Scott v. Parkview Realty & Improvement Co.

164 S.W. 532, 255 Mo. 76, 1914 Mo. LEXIS 4
CourtSupreme Court of Missouri
DecidedFebruary 17, 1914
StatusPublished
Cited by4 cases

This text of 164 S.W. 532 (Scott v. Parkview Realty & Improvement Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott v. Parkview Realty & Improvement Co., 164 S.W. 532, 255 Mo. 76, 1914 Mo. LEXIS 4 (Mo. 1914).

Opinion

WILLIAMS, C.

Trial was had in the circuit court of the county of St. Louis, before a jury, resulting in a verdict and judgment in favor of plaintiffs' upon the third count of their petition in the sum of $116,381.35'. The case was tried upon the issues raised by the first and third counts of plaintiffs ’ petition, defendant’s second amended answer and plaintiffs’ reply. This is the second appeal in the case. The opinion upon the first appeal was rendered by Court in Banc and is reported in 241 Missouri at page 112. The pleadings upon the part of the plaintiffs are the •same as they were upon the first trial.

[83]*83By this suit plaintiffs seek to recover from the defendant company the sum of $77,933.94, with interest thereon, for an alleged balance due plaintiffs for work done in grading a large tract of land belonging to defendant and located near the city limits of the city of St. Louis. The first count of the petition was founded upon contract and the third count upon quantum meruit. The second amended answer pleads settlement, accord and satisfaction and a counterclaim, for liquidated damages in the sum of $32,500 for failure to complete the grading work within the time provided by the grading contract and the extensions and modifications thereof. Aside from the pleading of the counterclaim the second amended answer, while containing more words, is, as to the issues raised, of practically the same effect as the answer upon the first trial. The reply is the same as upon the first trial. It contains, a general denial and pleads confession and avoidance as to the settlement, accord and satisfaction set forth in the answer.

On February 12, 1902, plaintiffs and the defendant company entered into a written contract whereby plaintiffs agreed to do certain grading work upon a tract of land containing about three hundred acres which -the defendant owned and was desirous of having graded and leveled preparatory to dividing the tract into residence lots and offering the same for sale to the public. The contract provided that the amount of grading should not be less than 1,400,000 nor more than 2,100,000 cubic yards of earth. The work was to be accomplished by cutting down the high portions of the tract and depositing the dirt therefrom into the valleys or lower levels of the tract. The work was to be done in a workmanlike manner and in conformity with directions given by Pitzman’s Company of Surveyors and Engineers, as engineers, of defendant company. The tract of land to be graded was approximately three times as, long as it was wide; the long [84]*84way being east and west. The right of way of the Wabash Railroad Company entered the tract at the southeast corner thereof and ran diagonally across the eastern portion of the tract in a northwesterly direction. A short distance west of the Wabash Railroad Company’s right of way the river Des Peres crossed the tract from south to north. Skinker Road ran north and south through the tract leaving about one-third of the entire tract west of Skinker Road. This roadway had been cut down so that it was approximately ten feet lower than the surface of the tract adjoining the roadway. The land adjoining Skinker Road was to be cut to a depth of about twenty-five feet and Skinker Road was to be lowered about fifteen feet. The tract of ground was bounded on the south by the right of way of the St. Louis, Kansas City and Colorado Railroad and on the north by Delmar boulevard. By the terms of the contract plaintiffs were to receive eighteen cents per cubic yard based upon an average haul of 1400 feet and three-fourths of a cent extra per cubic yard for every hundred feet of average haul over 1400 feet. The original contract provided that in the event plaintiffs should fail to complete the work by November 1, 1902, they should pay, as liquidated damages, the sum of $500 for each and every day’s delay after that date and, if the plaintiffs should complete the work prior to that date they would receive additional compensation of $100 per day for each and every day that the work was finished ahead of time. The contract contained the' following provisions: “The engineer’s opinion as to the increase of haul is to be binding on both parties. . . . And when all the work embraced in this contract is fully completed, agreeably to the specifications and stipulations of this agreement, and accepted by' the engineer, said engineer shall cause a final estimate to be made of the amount and value of said work according to the terms and prices of this agreement. [85]*85From the total amount so found he shall deduct all sums previously paid or rightfully retained, and certify the remainder as then due. Provided further, that nothing herein contained shall he construed to affect the right of the second party, hereby reserved, to reject the whole or any portion of the work aforesaid should the said certificate be found or known to be inconsistent with the terms of this agreement, or otherwise improperly given. ’ ’

The contract was silent with reference to the routes over which the dirt was to be hauled and also silent as to what appliances should be used in doing the work. On November 9, 1902, in consideration of certain modifications of the original contract the defendant company, by written agreement, extended the time for completion of the work from November 1, 1902, to July 1, 1903> and provided that the clause providing for the payment to the plaintiffs of the sum of $100 per day for each day that the contract might be finished ahead of time should be canceled but that the modification should not in any wise be taken to limit the right of the defendant company to receive stipulated damages for each day’s delay in completing the work after July 1, 1903. Later (the date is not given) the contract was modified by a further written agreement signed by both parties whereby the time for completion of the work was extended from July 1, 1903, to October 1, 1903, upon the conditions that the plaintiffs agree, upon notice from the engineer in charge, to complete all work on such portions as should be required for actual use and disposition prior to November 1, and as a further consideration of such extension it was agreed that the maximum amount of grading should be increased to 2,250,000 cubic yards, and further provided that the defendant might, in his discretion, have other parties do filling on said land with earth excavated outside of said land. Said written agreement provided that the original contract and [86]*86the modifications thereof were modified and amended to conform with the provisions of the last agreement. The total amount of dirt handled by plaintiffs was 2,053,595 cubic yards and concerning the amount of yardage there was no dispute.

This whole controversy arises over the determination of the length of the average overhaul. Plaintiffs contend that the average haul for the entire work was 2166 feet, which would leave the average overhaul to be 766 feet. Defendant contends that the average length of haul on the entire work was 1660 feet, which would leave the average overhaul 260 feet. Prior to the institution of this suit the defendant company had paid the plaintiffs the total sum of $426,022.70, which was the total sum that the work would amount to, if the average overhaul was 260 feet as contended by defendants. This suit is to recover for the haul of the total yardage the further distance of 506 feet. The work was completed about December 5, 1903. At that time the plaintiffs, had received from the defendants the total sum of $349,525>.10 on account. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Poe v. Illinois Cent. Railroad Co.
99 S.W.2d 82 (Supreme Court of Missouri, 1936)
Scott v. Barton
226 S.W. 958 (Supreme Court of Missouri, 1920)
Scott v. Luehrmann
213 S.W. 855 (Supreme Court of Missouri, 1919)
Barrett v. Stoddard County
197 S.W. 914 (Supreme Court of Missouri, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
164 S.W. 532, 255 Mo. 76, 1914 Mo. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-v-parkview-realty-improvement-co-mo-1914.