Scott + Reid General Contractors, Inc. v. Sam Stanton and Heather Stanton

CourtCourt of Appeals of Texas
DecidedOctober 7, 2022
Docket05-22-00400-CV
StatusPublished

This text of Scott + Reid General Contractors, Inc. v. Sam Stanton and Heather Stanton (Scott + Reid General Contractors, Inc. v. Sam Stanton and Heather Stanton) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott + Reid General Contractors, Inc. v. Sam Stanton and Heather Stanton, (Tex. Ct. App. 2022).

Opinion

Affirm and Opinion Filed October 7, 2022

In The Court of Appeals Fifth District of Texas at Dallas No. 05-22-00400-CV

SCOTT + REID GENERAL CONTRACTORS, INC., Appellant V. SAM STANTON AND HEATHER STANTON, Appellees

On Appeal from the County Court at Law No. 1 Dallas County, Texas Trial Court Cause No. CC-17-05704-A

MEMORANDUM OPINION Before Justices Myers, Pedersen, III, and Garcia Opinion by Justice Myers Scott + Reid General Contractors, Inc. appeals the trial court’s order denying

its motion to compel arbitration. Appellant brings two issues contending the trial

court’s denial of the motion was an abuse of discretion. We affirm the trial court’s

order.

BACKGROUND Sam Stanton and Heather Stanton own a house. Behind the house is a

commercial center. The property directly behind their property was undergoing

construction of the Bellomy Office building owned and operated by 4415 W Lovers

Lane, LLC and various entities using the name “Bellomy.” Appellant was the general contractor for the construction project. The general

contract between appellant and 4415 stated appellant would “take reasonable

precautions for the safety of, and shall provide reasonable protection to prevent

damage, injury or loss to . . . other property at the site or adjacent thereto . . . .” The

general contract did not contain an arbitration provision but instead provided that

disputes between 4415 and appellant would be resolved first by mediation with the

architect, and if that was unsuccessful, then by “Litigation in a court of competent

jurisdiction.”

The construction project required excavation for a parking garage. The

excavator for the project was A&J Bobcat Service LLC. Appellant’s subcontract

with A&J provided that any disputes between appellant and A&J that could not be

resolved by other described means “shall be submitted to arbitration . . . conducted

in accordance with the Construction Industry Dispute Resolution Procedures . . . as

set forth by the American Arbitration Association.”

The Stantons alleged their property was damaged by the excavation. They

sued appellant, A&J, 4415, and two Bellomy entities. The Stantons’ claims included

breach of contract against appellant. Although the Stantons did not have a contract

with appellant, they alleged they were third-party beneficiaries of the general

contract because their property bordered the construction site and appellant promised

in the general contract that it would “provide reasonable protection to prevent

damage, injury or loss to . . . other property at the site or adjacent thereto.” They

–2– alleged appellant breached the contract by failing to prevent damage and by failing

to repair the damage to their property caused by the excavation.

The Stantons also alleged that “[t]o the extent that S + R [appellant]

contracted with A+J [sic] to perform work under the Contractor Agreement, then the

Stantons are also third-party beneficiaries of such agreement.” They alleged that to

the extent A&J performed work at appellant’s direction and the work damaged the

Stantons’ property, appellant and A&J breached their obligations under the general

contract “and/or any related agreement” between appellant and A&J to remedy the

damage.

Appellant moved to compel arbitration of the Stantons’ claims. Appellant

argued that the Stantons, by alleging they were third-party beneficiaries of the

subcontract with A&J, were subject to the arbitration provision in that subcontract

for any claim of damages resulting from the alleged breach of the subcontract. The

Stantons presented evidence that A&J did not perform the excavation work under

the subcontract with appellant but under a separate contract directly with 4415 and

the Bellomy entities. The Stantons argued that because the excavation work was not

performed pursuant to appellant’s subcontract with A&J, the condition under which

the Stantons alleged to be third-party beneficiaries to the subcontract was not met,

and the arbitration clause in the subcontract did not apply to the Stantons.

The trial court denied appellant’s motion to compel arbitration. Appellant

brings this interlocutory appeal of that order. See TEX. CIV. PRAC. & REM. CODE

–3– ANN. § 51.016 (appeal of order denying motion to compel arbitration under Federal

Arbitration Act); id. § 171.098(a)(1) (appeal of order denying motion to compel

arbitration under Texas Arbitration Act).

REVIEW OF MOTION TO COMPEL ARBITRATION In its first issue, appellant contends the trial court erred by denying the motion

to compel arbitration. Appellant asserts it established the existence of a valid and

mandatory arbitration agreement encompassing the Stantons’ claims and that the

Stantons did not prove a defense to the enforcement of the arbitration provision.

We review the denial of a motion to compel arbitration for an abuse of

discretion, deferring to the trial court on factual determinations that are supported by

the evidence and reviewing legal determinations de novo. Henry v. Cash Biz, LP,

551 S.W.3d 111, 115 (Tex. 2018). The trial court did not issue findings of fact or

conclusions of law to explain its denial of the motion to compel arbitration. We

must, therefore, uphold the trial court’s decision on any appropriate legal theory

urged below. Bonded Builders Home Warranty Ass’n of Tex. v. Rockoff, 509 S.W.3d

523, 531–32 (Tex. App.—El Paso 2016, no pet.).

The first question is whether appellant proved the existence of an arbitration

agreement applicable to the parties. Appellant argues it proved the existence of the

arbitration agreement. Appellant states in its brief that the Stantons admitted at the

hearing on the motion to compel arbitration that the A&J subcontract with its

arbitration provision existed and that it applied to them. Appellant quotes the

–4– Stantons’ attorney, Mr. Minter, from the hearing to compel arbitration, and appellant

asserts Mr. Minter admitted the existence of an arbitration agreement between the

parties:

Mr. Minter: . . . [W]e pled that to the extent that S+R contracted with A&J to perform work under the contractor agreement, then the Stantons are also third-party beneficiaries. But what this turns on is not that there was a contract between S+R, which was the general contractor for the property, and A&J, who was hired to do the excavation work. There was such a contract.

(Emphasis added by appellant.) However, appellant does not quote what Mr. Minter

said next:

What is not being said here and what I’m getting ready to say and I guess I’ll say in my response is that that contract as to the performance of A&J to do the excavation no longer existed when A&J did the excavation. At least, it did not exist under those terms. The testimony of Mr. Hoagland, S + R’s corporate representative, and the testimony of Mr. Jones, A&J’s representative, clearly point to the fact that there’s something going on in that suddenly S + R was told before the excavation started by the 4415 or Bellomy Group or whatever you want to call them was told get off the project. Then A&J contracted directly with the 4415 to do the excavation. And then Mr. Jones testifies—it is before this Court—that he then—there were change orders that modified the contract between S + R and A&J to the point that he was no longer to do the excavation under the original S + R and A&J contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Scott + Reid General Contractors, Inc. v. Sam Stanton and Heather Stanton, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-reid-general-contractors-inc-v-sam-stanton-and-heather-stanton-texapp-2022.