Schwartz v. Cronan

30 La. 993
CourtSupreme Court of Louisiana
DecidedMay 15, 1878
DocketNo. 5964
StatusPublished

This text of 30 La. 993 (Schwartz v. Cronan) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schwartz v. Cronan, 30 La. 993 (La. 1878).

Opinion

The opinion of the court was delivered by

Marr, J.

This suit was brought to recover the balance of an account alleged to be due for materials furnished to Cronan, and used in the construction of St. Patrick’s Hall.

The petition charges that the St. Patrick’s Hall Association is indebted to Cronan under the contract with him in an amount exceeding plaintiff’s demand; and that plaintiff served on the association a duly certified statement of the materials furnished by him, and caused registry of the same to be made in the office of the recorder of mortgages. The prayer is for judgment against Cronan and the association, in solido, with lien and privilege on the building known as St. Patrick’s Hall, and the ground on which it stands.

Cronan admits that he purchased the materials, but denies that he is indebted for them; and he specially denies that plaintiff has any privilege or preference. The association pleads a general denial; and specially denies that plaintiff has any privilege as claimed by him.

Eosdick & Co., by intervention and third opppsition, claim to be paid by preference the balance of an order given by Cronan to them, on the tenth June, 187J, payable out of the money coming to him for work done and materials furnished for the building, alleged to have been accepted by the association, verbally, on the day of its date, payable [994]*994whenever Oronan should be entitled to the amount free from any privilege or lien claims against him on the funds.

To this petition Cronan and the association answered by general denial. Schwartz in his answer alleges that the order relied upon by intervenors has no legal existence; that it was given without valid consideration ; that it has not been accepted by the association ; and that intervenors ought not to be paid out of the money in the hands of the association in preference to him.

There was judgment in favor of Schwartz, against Cronan, for $301 38, and against the association for $500, with privilege on the funds in the hands of the association on the8th August, 1874, due to Cronan; and the residue in the hands of the association was reserved for ulterior adjudication. Eosdick & Co. and the association appealed separately; and Schwartz, in answer to the appeal, prays that the judgment may be so amended as to decree in his favor against the association the full amount of his demand, with lien and privilege on the funds belonging to Cronan, under his contract, in the hands of the association on the eighth August, 1874; and that “in other respects the judgment of the lower court be affirmed.”

The account sued on was sufficiently proven as against Cronan; and the order relied upon by intervenors was shown to have been given In settlement of a judgment in their favor, rendered against Cronan in January, 1874. This order was given to the attorneys of intervenors. It was presented by them to John Henderson, the vice-president, who represented and acted for the association in all that pertained to -the building of the hall. Henderson verbally accepted the order in the terms alleged, and it was left with him for payment; and he afterward made the two payments on account of it, as stated in the petition.

Cronan undertook to furnish certain iron work for the building, to put up the railing of the galleries, and to furnish mechanics to bolt and secure his cast iron work on Camp street, whatever that may have been, for the gross sum of $5070, without specification of the price of the sevei’al parts, except, so much for the east-iron work, and so much for the wrought-iron work. There was no agreement as to when any part of this work was to be commenced or completed, nor as to when or how the payment was to be made. His agreement, such as it was, was not registered in the office of the recorder of mortgages ; and, therefore, he was entitled to no privilege, and Schwartz could derive none from him by subrogation, or otherwise.

The privilege which the law grants to undertakers, workmen, and the furnishers of materials is, specifically, on the building and the lot of ground, not exceeding one acre, on which it is erected, R. C. C. 2772, 3249; and this is precisely the privilege which plaintiff asserted, and [995]*995¡sought to have enforced. We are relieved of the necessity of inquiring whether plaintiff had acquired and preserved this privilege in his owrt right, under articles 3249, 3272, of the R. 0. 0., because the judgment of •the district court did not allow him this privilege, but accorded him a privilege on the money due Oronan, in the hands of the association, on -the eighth August, 1874, the date at which plaintiffs claim seems to have been registered in the office of the recorder of mortgages, and at which he delivered a statement of his account to the president of the association. Plaintiff did not appeal from this judgment; and in his prayer for amendment of the judgment he asks that he may be •allowed the same privilege on the money for the whole amount, instead of for part only of his demand; and that the judgment appealed from ■be in other respects affirmed. This is an acquiescence in the judgment disallowing the specific privilege asserted and demanded in the petition ; and, while we incline to the opinion that he had no privilege on the 'building and lot of ground on which it is erected, we go no further ¡now than to say that we have no power to review the judgment in so 'far as it disallows that privilege, because plaintiff did not appeal; and ■because of his prayer for the affirmance of the entire judgment, excépt as to the amount allowed him against the association.

Cronan was not an undertaker, in the ordinary sense of the term. 'St. Patrick’s.Hall was not built by an undertaker of the entire work. The different parts were done by persons whose bids or offers were ■accepted; and Cronan’s bid for cast and wrought iron work to be used in the construction of the building, and for putting up the railings of the galleries, was accepted. In great part his undertaking was to furnish materials which those who constructed the building were to use •and put in place.

Schwartz did not deal with the association. He sold to Cronan, at different times, in April and May of 1874, sundry lots of old iron, principally cast iron, which was not in a condition to be used in the building. The testimony makes it quite uncertain as to what part of the iron sold by him to Cronan was used in the building; but so much of it as was applied to that purpose was melted at Cronan’s works, just as if it had been pig iron, and was cast into the shapes and patterns required in the ‘construction of the building. He is to be dealt with, therefore, as the furnisher of raw material to a manufacturer who wrought and fashioned it into the perfected material which he, the manufacturer, had undertaken to furnish to the owner, to be used in the construction of -the building.

Under the Code, the person who has contracted with the undertaker, ¡and not with the owner, of the building, has these remedies:

1. By art. 2770 of the R. C. C. masons, carpenters, and other work[996]*996men, those who, in the language of Troplong, have done un travail manueV in the construction of a building, may bring a direct action against the-owner, and may recover of him up to the amount which may be due by him to the undertaker at the time of the commencement of their action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baldwin v. Wood
11 La. 453 (Supreme Court of Louisiana, 1838)

Cite This Page — Counsel Stack

Bluebook (online)
30 La. 993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schwartz-v-cronan-la-1878.