to waters which are outstanding natural resources and which should be preserved because of their ecological, social, scenic or recreational purposes." 38 M. R. S. § 465( I). Class AA waters must be free-flowing and natural. Id.
3 Commissioner issued its final order on December 31, 2008, denying SMPI's
application. SMPI filed a timely appeal to the BEP on February 4,2009.'
On April 16, 2009, the BEP issued its decision, which incorporated and
upheld the Commissioner's decision. Specifically, the BEP found that SMPI has
not met its burden of affirmatively demonstrating 6 that its proposed project
meets the public benefit, environmental mitigation, environmental and energy
considerations, and water quality criteria necessary for approval under the
Maine Waterway Development and Conservation Act, 38 M.R.S. §§ 636 (3), (6),
(7), and (8). The failure to meet the applicable water quality standards led to the
denial of a water quality certification under Section 401 of the Clean Water Act.
33. USc. § 1341.
III. The Legal Framework
a. The Maine Waterways Development and Conservation Act
The Maine Waterways Development and Conservation Act was passed to
create a single application and permitting process for hydropower development.
5 The Department of Environmental Protection consists of the Commissioner and the BEP. 38 M.R.S. § 341-A(2). The Commissioner makes most licensing decisions, which may be appealed to the BEP for review. 38 M.R.S. §§ 341-A(4) and 341-8. An aggrieved party has 30 days after receipt of notice of final agency action to file a petition for judicial review. 38 M.R.S. § 346(1),5 M.R.S. § 11002. For this reason, SMPI's appeal is only from the BEP's April 16, 2009 decision.
6 The DEP's Rules Concerning the Processing ofApplications and Other Administrative Mailers, 06-096 CMR 2 § 11 (F), provide guidance on an applicant's burden of proof. Under the rules, "[a]n applicant for a license has the burden or proof to affirmatively demonstrate to the Department that each of the Iicensing criteria in statute or rule has been met. ... For those matters relating to a licensing criteria [sic] that are disputed by evidence the Department determines is credible, the applicant has the burden of proving by a preponderance of the evidence that the licensing criteria are satisfied."
4 38 M.R.S. § 632(2)? The policy and purpose of the MWDCA states: "[I]t is the
policy of the State to support and encourage the development of hydropower
projects by simplifying and clarifying requirements for permits, while assuring
reasonable protection of natural resources and the public interest in the use of
waters of the State." [d. The MWDCA requires any person initiating
construction or reconstruction of a hydropower project to secure a permit from
the Department of Environmental Protection. 38 M.R.S. § 633. In order for a
permit to be approved, the MWDCA requires the applicant to demonstrate, and
the DEP to approve, that the proposed hydro project meets eight criteria. 38
M.R.S. § 636, Save 0111' Sebnstieaak, flle. v. Bd. aJEl/vtl. Prot., 2007 ME 102, err 14, 928
A.2d 736, 740. In reviewing SMPI's pennitthe BEP found that SMPI's project did
not meet four of the eight criteria. The four criteria under Title 38, Section 636
the BEP determined SMPI did not meet are as follows:
3. Public Benefits. The project will result in significant economic benefits to the public, including, but not limited to, creation of employment opportunities for workers of the State. 6. Environmental mitigation. The applicant has made reasonable provisions to realize the environmental benefits of the project, if any, and to mitigate its adverse environmental impacts. 7. Environmental and energy considerations. The advantages of the project are greater than the direct and cumulative adverse impacts over the life of the project based upon the following considerations: A. Whether the project will result in significant benefit or harm to soil stability, coastal and inland wetlands or the natural environment of any surface waters and their shorelands; B. Whether the project will result in significant benefit or harm to fish and wildlife resources. In making its determination, the department shall consider other existing uses of the watershed and fisheries management plans adopted by the Department of Inland Fisheries and Wildlife, the Department of Marine Resources and the Atlantic Salmon Commission;
7 Under the statute, "hydropower" includes both electrical and mechanical power. 38 M.R.S. § 632(4).
5 C. 'Whether the project will result in significant benefits or harm to historic and archeological resources; D. Whether the project will result in significant benefit or harm to the public rights of access to and use of the surface waters of the State for navigation, fishing, fowling, recreation and other lawful public uses; E. Whether the project will result in significant flood control benefi ts or flood hazards; and F. Whether the project will result in significant hydroelectric energy benefits, including the increase in generating capacity and annual energy output resulting from the project, and the amount of nonrenewable fuels it would replace. The department shall make a written finding of fact with respect to the nature and magnitude of the impact of the project on each of the considerations under this subsection .... 8. Water Quality. There is reasonable assurance that the project will not violate applicable state water quality standards, including the provisions of section 464, subsection 4, paragraph F, as required for water quality certification under the United States Water Pollution Control Act, Section 401. This finding is required for both the proposed impoundment and any affected classified water bodies downstream of the proposed im poundment.
See 38 M.R5. § 636.
The Department of Environmental Protection further defined the
requirements of 38 M.R.S. § 636 by administrative rule. Me. Dep't of Envtl. Prot.,
Ad771il1istmtive Rules for Hydropower Projects, 06-096 CMR 450. H To meet the
"public benefit" criterion under 38 M.R.S. § 636(3), the rules require the applicant
to show that the economic benefits "claimed from the proposed project are real,
in that these benefits would not result but for the project. ... [and] the applicant
must demonstrate that the project's economic benefits are greater than it's [sic]
economic costs, and that the resulting net benefit is significant." 06-096 CMR 450
§ 5(A)(3). The rules acknowledge that the terms "benefit" and "significant"
inherently require comparisons between alternative conditions. [d.
8 Available at thef()llowing website address: http://www.maine.gov/sos/cec/rules/06/chaps06.htm
6 Under 38 M.R.S. §636(6), the criterion for "environmental mitigation," the
rules define "mitigation" as "any action taken or not taken to avoid, minimize,
rectify, reduce, eliminate, or compensate for actual or potential adverse
environmental impacts." 06-009 CMR 450 § 3(H). The reasonableness of an
applicant's provisions to mitigate adverse environmental impacts depends on the
significance of the resources affected. 06-096 CMR 450 § 5(A)(6). Additionally,
under the criterion "environmental and energy considerations," 38 M.R.S. §
636(7), the rules provide the criterion will be met when the balance of the
project's advantages are greater than the project's adverse impacts based on the
specified environmental and energy considerations enumerated under Section
636(7)(A)-(F). 06-096 CMR 450 § 5(A)(7).
b. The Clean Water Act
SMP!' s proposed project is subject to the requirements of the Federal
Clean Water Act because it qualifies as an "activity ... which may result in [a]
discharge into the navigable waters [of the United States]." 33 U.s.c. §
1341(a)(1). Under Section 401 of the CWA, an applicant for a federal license or
permit to conduct an activity that may result in a discharge must comply with
state water quality standards. [d. This requirement is reiterated in the MWDCA
under Section 636(8), which requires reasonable assurance that the project will
not violate applicable state water quality standards. 38 M.R.S. § 636(8).
The State of Maine classifies water quality standards based on (1)
designated uses and related characteristics of those uses, (2) water quality criteria
necessary to protect those uses, and (3) a water quality antidegradation policy.
38 M.R.S. § 464(1). Class A waters are the second highest water quality
classification. 38 M.R.S. § 465(2). Class A waters must be characterized as
7 natural, and certain designated uses that disrupt the flow are permitted. 38
M.R.S. § 465(2)(A). The designated uses for Class A waters include recreation,
habitat for fish and other aquatic life (which must be characterized as natural),
fishing, navigation, and certain hydroelectric power generation. [d. The water
quality criteria for Class A waters require that the dissolved oxygen content be
not less than 7 parts per million or 75% saturation, whichever is higher; and the
aquatic life and bacteria content of Class A water shall be as naturally occurs. 38
M.R.S. § 465(2)(B). The antidegradation policy provides that "[e]xisting in
stream water uses and the level of water quality necessary to protect those
existing uses must be maintained and protected," and that "[e]xisting in-stream
water uses are those which have actually occurred on or after November 28,
1975, in or on a water body whether or not the uses are included in the standard
for classification of the particular water body." 38 M.R.S. § 464(4)(F).
IV. SMPI's Grounds for Appeal
On appeal, SMPI argues that the BEP's permit denial is inconsistent with
the MWDCA and constitutes legal error. SMPI argues that: (1) because the BEP
concluded that several alternatives to the proposed dam were available, the BEP
incorrectly applied an "alternatives" test to the MWDCA, and did not properly
balance the statutory criteria of the MWDCA; (2) the BEP improperly relied on a
factually incorrect, results driven report by the IF&W, and that the BEP
unlawfully delegated its decision-making authority to the IF&W; and (3) the BEP
failed to recognize that the Legislature has pre-determined that fish passage
facilities are sufficient mitigation for any adverse impacts a project will have on
upstream and downstream fish migration.
8 I. Standard of Review
When the Superior Court acts in an appellate capacity to review a decision
of an administrati ve agency, the court reviews the agency's decision directly for
an abuse of discretion, error of law, or findings not supported by the evidence.
Ulinllo v. Bd. of Envtl. Prot., 2009 ME 89, 9I 12, 977 A.2d 400, 407. In evaluating an
80C Appeal, it is not for the court to determine whether it would have reached
the same result as the agency, but to decide whether the record contains
competent and substantial evidence in support of the decision reached. CWCO,
Inc. v. Superintendent of I7zsurmzce, 1997 ME 226, 9I 6, 703 A.2d 1258, 1261. "An
administrative decision will be sustained if, on the basis of the entire record
before it, the agency could have fairly and reasonably found the facts as it did."
Id. The party seeking review of final agency action has the burden of proof.
Greely v. COlllllz'r, Dep't of Hili 11 n11 Servs., 2000 ME 56, 9I 9,748 A.2d 472,474. In
order to meet this burden, a petitioner must demonstrate that the record compels
a contrary conclusion. Kroeger v. Dep't of Ellvtl. Prot., 2005 ME 50, 9I 8, 870 A.2d
566, 569. "Inconsistent evidence will not render an agency decision
unsupported./I Seider v. Bd. of Exnllz'rs of Psyc1lOlogists, 2000 ME 206, 9I 9, 762 A.2d
551,555.
II. Alternatives Analysis
SMPI contends that the MWDCA is unlike other statutes within the DEP's
jurisdiction, such as the Natural Resources Protection Act, 38 M.R.S. § 481,
because the MWDCA specifically promotes the creation of hydropower projects,
and because the MWDCA does not require an "alternatives analysis," i.e., a
showing by the applicant that no less environmentally damaging alternative to
9 the proposed project is possible. 9 SMPI contends that the MWDCA does not
contain an alternatives analysis and that the BEP committed legal error when it
applied the alternatives analysis to the "environmental mitigation" and "public
benefits" criteria under 38 M.R.S. § 636. SMPI argues that instead of an
alternatives analysis, the MWDCA requires a balancing of factors for the "public
benefits" and "environmental mitigation" criteria.
Contrary to SMPI's assertions, the BEP did not commit legal error by
applying an alternatives analysis to its evaluation of SMPI's proposed project.
With respect to the environmental mitigation criterion, the BEP found:
[T]hat appellant has not presented any persuasive evidence that reasonable provisions have been made to realize the environmental benefits, if any, and to mitigate the adverse environmental impacts of the proposed project. The evidence in the record supports the findings that there are several feasible altenzatives that would allow operation of some or all of the sawmill machinery, thus avoiding the adverse environmental impacts associated with the reconstruction of the dam. 10
April 16, 2009 Order, p. 8 (enlphasis added) ("BEP Order"). Under the
environmental mitigation criterion, an alternatives analysis is implied. The term
"mitigation" is defined as "any action taken or not taken to avoid, minimize,
rectify, reduce, eliminate, or compensate for actual or potential adverse
environmental impacts." 06-096 CMR 450 § 3(H). Mitigation actions include:
') See, e.g., 09-096 CMR 310 § 9(A), which provides an alternatives analysis for applicants proposing regulated activities in, on, over, or adjacent to a wetland or water body.
10 The three feasible alternatives based on SMPI's alternatives analysis mentioned in the BEP's findings are: "installing a gate in the breached section of the dam that could be opened to allow fish passage/ spawning activity and closed to allow mill operation; using various forms of auxiliary power to operate the mill; and using pumps to fill a headbox with river water that would then power the mill in the absence of a reconstructed dam." BEP Order, p. 8.
10 "[a]voiding an impact altogether by not taking a certain action or parts of an
action," and "[m]inimizing an impact by limiting the magnitude or duration of
an activity or by controlling the timing of an activity." Id. As the BEP argues,
under this definition of mitigation, alternative may be considered to avoid
potentially adverse environmental impacts.
SMPI argues that BEP's findings of feasible alternatives for the
environmental mitigation criterion led the BEP to also find that SMPI did not
meet the public benefit criterion. With respect to the economic benefits under the
public benefit criterion, the BEP found that "[t]he evidence in the record supports
the findings that there are several feasible alternative that would allow operation
of some or all of the sawmill machinery, and this diminishes the economic
benefits that can be claimed for the project." BEP Order, p. 10. An alternatives
analysis may also be used to evaluate the potential public benefits of a proposed
project. The Ad1l1illistmtive Regulatiolls for Hydropower Projects provides the
following explanation of "benefit" as it is used in 38 M.R.S. § 636(3):
"Benefit" is a term which requires a comparison between at least two conditions.... [I]n order to accurately evaluate the existence and extent of the economic benefits that may result from a proposed hydropower project, it is necessary to compare two alternative futures: the economic conditions likely to exist if the project is built versus those likely to exist without the project.
06-096 CMR 450 § 5(A)(3). The regulation clearly contemplates consideration of
the economic outcome with the proposed project as opposed to without the
proposed project. In considering the value of the of the project if built, compared
to the economic outcome without the project, it is reasonable for the BEP to
consider how feasible alternatives to the proposed project may diminish the
overall economic benefit of completing the project. Therefore, the BEP's
11 interpretation of the MWDCA to employ an alternatives analysis is not an error
of law. See Save GilI' Sebasticook, at
"administrative agency's interpretation of a statute administered by it, while not
conclusive or binding on this [CJourt, will be given great deference and should
be upheld unless the statute plainly compels a contrary result.").
III. Balancing the Statutory Criteria
SMPI claims that the MWDCA mandates a balancing test, and claims that
the BEP did not give appropriate weight to the economic and social benefits of
SMPI's project. SMPI claims that the BEP failed to give appropriate weight to
employment opportunities, increases in the purchasing power of Maine citizens,
and the benefits of energy security, and claims that the BEP instead focused on
falsely inflated values assigned to fisheries. SMPI claims that the total value of
the project is $409,191 per year, compared to an estimated loss of fish habitat
worth only $15,325 annually. R. Tab 314, pp. 219-227; SMPI Brief, p. 21.
The DEP's Admil/istrative Regulations for Hydropower Projects provides
further guidance in terms of the types of economic costs and benefits the BEP
should consider when evaluating the "Public Benefit" criterion.
[E]conomic benefits may include, bllt are /lot limited to, increases in the income or purchasing power of Maine citizens, energy security from reducing dependence upon fossil fuels, and creation of employment opportunities for workers of the State.... [E]conomic costs may include, but are I/ot lil1/ited to, decreases in the income or purchasing power of Maine citizens, the value of other hydroelectric generating opportunities diminished or eliminated by a project, and the elimination of employment opportunities for workers of the State.
06-096 CMR 450 § 5(A)(3) (emphasis added). The BEP accepted the
Commissioner's December 31, 2008 findings that SMPl's proposed project would
result in economic benefits to the public in the form of employment in the
12 production and transportation of specialty wood products, no-cost educational
opportunities, and as an enhanced tourist attraction. The BEP also found that the
economic benefits that can be claimed for the projects are much less than asserted
by SMPI because (1) some of the claimed benefits already exist without
constructing the dam, and (2) some of the claimed benefits for the project can be
achieved by alternatives to the construction of the dam, further diminishing the
value of the proposed project. The BEP also agreed with the Commissioner and
found that the proposed project would result in economic costs to the public due
to adverse impacts on an economically significant Crooked River / Sebago Lake
landlocked salmon fishery because the project will reduce upstream passage,
spawning and nursery habitat, and will reduce recreational fishing for
landlocked salmon. The BEP's findings are supported by substantial evidence,
and SMPI has not met its burden in demonstrating by a preponderance of the
evidence that the construction of the dam will result in a significant economic
benefit.
SMPI also contends that the BEP did not properly balance the
environmental and energy considerations required by 38 M.R.S. § 636(7).
Specifically, SMPI contends that the BEP violated the MWDCA by undervaluing
hydro-mechanical projects. This argument is unsupported because SMPI's main
support for this claim is from a September 19, 1985 memo to the Commissioner
of the Department of Conservation - which was written nearly 25 years prior to
the BEP's decision. SMPI Brief, p. 23, citing R. Tab. 5, p. 2. Additionally, SMPI
claims the BEP violated the MWDCA by failing to give sufficient weight to the
benefits of historical preservation.
13 As stated above, the BEP is required to balance advantages of a proposed
project against its direct and cumulative adverse impacts over life of the project
based on the enumerated considerations of Section 636(7). In weighing the
considerations, the BEP concluded that the existing landlocked salmon fishery is
too important a resource to put at risk of diminishment for the sole benefit of the
restoration of a historic water powered sawmill. The BEP found that
reconstruction of the breached dam would substantially alter 2,000 square feet of
the landlocked salmon spawning habitat and would alter 1.4 acres of nursery
habitat. Additionally, the BEP found that the proposed rock ramp fishway
would reduce upstream passage for adult landlocked salmon from 100% to
99.5% and for juvenile landlocked salmon from 45% to 28.2% at river flows
between 25 cubic feet per second (cfs) and 650 cfs, when compared to existing
conditions. The BEP's findings with respect to environmental and energy
considerations are supported by substantial evidence.
IV. The IF&W's Report
SMPI argues that the BEP's reliance on the IF&W's report constituted an
impermissible delegation of the BEP's decision-making authority, and claims that
IF&W's report was biased against the construction of a dam. The BEP
acknowledges that well before any decisions were issued, the DEP had to correct
the IF&W's consulting biologist Francis Brautigam as to the IF&W's limited
advisory role, and noted in that letter that many of Brautigam's
recommendations appeared to go beyond the IF&W's limited role of evaluating
the impacts on fisheries. R. Tab 314, p. 261; Letter from Dana Paul Murch, Dams
and Hydropower Supervisor, Dep't of Envtl. Prot., to Francis Brautigam,
Regional Fisheries Biologist, Maine IF&W (March 24,2008). Brautigam's overly
14 critical analysis was noted in the BEP's Order. BEP Order, p. 7. Based on these
efforts, the DEP and the BEP ensured that the IF&W report was not taken into
consideration beyond its limited advisory role pursuant to 38 M.R.S. § 634(3) and
§ 636(7)(B). SMPI has failed to offer any evidence showing that the DEP or BEP
improperly delegated decision-making authority to the IF&W or improperly
relied on findings in the IF&W's report. As a result, SMPI's claim that the BEP's
use of the IF&W report constituted legal error fails.
a. Water Quality
SMPI alleges that the BEP's reliance on the IF&W's comments led to the
BEP's finding that the proposed project did not meet the water quality standards
under 38 M.RS § 636(8) and Section 401 of the Clean Water Act. 33 USc. §
1341. SMPI claims that this is evidenced by the DEP's change in position from
believing the project would meet water quality standards, to stating in the DEP
Order without explanation that the project would not meet water quality
standards. See SMPI Brief, p. 15 n. 3. In support of its assertion, SMPI references
a form dated May 27, 2003, which contains the comments of two members of the
DEP's Biological Monitoring Program within the Division of Environmental
Assessment. R. Tab 61, p. 13.
As the BEP points out, SMPI has taken the comments on this form out of
context. According to the BEP, the Biological Monitoring Program assesses the
health of rivers, streams, and wetlands by using water sample results to
determine attainment of water quality standards associated with Class AA, A, B,
and C water bodies. BEP Brief, p. 23. The BEP states the comments from the
Biological Monitoring Program are limited to whether or not SMPI's proposed
project will meet the water quality criteria for Class A water bodies. The
15 Commissioner of the DEP accepted, and the BEP adopted, the Biological
Monitoring Programs finding that with the proposed project in place, the water
would contain sufficient dissolved oxygen to meet the Class A water quality
standards.
However, the BEP found that the proposed project would not meet the
State's anti degradation policy and did not meet the water quality criteria because
with the project in place the river would not remain suitable for the designated
uses of "habitat for fish" and "recreation". R. Tab 1, pp. 12-13. SMPI has failed
to show that the BEP unreasonably relied on the IF&W's report with respect to
the water q uali ty cri teria. The BEP's decision should be upheld because it is
supported by substantial evidence, and because SMPI has failed to show an
abuse of discretion or error of law.
V. Are Fish Passage Facilities Always Sufficient Mitigation?
SMPI argues on page eleven of its brief that by passing the MWDCA the
legislature recognized that dam projects involve adverse impacts and that some
amount of adverse impact is permissible and acceptable. SMPI bases this
conclusion on 38 M.R.S. § 635(l)(A)-(C), which lists permissible approval terms
and conditions. According to Section 635(l)(C), the "terms and conditions IIIny
include, but nrc not limited to: ... Provisions for the construction and maintenance
of fish passage facilities." 38 M.R.S. § 635(l)(C) (emphasis added). The fact that
the legislature allows the DEP to condition the approval of a project on the
construction and maintenance of a fish passage facility does not mean that a fish
passage facility will always be sufficient mitigation for any adverse impacts on
fish l1'ligration that may result from the construction of a dam.
16 DECISION
Scribner's Mill Preservation, Inc.'s 80C Appeal is DENIED.
Dated at Portland, Maine this day of ,~L ,2010.
R ert E. Crowley Justice, Superior Court
17 J Date Filed _0_5_-_1_9_-_0_9 _ CUMBERLAND County --o-9_--1--,--6--e Docket No. - __A_P_-O
Action _ _8_0_C_A_p"-'p'--e_a_l _
SCRIBNER'S MILL PRESERVATION MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION C/O SCOTT D. HATCH MAINE BOARD OF ENVIRONMENTAL PROTECTION 232 SCRIBNER MILL RD. HARRISON, ME 04040 Ys. Plaintiff's Attorney Defendant's Attorney
PRe-&B JANET MCLINTOCK AAG (MAINE DEP) SCOTT D. ANDERSON ESQ DEPARTMENT OF THE ATTORNEY GENERAL VERRILL & DANA 6 STATE HOUSE STATION PO BOX 586 AUGUSTA ME 04330 PORTLAND ME 04112-0586 DAVID SWETNAM-BURLAND, ESQ. STACY STITHAM, ESQ. (NATURAL RESOURCES PO BOX 3070 NOT A DIRECT PARTY) Date of LEWISTON ME 04243-3070 Entry