S.C.O. Development v. Consolidated Precast, No. Cv 113293 (Jun. 30, 1993)

1993 Conn. Super. Ct. 6233
CourtConnecticut Superior Court
DecidedJune 30, 1993
DocketNo. CV 113293 CV 113449
StatusUnpublished

This text of 1993 Conn. Super. Ct. 6233 (S.C.O. Development v. Consolidated Precast, No. Cv 113293 (Jun. 30, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.C.O. Development v. Consolidated Precast, No. Cv 113293 (Jun. 30, 1993), 1993 Conn. Super. Ct. 6233 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION CT Page 6234 FACTS

This action arises out of a construction payment dispute between the owner of the construction project, the contractor, and a subcontractor. The court finds the following facts were before the arbitrator. (See S.C.O. record.)

S.C.O. Development Company (hereinafter "S.C.O."), is the owner of a commercial construction project known as the "Gateway Project," located in Waterbury, Connecticut. On April 1, 1989, S.C.O. entered into a contract with Specialty Management Corporation (hereinafter referred to as "SMCORP"), which would serve as construction manager of the "Gateway Project." On July 14, 1989, SMCORP entered into a partnership agreement with William Steward Construction Management Corporation (hereinafter referred to as "Steward"), whereby they formed Specialty Management Company (hereinafter referred to as "SMC"), to "enter into and complete construction management contracts. . ." (See S.C.O. record, S-10, Partnership Agreement p. 1).

On December 15, 1989, SMC entered into a subcontract agreement with Consolidated Precast, Incorporated (hereinafter referred to as "CPI"), whereby CPI was to provide concrete precast for the "Gateway Project." CPI was to be paid $235,000.00 for its work. The subcontract agreement between SMC and CPI lists SMC as the contractor, CPI as the subcontractor, and S.C.O. as the owner of the project, Gateway Center. (See S.C.O. record, C-4).

On March 5, 1990, a letter was sent from Brian Connolly of S.C.O. to CPI, concerning specifications of the subcontract. Under Brian Connolly's name at the bottom of the letter is the title "Project Manager." It should be noted that this letter was sent on SMC stationery. (See S.C.O. record, C-4.) On August 3, 1990, S.C.O. sent a letter to First Federal Savings Loan of Waterbury, Connecticut, stating that First Federal was to count the number of pieces of precast installed each day by CPI, and to issue a check each day for the number of pieces installed. (See S.C.O. record, S-3.) On August 24, 1990, Neil Postighone, President of SMC, sent a letter to all subcontractors stating that their contracts had been assigned to S.C.O. and that all directions, correspondence and payments would be made directly from S.C.O. (See S.C.O. record, C-2.) CT Page 6235 The letter further stated that S.C.O.'s representative, Brian Connolly, should be contacted for any further information. S.C.O. issued checks to CPI on September 7, 1990, and on September 12, 1990, in the amount of $83,250.00 and $108,225.00, respectively. (See S.C.O. record, R-2 and R-3.) On February 12, 1991, S.C.O. sent a letter to CPI confirming a change order that S.C.O. had requested. A price of $656.91 was authorized for the order. (See S.C.O. record, C-2.) Letters were sent from CPI to S.C.O. on three different occasions, March 19, 1991, June 21, 1991, and September 3, 1991, requesting payment of the remaining money due on the contract, $24,181.91. (See S.C.O. record, R-4 and R-5.) S.C.O. has not paid the remaining money owed on the contract.

On September 16, 1991, CPI filed a demand for arbitration with the American Arbitration Association against S.C.O. and SMC accompanied by a document entitled "Claimant's Statement." On March 19, 1992, S.C.O. filed its answer and special defenses to CPI's demand for arbitration. While there was no written "submission" submitted to the arbitrator it is submitted that, from CPI's statement and S.C.O.'s answer and special defenses, the issues before the arbitrator were whether S.C.O. accepted an assignment of the subcontract and whether there was a novation of the contract by CPI. On December 25, 1992, the arbitrator made a written award in favor of CPI against S.C.O. in the amount of $27,637.60. The arbitrator held that "S.C.O. Development Company by its actions became a party to the written contract between Specialty Management Company and Consolidated Precast, Inc. Accordingly, they are bound by the arbitration clause contained therein and this arbitration has jurisdiction." (See S.C.O. record, Exhibit C Arbitrator's Award.) The arbitrator also held that SMC was not liable to CPI on the subcontract. The arbitrator denied CPI's claim against SMC for the remaining money owed under the contract and denied without prejudice SMC's crossclaim against S.C.O. because no award was made against SMC.

On January 20, 1993, S.C.O. filed an application to vacate arbitration award. S.C.O. has complied with the provisions of General Statutes 52-420(b) which requires that a motion to vacate an arbitration award be made within thirty days of receiving notice of the award. Although no transcript of the arbitration hearing was made, S.C.O. has filed a brief in support of its motion and a record of exhibits. On January 28, 1993, CPI filed an application to confirm the arbitration award CT Page 6236 in part and vacate in part1, accompanied by a memorandum of law. On March 1, 1993, CPI filed a motion in limine asking the court to preclude an evidentiary hearing regarding the arbitrability of this dispute and a memorandum of law in opposition to S.C.O.'s motion to vacate the arbitration award. Oral argument was heard before this court on March 3, 1993.

DISCUSSION

S.C.O. argues that an evidentiary hearing is always necessary when a subject matter jurisdiction dispute arises. S.C.O. states that it did not sign any agreement regarding arbitration with CPI; that it never signed a consent agreement to assign the contract between SMC and CPI; that it never signed the assignment form letter; and that the arbitrator exceeded his power in that the award is an irrational application of the law. S.C.O. argues that the arbitrator did not have subject matter jurisdiction to arbitrate this dispute because there was no agreement between S.C.O. and CPI. S.C.O. claims that since the arbitrator was without subject matter jurisdiction, this court is also without subject matter jurisdiction.

CPI argues that the arbitrator had subject matter jurisdiction over this dispute because S.C.O. accepted assignment of the subcontract and the agreement does not have to be signed by both parties to enforce an arbitration clause. CPI I also argues that the court's standard of review in this case is based on the arbitrator's decision, and is not de novo. Furthermore, CPI maintains that since S.C.O. is challenging the subject matter jurisdiction of the arbitrator and this court, S.C.O. has the burden of preserving a record of the arbitration hearing and the failure to do so should not allow S.C.O. to have another hearing concerning arbitrability.

CPI's remaining grounds to confirm the arbitration award are (1) that the court should follow the arbitrator's decision absent misconstruction by the arbitrator; (2) S.C.O. participated in the arbitration proceedings and has had a full and fair hearing on the merits; (3) S.C.O. failed to elect General Statutes 52-410 which would have allowed it to refuse to submit to arbitration and receive a court hearing instead; and (4) S.C.O. has received the benefit of CPI's work and has paid 90% of the contract price to CPI.

The arbitrator held that "S.C.O. Development Company by its CT Page 6237 actions became a party to the written contract between Specialty Management Company and Consolidated Precast, Inc." (See Record Exhibit C.)

"An assignment, like other agreements, may sometimes be implied from a transaction without express words. . . ." Williston on Contracts, 3rd. ed., p. 145.

An application to confirm or vacate an arbitration award "triggers special statutory proceedings that are not civil actions." Middletown v. Police Local, No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bic Pen Corporation v. Local No. 134
440 A.2d 774 (Supreme Court of Connecticut, 1981)
City of Middletown v. Police Local, No. 1361
445 A.2d 322 (Supreme Court of Connecticut, 1982)
American Universal Insurance v. DelGreco
530 A.2d 171 (Supreme Court of Connecticut, 1987)
Dugas v. Lumbermens Mutual Casualty Co.
540 A.2d 89 (Connecticut Appellate Court, 1988)
Cashman v. Sullivan & Donegan P.C.
578 A.2d 167 (Connecticut Appellate Court, 1990)
Bio-Polymers, Inc. v. D'Arrigo
579 A.2d 122 (Connecticut Appellate Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 6233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sco-development-v-consolidated-precast-no-cv-113293-jun-30-1993-connsuperct-1993.