Scoville v. Miller

40 Ill. App. 237, 1890 Ill. App. LEXIS 576
CourtAppellate Court of Illinois
DecidedMarch 13, 1891
StatusPublished
Cited by2 cases

This text of 40 Ill. App. 237 (Scoville v. Miller) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scoville v. Miller, 40 Ill. App. 237, 1890 Ill. App. LEXIS 576 (Ill. Ct. App. 1891).

Opinion

Moran, P. J.

The appeals in these eases were heard together in this court, on the same set of abstracts and briefs. The principal contentions are in each case the same, the contracts upon which the questions arise being in essential provisions identical. The actions were brought by the appellants, plaintiffs below, to recover for certain work done by them as sub-contractors in .excavating and grading the road bed of the Santa Fe railway under contracts with the defendants, who were principal contractors with the said railway company.

The controversy between the parties has reference chiefly to the amount of the different binds of excavation done under the contracts and allowed by the engineer of the work. The contention of appellants is, that the engineer in determining the amount of work done, did not proceed in accordance with the requirements of the contract, and that he allowed to the appellants very much less than they were in fact entitled to have. The contract fixed a certain price per cubic foot for earth work excavation, a higher price for loose rock, and a still higher price for solid rock excavation.

The specifications, which are made a part of the contract, declare, “ There shall be no classification of material of any kind other than earth, loose and solid rock, as provided for in these specifications and they provide, “Loose rock shall comprise:

“First. Shale or soapstone, lying in its original or stratified position, coarse boulders in gravel, cemented gravel, hard-pan or any other material requiring the use of pick and bar, or which can" not be plowed with a strong ten-inch grading plow, well handled behind a good six mule or horse team.

“Second. Detached rocks or boulders in masses exceeding one and a half cubic feet, and less than one cubic yard.”

The contract contained the following provision regarding the ascertaining and determining of the amount of work done under it:

“ Second. The work shall be executed under the direction and supervision of the chief engineer of said railway company and his assistants, by whose measurements and calculations the quantities and amounts of the several kinds of work performed under this contract shall be determined, and whose determination shall be conclusive upon the parties; and who shall have full power to reject or condemn all work or materials which in his or their opinion do not fully conform to the spirit of this agreement; and said chief engineer shall decide every question which can or may arise between the parties relative to the execution thereof, and his decision shall be binding and final upon both parties. And, whereas, the classification of excavation provided for in the annexed specifications is of a character that makes it necessary that special attention should be called to it, it is expressly agreed by the parties to this contract, that the'determination, by the measurements and calculations of the said engineer, of the respective quantities of such excavation, shall be final and conclusive.”

The engineer delivered estimates of the amount of the different kinds of work done, and the evidence showed that in arriving at the quantities of the different kinds of excavations, the cuts were measured to ascertain the total contents, and then certain percentages of the contents were called loose rock, and a certain percentage earth. This method of calculating the respective quantities of the different material was made necessary in the opinion of the engineer, by the variation of the material found in the cuts. There was but a portion homogeneous. There were sand pockets, and a continual change from hard to soft, and from soft to hard material, so that in some places the plow would run easily, and then upon the same level and in running the same furrow would strike material so hard that it would break out in chunks and could scarcely be plowed out at all. The material was all mixed up, and in classifying it, the engineers took into consideration what was called the force account, made by keeping watch of teams at work and the hardness of the material, and the amount of work accomplished, and allowed percentage of the different material by the exercise of their judgments upon their experience, knowledge and obsérvation of these various facts.

Appellants contend that this was not an estimate such as the contract required, and that the only determination of the engineer which could be binding, is one when, by actual measurement, the quantity of each kind of material should be ascertained. The argument is, that the only calculations which the engineer was to make, were mere mathematical processes to ascertain the bulk of a given material excavated, from actual measurements made.

This is not, in our opinion, a correct construction of the clause of the contract above set out, making the engineer’s determination conclusive upon the parties. The “ measurement” of an embankment or a cut includes the arithmetical calculation which will give the cubic contents, and if the engineer was to be confined to such calculations, then the word “ calculations ” in the connection in which it is used is tautological and unnecessary. The word as used in this clause of the contract, is to be understood in the sense of estimate, and the engineer was, after the measurement was ascertained by him, to determine by reference to the known contents and other data, the quantity of the different materials excavated. For instance, in the classification, hard pan as hard pan, pure and simple, is not to be called loose rock, but such material called hard pan, or any other material which should require the use of pick and bar, or which could not be plowed wdth a strong ten inch grading plow, well handled, behind a good six mule team. Now it is very manifest that where hard pan was struck, in order to know whether it was to be classed as loose rock or not, the engineer must know whether it requires the use of pick and bar, or that it could not be removed with a, ten inch plow and six mule team. What is hard pan is not defined in the contract, and it is apparent from the evidence in this case, that even those who claim to be experts do not agree as to what it is. The classification of the material and the calculation of the quantities involved something more than the ordinary arithmetical process of multiplying the length, width and depth together, and in view of this known difficulty of classification, and the opportunity for differences and dispute that would arise with regard to it, the parties deem it “necessary that special attention should he called to it,” for the purpose of expressly agreeing by the parties to the contract that “the determination, by the measurement and calculations of the said engineer, of the respective quantities of such excavation, shall be final and conclusive.” It would seem by this language the parties intended to render controversy as to the correctness of the engineer’s determination idle, and to bind themselves to submit to and abide by his conclusions. That such is the effect of the contract, where the engineer proceeds according to it, and in the absence of any allegation that in reaching his determination he acted fraudulently, has been repeatedly determined by the courts of last resort in this,as well as in other States. In our opinion, the engineer did in this case proceed according to the terms and true meaning and intent of the contract.

It is not contended that he was guilty of fraud in making his determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vincent v. Stiles
77 Ill. App. 200 (Appellate Court of Illinois, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
40 Ill. App. 237, 1890 Ill. App. LEXIS 576, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scoville-v-miller-illappct-1891.