Scott v. Keeth

116 N.W. 183, 152 Mich. 547, 1908 Mich. LEXIS 888
CourtMichigan Supreme Court
DecidedMay 1, 1908
DocketDocket No. 34
StatusPublished
Cited by5 cases

This text of 116 N.W. 183 (Scott v. Keeth) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott v. Keeth, 116 N.W. 183, 152 Mich. 547, 1908 Mich. LEXIS 888 (Mich. 1908).

Opinion

Hooker, J.

The complainant’s bill was filed to enforce a lien on a double three-story business building in the city of Saginaw for labor and material furnished under and in connection with a contract to install a steam-heating plant therein. The bill states that the contract provided for the erection of a steam-heating plant, etc., and that $425 was due upon it, while the item for extra work was not covered by the written contract, and amounts to $120.70. It alleged that the Citizens’ Savings Bank of Holly, Michigan, was the holder of two mortgages upon the premises at the time said contracts were made, and Keeth and the bank were made defendants. Mrs. Keeth was made a defendant after it appeared from Keeth’s answer that the building was claimed to be a homestead. All the defendants answered.

The cause was heard upon the merits and a decree was made favoring the complainant. It provided that the complainant should recover from Keeth the sum of $597.31, and that the same should be a lien upon the entire steam-heating apparatus, and upon all of the interests of defendant Keeth in the premises on August 13, 1903, describing said premises, but subject to Mrs. Keeth’s homestead rights, and subject to the rights of the bank under one of the mortgages, the other having been paid. It provided further, that if the defendants should disconnect the boiler described in the bill and should deliver the same unimpaired to the complainant at the premises, within 30 days of the date of the decree, the sum of $300 should be deducted from the amount of the decree. Costs were awarded to complainant and these were made a lien upon the premises, subject to the rights before mentioned, [549]*549and execution was ordered to issue at complainant’s option. The decree appears to have been satisfactory to all parties except defendant William Keeth, who alone has appealed.

Merits. Defendant Keeth claims that the complainant’s claim for installing the heater never became due, for the reason that the plant does not and. never has complied with the provisions of the contract. The learned circuit judge has not in his decree, or in any opinion, stated that it did comply with the contract except as it may be inferred from the fact that he found the contract price due and a lien upon the premises, and perhaps .that is not inconsistent with the fact that the plant has never befen made to do the work guaranteed by the contract. The contract consists of a submission of written specifications of the apparatus and work with a guaranty and proposal signed by the complainant, accepted in writing over the signature of Mr. Keeth.

The following extract contains a copy of guaranty and method of payments :

“Upon completion of the work herein specified the apparatus shall be tested in the presence of the owner or his representative. The owner shall supply all necessary fuel for testing said apparatus. * * *

“Guarantee.

“When the apparatus.herein proposed to be furnished is completed in accordance with the conditions herein, I guarantee that it shall be capable of warming all rooms mentioned in the schedule except second floor hall, to the temperature mentioned herein, during the coldest winter weather, when the building is furnished and occupied. I also guarantee that all work and materials furnished by me shall be free from any mechanical defects for a period of three years from the time the work is completed; it being understood and agreed that such acceptance shall not be deemed a waiver by you, of the guarantee made by us and set forth in this proposal. If, after this apparatus shall have been accepted by you and part thereof constructed by me under this proposal shall fail to accomplish this guarantee herein contained, I agree to examine, test [550]*550and remedy such defects at my own costs and expense, within a reasonable time after having received notice of such defect.

“Extras.

“ It is intended by these specifications to provide for the furnishing and setting up by us as otherwise stipulated, of everything essential to a complete and perfect working, low pressure steam apparatus, for the building named, and accordingly everything required for such an apparatus except as aforesaid, shall be furnished and set up by me, without extra charge to you. * * *

“ I will furnish all materials, tools and labor to complete heating and plumbing as per the above specifications, for the sum of Ten hundred and seventy-five dollars ($1,075).

“ Payments.

“ The first payment to be made when the material is delivered and to be the sum of Five hundred dollars ($500). Second, when completed, Three hundred and seventy-five dollars ($375). Third, January 1st, 1904, One hundred dollars ($100). Balance March 1st, 1904, $100.”

This work was completed in January, 1904, and the bill was filed in April of that year. The decree was made December 30, 1905.

Evidently defendant Keeth accepted this plant after a test which doubtless led him to believe it a compliance with the contract. He did not thereby waive his rights under the guaranty, and he has consistently and repeatedly asserted his dissatisfaction with the plant, and we may add that the proof is persuasive that the complainant has not complied with his guaranty. But we do not decide this for the reason that it is not controlling upon this record. It is not a case where defendant has asked affirmative relief, nor is there proof from which we can determine the amount, if anything, which should be awarded, if the question of recoupment could be considered. The circuit court could not avoid allowing complainant’s claim for the contract price, and had complainant appealed we might have found difficulty in affirming the option given defendants of removing and returning [551]*551the boiler as provided in.the decree. But the option was disregarded and the time for its exercise has long since expired, and therefore it will not be discussed.

The claim for extra work was proved. We feel justified in saying that the two items were a legal charge against defendant Keeth, subject to his right of action upon the guaranty.

Lien. Several questions relating to a right to a lien have been discussed. So far as the rights of the wife and the bank are concerned, they are made secure by the decree, complainant not having appealed. Mr. Keeth, however, claims that, inasmuch as a portion of the building was occupied as a residence by him, it was not subject to alien, inasmuch as his wife did not sign the contract; also that if he is not sustained upon that ground, the total absence of proof of value precludes a decree for complainant; also that execution cannot issue against him until a sale has shown a deficiency.

Homestead. Defendant’s counsel rely on 8 Comp. Laws, § 10711, to sustain his claim that a homestead is not subject to lien where the contract has not been signed by a wife.

As the law stood in 1885, Act No. 216, a lien was permitted to attach subject to the homestead exemption. See Lamont v. Le Fevre, 96 Mich. 175. See, also, Mills v. Hobbs, 76 Mich. 122.

• Act No. 179, Pub. Acts 1891, § 2, provided:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sharon v. Fee
168 N.W. 1045 (Michigan Supreme Court, 1918)
Case Threshing Machine Co. v. Scott
165 P. 485 (Washington Supreme Court, 1917)
Holland Furnace Co. v. Hartig
148 N.W. 169 (Michigan Supreme Court, 1914)
Argersinger v. Commonwealth Power Co.
129 N.W. 889 (Michigan Supreme Court, 1911)
Frolich v. Blackstock
119 N.W. 906 (Michigan Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
116 N.W. 183, 152 Mich. 547, 1908 Mich. LEXIS 888, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-v-keeth-mich-1908.