Scott Anderson Trucking v. Nielson Construction

2020 UT App 43, 462 P.3d 822
CourtCourt of Appeals of Utah
DecidedMarch 19, 2020
Docket20180274-CA
StatusPublished
Cited by4 cases

This text of 2020 UT App 43 (Scott Anderson Trucking v. Nielson Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott Anderson Trucking v. Nielson Construction, 2020 UT App 43, 462 P.3d 822 (Utah Ct. App. 2020).

Opinion

2020 UT App 43

THE UTAH COURT OF APPEALS

SCOTT ANDERSON TRUCKING INC., Appellee, v. NIELSON CONSTRUCTION, Appellant.

Opinion No. 20180274-CA Filed March 19, 2020

Seventh District Court, Castle Dale Department The Honorable Douglas B. Thomas No. 160700026

Joseph C. Rust, Attorney for Appellant Stevan R. Baxter, Michael D. Lichfield, and Chase Ames, Attorneys for Appellee

JUDGE JILL M. POHLMAN authored this Opinion, in which JUDGES GREGORY K. ORME and DAVID N. MORTENSEN concurred.

POHLMAN, Judge:

¶1 Nielson Construction (Buyer) appeals the district court’s summary judgment in favor of Scott Anderson Trucking Inc. (Seller) on Seller’s breach of contract claim. After Seller told Buyer that it would sell a product for $25 per ton and that it had 12,000 to 15,000 tons available, Buyer emailed Seller, saying that Buyer “will need 12000 tons of [the product] at 20% for the project [and] will pay [Seller] $25.00 a ton.” Buyer contends that the district court erred in determining that Buyer and Seller had an enforceable contract, that Buyer had not repudiated the contract, and that the contract was not a requirements contract. We affirm. Scott Anderson Trucking v. Nielson Construction

BACKGROUND 1

¶2 Buyer is a road builder that was hired to perform paving work on Gooseberry Road (the Gooseberry Project). For this project, Buyer required rotomill, which is recycled asphalt that can be combined with new asphalt for paving.

¶3 Seller is a trucking company that hauls and sometimes supplies construction materials like rotomill. Around the same time that Buyer needed rotomill for the Gooseberry Project, Seller had a pile of rotomill on its property that had been removed from Buyer’s previous project site.

¶4 In 2013, Buyer’s representative and paving manager, Bobby Peirce, spoke with Seller’s principal, Scott Anderson, about acquiring rotomill for the Gooseberry Project (the First Conversation). During the First Conversation, Peirce asked Anderson if Seller was interested in selling Buyer the pile of rotomill. Peirce also asked how much rotomill was available. Anderson explained that Seller “had somewhere between 12,000 and 15,000 tons remaining in the pile” and that it would sell the rotomill to Buyer for $25 per ton. In response, Peirce said that he “would have to review that price . . . with [Buyer’s] management.”

¶5 In December 2013, Peirce and Anderson spoke again (the Second Conversation). During the Second Conversation, Peirce told Anderson that “the price of $25 a ton was acceptable to [Buyer].” On December 31, 2013, Peirce emailed Anderson (the Email), stating,

1. “When evaluating the propriety of summary judgment on cross-motions for summary judgment, we view the facts and any reasonable inferences to be drawn therefrom in the light most favorable to the losing party.” Flowell Elec. Ass’n v. Rhodes Pump, LLC, 2015 UT 87, ¶ 8, 361 P.3d 91.

20180274-CA 2 2020 UT App 43 Scott Anderson Trucking v. Nielson Construction

Scott

There is 60000 tons of Asphalt on the Gooseberry Project we will need 12000 tons of Rotomill at 20% for the project will pay you $25.00 a ton. If there is more than that we may back haul some to Huntington thanks Bob.

The Email did not contain any conditions on the purchase related to the quality of rotomill, and Peirce did not subsequently communicate to Seller any different terms.

¶6 Buyer knew the location of Seller’s pile of rotomill, knew that it came from Buyer’s previous project, and had ample opportunity to inspect it. Yet Buyer did not view the rotomill until, at the earliest, the spring of 2015—at least sixteen months after the Email.

¶7 On September 12, 2015, Buyer started laying asphalt on the Gooseberry Project using rotomill from another source. Around that time, Peirce called Anderson to state that Buyer was rejecting Seller’s rotomill because it was “faded or bleached and it’s got lumps in it.” Peirce had viewed Seller’s stockpile of rotomill from his car and used that inspection as the basis for Buyer’s rejection. After Buyer rejected Seller’s rotomill, there was no market for it in the area.

¶8 Seller then sued Buyer for breach of contract. Both sides moved for summary judgment. In its motion, Buyer contended that the alleged contract between Buyer and Seller was indefinite and “too vague to enforce” and that Buyer was entitled to judgment as a matter of law. Seller opposed Buyer’s motion, arguing that the “amount of rotomill and purchase price of the rotomill are clear, definite, and enforceable contract terms.” In arguing that summary judgment instead should be granted in its favor, Seller further asserted that the undisputed facts showed that Buyer “breached a clear, definite, and enforceable contract

20180274-CA 3 2020 UT App 43 Scott Anderson Trucking v. Nielson Construction

for the sale of rotomill, damaging [Seller]” in the amount of $300,000. Buyer opposed Seller’s motion by arguing, in part, that even if a contract existed, Buyer rightfully terminated the contract when Peirce rejected the rotomill.

¶9 The district court agreed with Seller. It first determined “as a matter of law that there was, in fact, a contract between the parties pursuant to which [Buyer] agreed to purchase 12,000 tons of rotomill from [Seller] at $25 per ton.” The court next determined that the contract did not fail for indefiniteness because the contract “specifically states the quantity requested, the parties knew, at all relevant times, where the product was and where it came from, and [Buyer] agreed to pay $25 per ton for 12,000 tons.” The court further ruled that the contract lacked conditions about the quality of Seller’s rotomill and that Buyer had not included “any condition precedent . . . or reserved any conditions.”

¶10 On the question of whether Buyer rightfully terminated the contract, the district court concluded that Buyer “took too long as a matter of law to repudiate the contract.” The court reasoned that the Uniform Commercial Code, as adopted by Utah, required Buyer to “inspect the goods sooner than 16–18 months after agreeing to purchase the rotomill.” It explained that Buyer’s “first indication” to Seller in the spring of 2015 that Buyer was not “abiding by the terms of the contract” came too late, especially when Buyer “could have looked at the pile before and after the contract was formed but failed to do so.” As a result, the court determined that Buyer “did not reject or repudiate the contract for rotomill within a reasonable time” and that any alleged rejection of rotomill by Buyer was “ineffective.”

¶11 The court then ruled that Buyer’s breach of contract was “evident on September 12, 2015 when it moved forward on the Gooseberry Project without the rotomill” from Seller. The court thus granted summary judgment to Seller. And because Buyer

20180274-CA 4 2020 UT App 43 Scott Anderson Trucking v. Nielson Construction

was contractually obligated to pay a principal amount of $300,000 under the contract, the court awarded Seller $300,000, plus interest.

¶12 After the court announced its oral ruling but before it entered its written ruling, Buyer delivered a letter and a $300,000 check to Seller. Buyer’s December 18, 2017 letter stated,

Enclosed with this letter is a check made payable to [Seller] in the amount of $300,000, reflecting the amount of the principal sum found owing by [Buyer] to [Seller]. We are making this payment while awaiting a final judgment for the purpose of abating interest. In making this partial payment, [Buyer] fully and completely reserves its right of appeal and specifically relies on Utah Res. Int’l Inc. v. Mark Techs. Corp., 2014 UT 59, ¶ 33, 342 P.3d 761.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Draughon
Court of Appeals of Utah, 2026
Smith v. Creech
2025 UT App 195 (Court of Appeals of Utah, 2025)
Farm Bureau v. Weston
2023 UT App 136 (Court of Appeals of Utah, 2023)
Knowlton v. Knowlton
2023 UT App 16 (Court of Appeals of Utah, 2023)
UDAK Properties v. Canyon Creek
2021 UT App 16 (Court of Appeals of Utah, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2020 UT App 43, 462 P.3d 822, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-anderson-trucking-v-nielson-construction-utahctapp-2020.