Schultze v. Goodstein

81 N.Y.S. 946

This text of 81 N.Y.S. 946 (Schultze v. Goodstein) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schultze v. Goodstein, 81 N.Y.S. 946 (N.Y. Ct. App. 1903).

Opinions

HATCH, J.

This is an action brought to foreclose a mechanic’s lien filed by the assignee of the contractor, Manneschmidt. The contract provided for furnishing plumbing work upon premises owned by the defendant Goodstein. There was also a lien filed by the defendant Deng for materials furnished, and also by the Alberene Stone Company. Interest in the latter lien was assigned to Deng, and he was made a party defendant in the action. These two liens amounted to about the sum of $1,364, with interest thereon. No question is raised but that the materials represented by the liens owned by Deng were furnished to the building; that the defendant Goodstein received all the benefits arising therefrom; that the materials thus furnished answered in all respects to the requirements" of the contract; and that Deng has not been paid therefor. The issue litigated upon the trial related solely to the performance by the contractor of his contract; it being claimed that he did not substantially perform the same, but, on the contrary, was guilty of a willful and fraudulent departure from the plans and specifications to such an extent, and of so material a character that his assignee was not entitled to enforce the lien. The particulars in which it was claimed that there was substantial de[948]*948parture from the terms of the contract were that he had substituted earthen for iron sewer pipe; had failed to remove rock obstruction in the street, and thereby give a proper pitch to the sewer, which resulted in flooding the basement, and causing the same to become damp and unhealthy ; that he utilized old sewer connections connected with buildings formerly standing upon the land, which had been torn down to make place for the new building; that he substituted 1%-inch pipe for 2-inch pipe in the laundry tubs and sinks, and furnished a thinner and inferior pipe in the closet system. All of the material which was the subject of contest upon the trial was put into the building under the supervision and direction of an architect. After the completion of the plumbing work involving the disputed items, the. architect gave to the contractor a certificate that the work was completed in accordance with the terms of the contract, and that the contractor was entitled to payment therefor. Presumptively, therefore, the plaintiff was entitled to "enforce the lien which he had filed. He could only be defeated by establishing that the certificate which entitled him to payment therefor had been fraudulently obtained, and that the substitu-tians which had been made, or departures from the contract, were substantial, and were not authorized by or known to the architect at the time when he gave the certificate. Under this state of the case, the burden rested upon the defendant Goodstein to show fraud in obtaining the certificate which entitled the contractor to payment. This he sought to do by giving proof tending to show that the architect was not aware, when he delivered the certificate, that the changes had been made, and that the earthen pipe was put into the trench surreptitiously and hastily covered up before the architect had an opportunity to inspect the same. The architect testified that he had never authorized the particular departures complained of, and did not know at the time when the certificate was given that any such change had been made. In further support of the claim that the changes were substantial in character and worked damage to the defendant Good-stein, the latter and his son were called, and gave testimony tending to show that the sewer pipe, as laid, did not properly carry off the sewage; that it was forced back into the cellars of the building, and flooded the same, rendering them damp and uninhabitable for" the tenants and janitors in the building; that he was practically unable to keep a janitor, having had about twenty in eight months; that he had trouble over the entire house, and had expended at least $300 for temporary repairs to the plumbing. The testimony to show that earthen sewer pipe had been surreptitiously placed in the trench and hastily covered up came from a witness who was bitter in his hostility to the contractor, and whose testimony is very seriously shaken by reason thereof, and also in many respects by its inherent improbability. In effect, lie stated that the contractor deliberately and with fraudulent design brought upon the ground iron pipe and also earthen sewer pipe; that he concealed the latter, and, when there was no opportunity for inspection, put the same in the trench, and hastily covered it up. This testimony was met by a denial on the part of the contractor, who claimed and testified that, while he substituted earthen pipe for some of the sewer pipe leading from the building to the main sewer, the [949]*949reason therefor was because of an old sewer on the premises of iron pipe, which, when taken up, was found to be rusted to a mere shell, and the inside nearly filled with rust, this condition being due to the character of the soil; that, when this discovery was made, the architect directed the substitution of the earthen pipes, with a deduction to be made for the difference in price. He denied the surreptitious substitution of the earthen pipe, and testified that it was done openly, and was inspected before being covered up. Upon this subject he was corroborated by several of the workmen upon the premises and by the sewer inspector employed by the city, who testified that the sewers were open and- in process of construction for about two weeks; that there was no attempt to conceal the earthen pipe; that it was lying around on the top of the ground for that period, and was in the open sewers for some time, waiting for the inspector, who subsequently examined it and certified that it was properly laid. It is clearly seen, therefore, that the evidence on the part of the contractor tended to overthrow the testimony of the hostile witness, and upon this subject the proof preponderates in favor of the contractor that the tile sewer pipe was laid openly and without any attempt to conceal it from observation. This seems to be clearly established by the testimony of the inspector, who was in no respect contradicted, except by the hostile witness, and he does not say that the inspector did not examine it. In addition to this, it appears that while the defendant Goodstein and his son had given evidence tending to show that the basements were uninhabitable by reason of the overflow setting back from the sewer, and that the cellars were damp and wet, they were directly contradicted by' two janitors employed in the buildings, one of whom testified that he had been janitor for about six months; that he was acquainted with the janitors in all of the five, houses; that they had been there for four or five months, and that no janitor had been changed in the last few months; that there was no water overflow from the sewer, except once, when it was stopped up with a little grease in the pipe, and that caused a little water in the cellar. This janitor testified that he was a plumber, but that he had to do very little plumbing work about the apartments, and such as he did was limited to the putting in of a washer when it leaked; that twice in six months, by reason of grease getting into the pipes, there had been a little water, and that this was the only overflow he knew of, and he made no complaint to the defendant Goodstein. This was the janitor of No. 344. The janitor from No. 346-348 was called, and testified that he had been janitor for 5j4> months.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
81 N.Y.S. 946, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schultze-v-goodstein-nyappdiv-1903.