Scoular-Bishop Grain Co. v. Bassett Grain, Inc.

352 N.W.2d 904, 218 Neb. 280, 1984 Neb. LEXIS 1206
Nebraska Supreme Court·Decided August 10, 1984·No. 83-481·Published·Cited by 2 cases

Opinion

Grant, J.

Plaintiff, Scoular-Bishop Grain Co., filed an action against defendant, Bassett Grain, Inc., seeking damages for amounts due under a lease agreement and.a modification thereof. Bassett Grain, in its answer, admitted the execution of the agreements but denied it was indebted to Scoular-Bishop. Jury trial was waived and trial was had to the court. At the conclusion of all the evidence, the court found for Bassett Grain and dismissed the petition. Scoular-Bishop appeals, assigning as error the insufficiency of the evidence to support the court’s decision in favor of Bassett Grain and alleging that the evidence required the court to find that Scoular-Bishop should recover on its amended petition. Appellant thus bases its appeal purely on an evidentiary basis. We believe the court disposes of the matter by its conclusions of law with regard to the construction of the contracts between the parties, and we affirm.

The terms of the lease and the modification thereof are not in dispute. On June 1,1978, Bassett Grain, as lessor, leased a grain *281 elevator located at Long Pine, Nebraska, to Scoular-Bishop. Scoular-Bishop was to pay a basic, fixed amount of rent plus, as additional rent, an amount equal to 50 percent of the net operating income resulting from the operation of the leased elevator during each of Scoular-Bishop’s fiscal years. The lease also provided that in the event there was a net operating loss for the fiscal year, that loss would be applied against any subsequent net income under the ■ lease and that, at the termination of the lease, an adjustment would be made to reflect the total income and total losses; and if the losses exceeded the income, Bassett Grain would pay 50 percent of those losses to Scoular-Bishop.

When the June 1,1978, lease was executed, Scoular-Bishop’s fiscal year ended on April 30. During the first 2 fiscal years involving the lease (June 1,1978, to April 30,1979, and May 1, 1979, to April 30, 1980), there was operating income of approximately $28,000 and $190,000 yearly. Scoular-Bishop paid 50 percent of that income to Bassett Grain.

After the fiscal year ending April 30, 1980, Scoular-Bishop changed its fiscal year so that it would end on May 31. For the 13 months ending May 31, 1981, there was a net operating loss of over $164,000. The agreement between the parties ended on June 30, 1981.

On July 11, 1980, the parties executed another agreement. Bassett Grain was having financial difficulties and requested Scoular-Bishop to make certain payments to Bassett Grain’s creditors rather than to Bassett Grain itself. Scoular-Bishop agreed to do so. Specifically, Scoular-Bishop agreed to pay three named creditors of Bassett Grain atotal of over $171,000 in lieu of all rent due up to April 30, 1981, including both the basic monthly rent and the percentage rental based on net operating profits or losses. The July 11, 1980, agreement further provided, in paragraph 2 thereof,

2. Each of the foregoing payments [to the described creditors] by the Lessee [Scoular-Bishop] shall be deemed to be made by the Lessee on account of rent due and becoming due under the lease up to April 30, 1981 and shall be charged to and deducted from such rent. If the total amount of all of such payments shall be in excess of *282 the aggregate amount of rent due and becoming due under the Lease up to April 30, 1981, the Lessor [Bassett Grain] shall not be liable for such excess or any part thereof.

(Emphasis supplied.)

This July 11, 1980, agreement also contained two other paragraphs which must be considered. Paragraph 5 states, “Except as modified by the provisions of this agreement, all of the terms and conditions of the Lease shall remain in full force and effect.” Paragraph 8 provides, “This instrument constitutes the entire agreement , and understanding of the parties with respect to the transactions contemplated hereby and supersedes any and all prior agreements and understandings relating to the subject matter hereof.”

The two agreements described above were placed in evidence. Scoular-Bishop called two witnesses, the manager of the elevator and the secretary-treasurer of the company. Neither witness testified as to any matters concerning the relationship between the two agreements or the conflicting paragraphs 5 and 8 in the July 11, 1980, agreement. The secretary-treasurer did testify and gave proper foundation for two exhibits comprising the monthly computer runs showing, from Scoular-Bishop’s books and records, the profit and loss for each month and year of the agreement between the parties. Bassett Grain did not present any evidence, and the matter was submitted to the trial court.

The trial court decided the matter by construing the July 11, 1980, agreement. At the conclusion of the trial, the court stated:

THE COURT: This agreement that was signed the 11th day of July, 1980, seems to indicate that everything is square between the parties on that date, and at paragraph 8 it says that this agreement constitutes the entire agreement and understanding of the parties with respect to the transactions contemplated herein and supersedes any and all prior agreements and understandings related to the subject matter hereof, so it would seem to me by that agreement you are at point zero in your accountings. It does provide that these specific payments that were to be made to the — that are outlined in paragraph 1, and *283 specifically to whom at (a), (b) and (c), and those payments are to be made through the month of April, and if the total amount of all such payments shall be in excess of the aggregate amount of rent due and becoming due under the lease up to April 30th, 1981, the lessor shall not be liable for such excess or any part thereof.

These observations were reflected in the court’s journal entry, which stated that the court finds

That, by reason of the agreement of the parties received into evidence as Exhibit No. 2 [the July 11, 1980, agreement], the obligation, if any, of the Defendant for any deficit operations under the percentage rental provisions of the lease as of April 30th, 1981 was zero (0) as between the parties.

The trial court properly construed the July 11, 1980, agreement as a matter of law. As stated in Don J. McMurray Co. v. Wiesman, 199 Neb. 494, 498, 260 N.W.2d 196, 199 (1977), “When the terms of a contract and the facts and circumstances that aid in ascertaining the intent of the parties are insufficient to raise an issue of fact, the interpretation of the contract is a matter of law.” In this case no evidence as to any facts and circumstances that would aid in ascertaining the intent of the parties was adduced before the trial court, and the interpretation of the contract was purely a matter of law. The court determined that paragraph 8 of the July 11, 1980, agreement controlled and that the second agreement completely supplanted the earlier agreement, referring to it only to incorporate certain language.

There is no assignment of error challenging this dispositive contract construction by the trial court. Neb. Ct. R. 9D(l)d (Rev.

Free access — add to your briefcase to read the full text and ask questions with AI

Scoular-Bishop Grain Co. v. Bassett Grain, Inc., 352 N.W.2d 904, 218 Neb. 280, 1984 Neb. LEXIS 1206 (Neb. 1984).

352 N.W.2d 904 (Scoular-Bishop Grain Co. v. Bassett Grain, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State on Behalf of Joseph F. v. Rial
554 N.W.2d 769 (Nebraska Supreme Court, 1996)
Flansburgh v. Coffey
370 N.W.2d 127 (Nebraska Supreme Court, 1985)